CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. As on 18/01/2020 CLIENT INDIAN INSTITUTE OF MANAGEMENT - RANCHI
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Academic Block 01 (G+3+4), Admin Block (G+3+4) and Academic Block- 02 (G+2) Built up area : 29814sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Academic Block - 1 (G+3+4) 3 rd floor level slab completed and shuttering of Terrace slab is in progress.
Physical progress as on 18/01/2020 Academic Block - 1 (G+3+4) Part 02 2 nd floor level slab completed and shuttering of 3 rd floor level slab is in progress.
Admin Block (G+3+4) CLIENT INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Admin Block (Part 1) All works up to plinth level is completed, column casting up to First floor level is in progress.
Physical progress as on 18/01/2020 Admin Block – part 2 All works up to plinth level is completed, Shuttering of First floor slab is in progress.
Academic Block 2 (L+G+2) CLIENT INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Academic Block-2 (Part -01) Raft casting completed, column casting up to plinth level is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Director‘s residence (G+1) Built up area: 300 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2019 Director‘s residence (G+1) Structure Completed, Brick work and plaster is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Hostel Block (G+8)- 3 Wings Built up area : 18460 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Hostel Block (G+8) lower wing Structure completed up to 1 st floor, Shuttering of 2 nd floor slab is in progress.
Physical progress as on 18/01/2020 Hostel Block (G+8) Middle wing Structure up to plinth level is completed, 1 st floor level slab shuttering is in progress.
Physical progress as on 18/01/2020 Hostel Block (G+8) Upper wing Structure up to plinth level is completed, 1 st floor level slab shuttering is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Faculty Housing - 01 (S+10) Built up area: 4286 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Faculty Housing 01 Structure completed up to 1 st floor level, Shuttering of 2 nd floor slab is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Faculty Housing - 02 (S+10) Built up area : 4286 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Faculty Housing - 2 All works up to plinth level is completed, wall reinforcement binding is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Seminar hall (G+1) Built up area : 3300 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 SEMINAR HALL (G+1 ) Casting of First floor slab and balcony slab completed, brick work is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Dining Hall (G+1) Built up area : 2650 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical Progress as on 18/01/2020 Dining Hall (G+1) Structure up to 1 st floor is completed, Shuttering of 2 nd floor slab is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Community Centre (G+1) Built up area : 1750 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Community Centre (G+1) Casting of grade slab is in progress (95%), column casting up to First floor level is in progress.
Physical progress as on 18/01/2020 Service Block Casting of first floor slab is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Type A Housing (S+5) (10 Unit) Built up area : 2177 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Type A Housing (S+5) Casting of 3 rd floor slab is in progress, Block work of 1st floor is in progress.
CONSTRUCTION OF PERMANENT CAMPUS (PHASE I WORKS) OF IIM RANCHI, JHARKHAND. Type C housing (S+3) (12 Unit) Built up area : 1421.4 sqm INDIAN INSTITUTE OF MANAGEMENT - RANCHI
Physical progress as on 18/01/2020 Type C housing Casting of 3 rd floor slab is in progress, block work of 1st floor is in progress.
THANKING YOU CLIENT INDIAN INSTITUTE OF MANAGEMENT - RANCHI