closure
play

Closure 2007-2013 Seminar Prague June 2015 Building blocks of the - PowerPoint PPT Presentation

Closure 2007-2013 Seminar Prague June 2015 Building blocks of the Seminar Changes and lessons learned compared to 2000-2006 Modifications of the closure guidelines Advanced phasing, non-functioning Revenue generating


  1. Closure 2007-2013 Seminar Prague June 2015

  2. Building blocks of the Seminar • Changes and lessons learned compared to 2000-2006 • Modifications of the closure guidelines • Advanced phasing, non-functioning • Revenue generating projects, State aid • FEI, Durability of operations • Monitoring of indicators • Irregularities, suspended operations, force majeure • Timing and closure documents • Calculation of final payments and flexibility • Closure of programmes with no succession programme in 2014-2020

  3. Closure 2007-2013 Changes and Lessons learned from 2000-2006 Modifications to the closure guidelines Andreas von Busch

  4. Major changes compared to Closure 2000-2006 (1) : in substance Final date of eligibility & deadline for submission of  closure documents fixed in the Regulation: no extension possible No individual closure of Cohesion Fund projects since CF  has been mainstreamed

  5. Major changes compared to Closure 2000-2006 (2): irregularities Disclosure of the annual total projected error rates and  residual risk rate for the programme at closure Reporting on withdrawn and recovered amounts, pending  recoveries and irrecoverable amounts, not only on recoveries No payment of irregularities at closure unless amounts are  irrecoverable and the MS requests the EU Budget to share the burden of the loss and Commission accepts A commitment will remain open for pending recoveries  Quarterly reporting to OLAF independent of the reporting on  irregularities under Cohesion policy rules

  6. Major changes compared to Closure 2000-2006 (3): form & procedure Final Implementation Report  following a template in annex XVIII of Commission regulation  one-step approach for admissibility and quality check of the Final  Implementation Report Specific reporting on FEI following 2011 amendment of  the General Regulation Electronic submission of closure documentation via SFC 2007 

  7. Most problematic issues at closure 2000-2006 Closure documents were prepared at the last moment  Insufficient number or late execution of checks  Incomplete documents and long " ping-pong " between the  Commission and the Member State to obtain additional information Disagreements with the Commission over the extent and  application of financial corrections Lack of overbooking results in net loss  Not enough staff allocated to closure 

  8. Closure Guidelines Interpretation of legal provisions Commission Decision • Discussion in COCOF in June-October 2012 • Adoption of the Closure Guidelines (CGL) by the Commission 20 March 2013 • 20 Closure Seminars covering 28 Member States • 6 Q&A uploaded in CIRCA; Aggregated version before summer • Modification of the General Regulation in December 2013 requires adjustment of the CGL • Council Conclusion of 18 December claims further flexibility to maximise use of existing commitments

  9. Modification of the General Regulation Regulation (EU) No 1297/2013 of 11 December 2013 amending Council Regulation (EC) No 1083/2006 modifies Art 77 and • extends the top-up for Member States that remained in a financial support mechanism at the date of the adoption of the modification • introduces by a new paragraph (12) a 10% flexibility at priority level at closure. • ‘ 12. By way of derogation from paragraph 10, the Union contribution through payments of the final balance for each priority axis shall not exceed, by more than 10 %, the maximum amount of assistance from the Funds for each priority axis as laid down in the decision of the Commission approving the operational programme. However, the Union contribution through payments of the final balance shall not exceed the public contribution declared and the maximum amount of assistance from each Fund to each operational programme as laid down in the decision of the Commission approving the operational programme. ’ ;

  10. European Council conclusion • European Council mandates in December the Commission to • "find solutions to maximise the use of commitments under the 2007-2013 MFF period and recognises the desirability of delivering long- term projects in the years ahead using the flexibility of the existing rules "

  11. Adaption of Closure Guidelines following Council Conclusions 2 main elements added to the modifications already discussed in EGESIF in October • The possibility to justify eligible expenditures for Financial Instruments operations by loans, guarantees or equity provided to final recipients up to the date of the submission of the closure documents as long as these can be covered by the closure declaration. • The simplification of phasing conditions to respond better to the technical requirements of implementation without compromising the audit trail.

  12. Adaption of Closure Guidelines to be explained in more detail in the relevant building block • Phasing : • Advanced phasing, non-functioning projects by Annick Villarosa (REGIO F1- Operational Efficiency) • FEI- extension for payments to final recepients: • Financial engineering instruments, Durability of operations (Art 57) by Carole Mancel-Blanchard (REGIO B4- Legal affairs) • Flexibility: • Calculation of final payments and flexibility by Carole Mancel- Blanchard (REGIO B4- Legal affairs)

  13. Closure 2007-2013 Advanced phasing, non-functioning projects Annick Villarosa

  14. Phasing (1) - Changes in the CGL OUT • 'ready to be used for its purpose' IN • 3 programming period phasing not possible • Productive investments can be phased

  15. Phasing (2) – Definition of phases  Two clearly identifiable stages (from a physical & financial point of view)  not possible to use only financial milestone (85% of costs, or 75% of construction or materials, etc.) for defining a phase  a phase should be auditable with regard to its physical object, allocated amounts and results achieved, meaning that it should demonstrate achievement of tangible targets. N.B. Failure to complete in 2014-2020 may trigger financial correction and possible irregularities under phase 2 may affect phase 1 (potential financial correction on both phases)

  16. Phasing (3) – Definition of phases Infrastructure projects – define phases based on outputs phasing based on bill of quantities  physical progress as acknowledged by the supervising  engineer purchase of raw material possible under both phases  R&D For staff costs clear cut-off date for salaries to fix for each phase Equipments in projects Pieces of equipment can be purchased under both phases IT projects (immaterial elements) Consider phasing: analysis, design, implementation, testing, roll-out

  17. Phasing (4) – Major Project amendment  Submit amendment request by 30 September 2015 .  Update the original application and take into account revised project details/timeline  update of documents or procedures may be needed (CBA, EIA, permits ).  Amended decision reaffirms overall objective of the major project, the scope of each phase and the corresponding financial allocation

  18. Phasing (5) – MP approval in 2014-2020  Conditions for applying simplified notification i.e. without Independent Quality Review for phase 2 (Article 103)  Phase 1 to be approved by 31/12/2015  Sum of total eligible costs of all phases above threshold (50 or 75 million € )  COM assessed all phases and no subtantial changes occured  Otherwise (Article 102): either notification or Commission's full assessment of phase 2 – just as a new MP  Project application of phase 2 should refer to both phases and also to the overall physical and financial objective.  In all cases, phase 2 to be included in the MP list of the programme

  19. Phasing (6) - Horizontal costs Certain costs cover both phases, but paid at the beginning of project implementation (in phase 1) i.e. before 12/12/2015 i.e. land purchase, insurance cost, project preparation – feasibility study, impact assessment, consultancy  Land purchase : up to 10% of the total eligible expenditure of phase 1 (threshold in General Regulation)  Insurance cost : eligible, but cannot be a phase 1 in itself  Project preparation (studies, EIA, etc.) : eligible, can even be a phase in itself, but consider possibility of a separate project (to avoid administration)

  20. Phasing (7) – Contractual advances Contractual advance payments are eligible if - Beneficiary paid before 31/12/2015, the invoice has been issued and corresponding work/service delivered - The compliance of the operation checked by closure ELIGIBLE ONLY IF national rules or contractual practices for a given type of work or service already allow for such payment modalities. When phased: A) Either ONE contract (or the contracts) cover both phases B) Or contracts are specific to each phase

  21. Phasing (8) – advances: contract covers both phases The amount of the advance to be matched by physical delivery (works, services) by closure Acceptable: Advance payment Phase 1 Phase 2 (remaining (i.e. € 5 million) (min. € 5 million) eligible costs) NOT acceptable: Phase 1 Advance payment Phase 2 ( € 2 (i.e. € 5 million) (remaining eligible costs) million)

Recommend


More recommend