city of billings w o 18 06
play

CITY OF BILLINGS W.O. 18-06 EBURD 10 TH TO 13 TH INFRASTRUCTURE - PowerPoint PPT Presentation

CITY OF BILLINGS W.O. 18-06 EBURD 10 TH TO 13 TH INFRASTRUCTURE IMPROVEMENTS 4th Ave North 4th Ave North North 9th Street 1st Ave North 1st Ave North Project Location Planned Improvements Public Utilities 1. Upsize storm drain and


  1. CITY OF BILLINGS W.O. 18-06 EBURD – 10 TH TO 13 TH INFRASTRUCTURE IMPROVEMENTS 4th Ave North 4th Ave North North 9th Street 1st Ave North 1st Ave North

  2. Project Location

  3. Planned Improvements Public Utilities 1. Upsize storm drain and install additional inlets – create more drainage capacity 2. Replace sewer mains (7 blocks) in alleys Private Utilities 1. MDU may replace gas mains in the project area

  4. Planned Improvements Streets & Sidewalks - Curb and gutter - Sidewalks/boulevards - Bulb-outs with ADA ramps at intersections - On-street parking - Bike lanes

  5. Street Configurations North 11th Street/North 12th Street

  6. Street Configurations 2nd Avenue North/3rd Avenue North Bike lanes for 2 nd Avenue North and 1. 3 rd Avenue North

  7. Planned Improvements Street Lighting - Ornamental street lighting throughout the EBURD - A total of 212 new street lights

  8. Street Lighting Map

  9. Before and After 2nd Avenue North – Looking West Toward North 11th Street

  10. Before and After North 12th Street – looking North Toward 4th Avenue North

Recommend


More recommend