Santiago Solar: Case Study of a Metropolitan Solar Plant Columbia University, September 2019 Confidential 2 Introducing AME AME is an infrastructure developer with a strong track record. Focus on Gas and LNG infrastructure, combined cycle


  1. Santiago Solar: Case Study of a Metropolitan Solar Plant Columbia University, September 2019

  2. Confidential 2 Introducing AME AME is an infrastructure developer with a strong track record. Focus on Gas and LNG infrastructure, combined cycle power plants, solar PV and CSP and wind Gas and LNG Solar PV generation technologies, and other innovative technologies in the energy infrastructure space including public transport mobility and energy services Co-owner with EDF of the 5 th largest generator in Chile. 1,200 MW in CCGTS and solar PV currently operating in Chile and Peru, together with a significant development pipeline of projects including CCGT and renewable technologies AME plans to balance its portfolio with 600 MW of additional renewable capacity by 2023 Wind e-nnovation

  3. Santiago Solar: Case Study of a Metropolitan Solar Plant AME

  4. Confidential 4 Santiago de Chile Population 6 million Energy consumption 20,000 GWh/y AME

  5. Confidential 5 Trade off – radiation vs transmission cost / risk Santiago has extremely high radiation by world standards, even if it is 20% lower than northern Chile AME

  6. Confidential 6 Trade off – radiation vs transmission cost / risk CMG por Bloque (Solo Solar) 120 Day time prices by injection node 100 80 CMg [USD/MWh] 60 Crucero - Solar 40 Diego de Almagro - Solar Quillota - Solar 20 0 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00 10,00 11,00 12,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 9,00 10,00 11,00 12,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00 2.017 2.018 2.019 AÑO - MES

  7. Confidential 7 Santiago Solar: A metropolitan solar project 45 km (27 miles) north of Santiago

  8. Confidential 8 Timeline AME

  9. Confidential 9 Santiago Solar site (pre-build) AME

  10. Confidential 10 Timeline AME

  11. Confidential 11 Til- til is an area of Santiago which has experienced significant levels of conflict between citizens and businesses in recent years AME

  12. Confidential 12 Meaningful and genuine dialogue with the community • Respectful and genuine consultation • Real changes made to project design to adjust to community concerns • Contributions designed to be relevant to the project and address real needs

  13. Confidential 13 Timeline AME

  14. Confidential 14 In the 2014 tender process, Santiago Solar presented the lowest adjudicated offer, winning with a price of US$79.88/ MWh. AME

  15. Confidential 15 Timeline AME

  16. Confidential 16 Santiago Solar site (pre-build) AME

  17. Confidential 17 Santiago Solar site (pre-build) AME

  18. Confidential 18 Santiago Solar site (pre-build) AME

  19. Confidential 19 145 ha reforested with native species (360 acres) 125 ha agricultural land improved (310 acres) AME

  20. Confidential 20 Timeline AME

  21. Confidential 21 Regulated client withdrawals real / projected 2010 - 2025 Real/Projected Withdrawal Objective Withdrawal Rate 160,0% 140,0% 120,0% 100,0% WITHDRAWAL % 80,0% 60,0% 40,0% 20,0% 0,0% 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 AME

  22. Marginal Prices in the SIC / SEN 2010 – 2019 100,0 150,0 200,0 250,0 300,0 50,0 - ene-10 abr-10 2010 jul-10 oct-10 ene-11 abr-11 2011 jul-11 oct-11 ene-12 abr-12 2012 jul-12 CMg Quillota 220 oct-12 ene-13 abr-13 2013 jul-13 oct-13 ene-14 CMg Crucero abr-14 2014 AME jul-14 oct-14 ene-15 abr-15 2015 jul-15 CMg Diego de Almagro oct-15 ene-16 abr-16 2016 jul-16 oct-16 ene-17 abr-17 2017 jul-17 oct-17 ene-18 abr-18 2018 jul-18 oct-18 ene-19 2019 abr-19 jul-19 Confidential 22

  23. Marginal Prices in the SIC / SEN 2010 – 2019 100,0 150,0 200,0 250,0 300,0 50,0 - ene-10 abr-10 2010 jul-10 oct-10 ene-11 abr-11 2011 jul-11 oct-11 ene-12 abr-12 2012 jul-12 CMg Quillota 220 oct-12 ene-13 abr-13 2013 jul-13 oct-13 ene-14 CMg Crucero abr-14 2014 AME jul-14 oct-14 ene-15 abr-15 2015 jul-15 CMg Diego de Almagro oct-15 ene-16 abr-16 2016 jul-16 oct-16 ene-17 abr-17 2017 jul-17 oct-17 ene-18 abr-18 2018 jul-18 oct-18 ene-19 2019 abr-19 jul-19 Confidential 23

  24. Confidential 24 Timeline AME

  25. Confidential 25 Timeline AME

  26. Confidential 26 Timeline AME

  27. Confidential 27 AME

  28. Confidential 28 FACTS & * 100 FIGURES * Based on average home consumption of 1.785 kWh /y (Obrecht, 2016) AME

  29. 29 Confidential Award winning approach Winner of the Association of Generators ’ “Good Practices Contest for a more Sustainable Electric Future, 2018 Women of theYear Award, 2017, Ministry of Energy Outstanding results in the Project Acceptance Index for large scale renewable energy projects, Ministry of Energy and Gernman GIZ Winner of Latin American Green Awards 2019 “ Oasification; Forest Solutions for Desertification ”

  30. Confidential 30 A few words about the greenhouse …