BUREAU OF FACILITIES, ARCHITECTURE DIVIS DEPARTMENT OF PUBLIC WORKS Demolition of the Cowley- Goettman Recreation Center Community Meeting #2 April 10, 2019
Mayor William Peduto Mike Gable, CPRP City of Pittsburgh Department of Public Works (DPW) Director Councilwoman Darlene Harris Pittsburgh’s 1st District Chris Hornstein, RLA DPW Assistant Director – Bureau of Molly Onufer Facilities Community Affairs Manager Casimir Pellegrini III, AIA Leah Friedman Senior Project Architect Community Liaison Andrea L. Ketzel, RLA Senior Project Landscape Architect Joe Adiutori, Jr., AIA Associate Project Manager Harvey Butts Associate Project Manager 3
1. INTRODUCTIONS 2. REVIEW BUILDING CONDITION & THE FACILITIES OPTIMIZATION PLAN 3. DISCUSS WHAT SHOULD BE SALVAGED FROM THE BUILDING 4. REVIEW DEMOLITION PROCESS 5. REVIEW COST ANALYSIS 6. Q&A 7. CONCLUSIONS Presentation Outline 4
Cowley-Goettman Recreation Center 5
6
7
8
9
10
11
12
13
Facilities Optimization Plan 14
15
16
Architectural Salvage – Stone Work 17
Architectural Salvage – Gym Flooring 18
Architectural Salvage – Building Signage 19
Architectural Salvage – Wall Mosaic 20
Misc. Salvage – Basketball Standards & Banner 21
Misc. Salvage – Warming Table & Billiard Table 22
Miscellaneous Salvage – Frigidaire Fridge 23
Miscellaneous Salvage – Westinghouse Fridge 24
1. Engineering (4 to 6 weeks); currently ongoing 2. Permitting & Termination (4 to 8 weeks) Will occur after the award, but prior to demolition. • Utilities to the building will be terminated. • 3. Building Demolition (12 to 18 weeks) The City will work with the community to minimize impact to park usage. • 4. Mitigation Efforts: Noise: Operation times to be specified in order to minimize disturbance. • Air Quality: Specify dust suppression & haul away all materials by contractors. Note: No • material processing (i.e. brick crushing) will be allowed on-site Pest Control: Building to be exterminated prior to demolition. • Safety: Temporary perimeter fence will be installed around the building. • Post-Demolition Improvements: Engineered Slope will be required & the installation of a • railing along the sidewalk. Demolition Process (4 to 6 months) 25
Demolition Engineering Proposal 26
27
28
Funding Sources 29
BUREAU OF FACILITIES, ARCHITECTURE DIVIS DEPARTMENT OF PUBLIC WORKS Question & Answer Session
Next Steps 31