cryogenic cavern in asian site
play

Cryogenic cavern in Asian site Conceptual design of the cryogenic - PowerPoint PPT Presentation

Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system Storage of helium inventory Cooling water for cryogenic system


  1. Cryogenic cavern in Asian site • Conceptual design of the cryogenic system • Layout of the cryogenic plant for site A & B • New layout of the cryogenic system • Storage of helium inventory • Cooling water for cryogenic system • Summary & Future Plan KEK K. Hosoyama

  2. Conceptual Design of Cryogenic System 1 SC 2 K Ref. 4 K Ref. Helium Gas Cooling Cavities Cold Box Cold Box Compressor Tower 2K 2K 4K Multi-transfer Line Multi-transfer Line Helium Gas Piping Cooling Water Piping There are many option of layout of main components: • 4K cold boxes will be installed in the large caverns at the end of access. • Compressor units will be installed in underground tunnel. Helium Gas surface ? Compressor underground ? Cooling Tower 2 K and 4 K Ref. Access Tunnel Cold Box Helium Gas 1 ~ 2 km Compressor SC Cavities ~ 5 MW x 2 units in Main Tunnel

  3. Conceptual Design of Cryogenic System 2 Cooling Tower Cooling Tower Access Tunnel Access Tunnel He Compressor He Compressor x 2 units x 2 units ~ 5 MW x 2 2K He Ref. x 2 units ~ 5 MW x 2 4 K He Ref. 2K He Ref. x 2 units Cryomodule Cryomodule Cryomodule Cryomodule 2.5 km 2.5 km 5 km 5 km Multi-transfer Line • 4K cold boxes will be installed in the large caverns at the end of access. • Two 2K cold boxes must be installed in the caverns at 5 km intervals and each 2K cold box supports cooling of ~2.5 km long cryogenic unit. • Long multi-transfer line must be installed in the main tunnel to connect 2K and 4K refrigerators. • We must carry in the 2K cold box and distribution box through main tunnel.

  4. Layout of Cryogenic Plants for Mountain Site-B • 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel • 4 K cold boxes & compressor units will be installed at the end of access tunnel 2.5 km 2.5 km 5 km 5 km 2.5 km 2.5 km 5 km 5 km 1.1 km 2.2 km 1.9 km 2.6 km 2 km 1.3 km 2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1 Zone 6 Zone 5 Zone 4 Zone 3 Zone 2 Zone 1 3.8 km 4.8 km 5.8 km 5.1 km 4.7 km 5.4 km 2K Ref. cold box ( + cold compressor) Comments : 4 K Ref. cold box 1) Long multi-transfer line must be installed in the main tunnel He Compressor 2) End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. Access Tunnel 3) Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel. 4) Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

  5. Layout of Cryogenic Plants for Mountain Site-A • 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel • 4 K cold boxes & compressor units will be installed at the end of access tunnel 2.5 km 5 km 5 km 2.5 km 2.5 km 5 km 5 km 2.5 km 0.7 km 0.2 km 0.2km 0.2km 1.3 km 1.6 km H = 50m H = 30 m H = 40m 2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1 Zone 5 Zone 9 Zone 8 Zone 7 Zone 6 Zone 4 Zone 3 Zone 2 Zone 1 1.9 km 4.1 km 4.1 km 4.2 km 2.0 km 2.0 km 5.0km 3.5 km 3.8 km 2K Ref. Cold box ( + cold compressor) Comments : 4.4 K Ref. cold box 1) Long multi-transfer line must be installed in the main tunnel He compressor unit 2) End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. Shaft 3) Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel. Access Tunnel 4) Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

  6. Cryogenic Cavern (old version) • The 4K ref. cold box can be installed in cavern prepared for assembling TBM • The size of the cold box will be limited by transportation on road from factory to the site Sub tunnel Main tunnel 18kW Helium ref. cold box / CERN LHC Access tunnel 4 K ref. cold box Cavern at the end of access tunnel: used for assembling Transportation of the cold box TBM for the tunnels

  7. Installation of Main Cryogenic Components • 4K cold box will be carried through the access tunnel to the cavern at the end of access tunnel. -- Enough cross section for transportation of 4K cold box and compressor unit! Problems: • 2K cold box must be carried in and out through the main tunnel. • 2K caverns must be constructed for installation of 2K and distribution boxes. • Multi-transfer line must be installed in the crowded main tunnel. Multi-transfer Line (between 4K and 2K cold boxes) Cryo-module Cold box for LHC 18 kW at 4.5K Ref. 7.2 m D 3.9 m 10.2 m D 4.1 m D 5.2 m Access tunnel Main tunnel Sub tunnel

  8. New Layout of Cryogenic Plant • To solve following problems: a) Installation of 2K cold through main tunnel b) Need the 2K cryogenic cavern and the long multi-transfer line. --- We decide to change the route of access tunnels to reach to the 2K cold boxes! New access tunnel plan: • Cryogenic caverns will be constructed at the end of the access tunnels at every 5 km intervals in the tunnel. • Main components of two cryogenic plants: compressor units, 4K refrigerator cold boxes, 2K cold boxes, distribution boxes, and multi-channel transfer line, will be installed in the cryogenic cavern.

  9. Concept of New Cryogenic Cavern Access tunnel 2K cold box Compressor 4K cold box Main tunnel Sub tunnel Access tunnel 8 m 30 m 56 m 20 m 20 m

  10. Detailed Structure of Cryogenic Cavern • Temporary size of the cryogenic cavern is given here as for starting point. • To decide the shape and size of cavern, we need the detailed design study of the main components and these layout in the cavern. • We must keep contact with cryogenic experts who designed, constructed and has long operation experience of similar system. • We need close collaboration with industry to carry out the design study. • In designing the cryogenic system we must care about the safety and maintenance. compressor unit x 2 4K cold box x 2 2K cold box x 2 2K distribution box ( 50,000 L ) liquid helium Dewar

  11. Helium Compressor Unit • The helium compressor is installed in far end of the cryogenic cavern • Location of the cavern is ~ 60 m away from the main tunnel to avoid the vibration 26 m Compressor + Motor 5 m x 1.9 m x 2 m H 6 m 12.5 m Helium compressor for18kW Helium Ref / CERN LHC

  12. 4K Ref. Cold Box for LHC Size of 4K cold box Linde 18kW@ 4.5K D4m x L18 m

  13. 4.5K + 1.8K Cold Box and Distribution Box for LHC

  14. Cold Compressor for LHC 1.8K Refrigerator Size of Impeller 104 115 165 251

  15. Storage of Helium Inventory ILC Cryogenic Systems Reference Design T.J. Peterson et al. CEC Vol. 53 • Required Liquid Helium ~ 650,000 L • Storage as gas: standard 100 m 3 gas storage tank (D3 m x L15 m) ~ 250 units • Storage as liquid: ~50,000 L liquid helium Dewar (D3 m x L10 m ) Vaporization loss: 50,000 L x 0.5%/day = 250 L / day ~10 L/hr Small refrigerator can be used as “Baby - Sitter”

  16. Conceptual Design of Water Cooling System Option Cooling Tower A Shaft for Cooling Tower Cooling Tower Cluster Access Tunnel ~ 100 m Compressor 4K cold box 1 ~ 2 km 1) Cooling tower at the entrance of access tunnel can support cooling of underground 2 cryogenic plants. 2) Cooling tower cluster can support cooling of ~ 8km long distributed heat load. The cooling water circulate in 900 mm in diameter pipe. 3) By installation of the cooling tower in the tunnel, we can eliminate heat exchanger which need to cut the head pressure. But we need large bore shaft. 4) By using the “thermo - siphon” of refrigerant we can reduce the pipe size.

  17. Extraction of heat from the tunnel (1/2) Plan A’ Plan A Circulation of water Underground Cooling Tower Latent Heat of Water 1) Use the specific heat 1) Eliminate the heat exchanger 37 o C 2) Large amount of mass flow 2) Need large dia. shaft Cooling 3) Large size and long length piping Tower 4) Heat exchanger to cut pressure 32 o C D H = 100 m ~150 m Heat Exchanger Shaft D H = 100 m ~150 m Access tunnel 37 o C 37 o C 37 o C 37 o C Specific Heat of Water Cooling Tower 42 o C 32 o C 32 o C 42 o C

  18. Conceptual Design of Underground Cooling Tower Surface 1 L / sec = 539 kcal / sec = 2253 kW 7 m 1 MJ = 0.44 L / sec = 1.6 m3 / hr Underground 10 m Cooling Tower ~100 m ~ 3 m 2 Fan 2 m 0.5 MW 5 MW 30 m2 60 m2 ~ 9 m 37 ℃ 5 MW Cooling Water 32 ℃ Supply Water ~ 8 m 3 / hr Cooling Tower

  19. Underground Cooling Tower Top view scale Cooling Cooling Cooling 5 m x 5 m 7 m 10 m Tower Tower Tower 5 m 21 m D 7 m D 7 m Side view D 10 m D 10 m Cooling Cooling Cooling 10 m 10 m Cooling 5 m Tower Tower Tower Tower 5 m 10 m

  20. Extraction of heat from the tunnel (1/2) Cooling Plan B Plan A Cooling Tower Tower Circulation of water Circulation of refrigerant Latent Heat of Water Condenser NH3, R410A, R32 1) Use the specific heat 37 o C 2) Large amount of mass flow 1) Use the vaporization heat 3) Large size piping 2) Small amount of mass flow Tc =32 o C 4) Heat exchanger to cut pressure 3) Small size piping 4) Eliminate 32 o C h1 the heat exchanger H = 100 m ~150 m Gas Liquid Heat Exchanger Latent Heat of Refrigerant 37 o C 37 o C 37 o C h3 At room temperature, the vapor pressure of water Pump is very low. h2 The capacity of heat flow Te = 35 o C 32 o C 42 o C is very small! Evaporator

Recommend


More recommend