citizens transportation advisory committee
play

Citizens Transportation Advisory Committee December 15, 2010 PROJECT - PowerPoint PPT Presentation

Citizens Transportation Advisory Committee December 15, 2010 PROJECT NEEDS & BENEFITS Provide direct connection from Port to Interstate Highways from I 395 via Watson Island Maintain Port as Countys second leading Economic


  1. Citizens’ Transportation Advisory Committee December 15, 2010

  2. PROJECT NEEDS & BENEFITS • Provide direct connection from Port to Interstate Highways from I ‐ 395 via Watson Island • Maintain Port as County’s second ‐ leading Economic Generator • Relieve congestion from Downtown Streets • Keep Port Competitive

  3. PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner VMS Operator Federal Support

  4. PUBLIC ‐ PRIVATE PARTNERSHIP ‐ P3 Contract Overview • Design ‐ Build ‐ Finance ‐ Operate ‐ Maintain Concession Agreement • 35 ‐ year contract between FDOT & MAT Concessionaire • Design and Construction period is 55 months • Operation and Maintenance period is the remaining 30+ years

  5. PUBLIC PRIVATE PARTNERSHIP – P3 Payments during O&M • Upon Tunnel opening, FDOT begins making availability payments adjusted yearly for inflation • Maximum Availability Payment $32.5M/yr • Payment is subject to reduction if Tunnel not operational during required hours • Contract includes ‘Handback’ requirements to ensure Tunnel is returned to FDOT in first ‐ class condition

  6. PUBLIC PRIVATE PARTNERSHIP – P3 FUNDING THE POMT Project Funding • FDOT contributing $457.5M • Miami ‐ Dade County contribution $357.5M • City of Miami contribution $50M • R/W donations (County & City) $50M • FDOT funding Tunnel Operations & Maintenance from statewide maintenance funds (about $200 million over 30 years)

  7. SCOPE OF WORK Shifting of EB MacArthur Cswy MacArthur Cswy Bridge Widening Twin tunnels under Government Cut Modification of Dodge Island Roadway System

  8. PROJECT STATUS: Watson Island • Construction of New Parrot Jungle Trail is 95% Complete • EB MacArthur Causeway has been shifted south to new alignment • Site Installation Permits for Support Operations under Bridge: • Water Treatment Plant • Concrete and Grout Batch Plant • Cooling and Power Systems • Mechanic Shop • Barge to Receive Spoils

  9. PROJECT STATUS: MacArthur Causeway & Bridge • Widening of MacArthur Bridge for Tunnel Traffic • Widening of the Median for Launching Pit – Tunnel Starting Point • Tunnel Support Operations located below Bridge

  10. PROJECT STATUS: Dodge Island • 60% Roadway Design Plans are under review process • Exploratory Geotechnical Borings performed and analyzed • Sub ‐ sea Ground Investigation performed in Channel • Construction began early in December 2010 • Ongoing Stakeholder Meetings with Cruise, Cargo & Port Reps

  11. TUNNEL BORING MACHINE • Tunnel Boring Machine (TBM) is currently being designed and fabricated in Germany. • 43’ diameter & +600 ft. long train • Expected Arrival is scheduled for May 2011 • EB Bore to begin September 2011 • Completion of WB Bore Spring 2013

  12. TUNNEL VERTICAL ALIGNMENT & SECTION • Tunnels are 3900 ft. long • +40 ft. under the Bottom of Channel • 5% Grade • Precast Lining Segments fabricated Off ‐ Site

  13. CONSTRUCTION SCHEDULE May 24, 2010 – Construction began on Watson Island December 2010 – Construction begins on Dodge Island Spring 2011 – Arrival of TBM in Miami Fall 2011 – Beginning of eastbound tunnel boring Spring 2012 – Completion of eastbound tunnel Spring 2013 – Completion of westbound tunnel Spring 2014 – Completion of Dodge Island roadway improvements May 15, 2014 – Grand opening of the Port of Miami Tunnel *THESE DATES ARE SUBJECT TO CHANGE BASED ON THE CONSTRUCTION SCHEDULE

  14. MAINTENANCE OF TRAFFIC (MOT) •Weekly MOT releases •Full ‐ time Communications Manager •Full ‐ time Traffic Manager •Full ‐ time Health & Safety Manager •Emergency Response vehicles •Live Cameras (Sunguide.org)

  15. TUNNEL RENDERING

  16. QUESTIONS? Visit www.portofmiamitunnel.com

Recommend


More recommend