central kit itchen upgrade
play

Central Kit itchen Upgrade December 17, 2018 Race to the Finish - PowerPoint PPT Presentation

Sequim School Dis istrict - Board Meeting Central Kit itchen Upgrade December 17, 2018 Race to the Finish December 17, 2018 1 Current Configuration / Option 3 Allows for more matching state funds 100% Code compliant


  1. Sequim School Dis istrict - Board Meeting Central Kit itchen Upgrade December 17, 2018 “Race to the Finish” December 17, 2018 1

  2. Current Configuration / Option 3 ➢ Allows for more matching state funds ➢ 100% Code compliant commercial kitchen ➢ Efficient work space ➢ Clears the area for new school ➢ Remains in budget December 17, 2018 2

  3. Kitchen Details ➢ 4080 SF ➢ New and modern kitchen equipment ➢ New freezer / cooler space and configuration ➢ New roof structure ➢ Designed for tie-in with future school construction December 17, 2018 3

  4. Schedule Overview SCHEDULE ➢ July / August – New kitchen area abatement and new kitchen construction began ➢ August / September - Full site structure deconstruction commenced ➢ November/December – Deconstruction complete – Site ready for new school structure ➢ January – New Kitchen to be completed December 17, 2018 4

  5. Deconstruction Progress …. Gone! December 17, 2018 5

  6. Construction Progress …. Moving Forward! December 17, 2018 6

  7. Challenges Overcome PROJECT CHALLENGES ➢ OPA portable classroom delivery /design / permitting / completion ➢ Wooden roof truss manufacturing backlog / delivery timelines ➢ Material / equipment spec’ing, ordering and delivery in very short timelines ➢ Extensive underground utility tunnels and concrete deconstruction ➢ Concealed asbestos piping December 17, 2018 7

  8. Schedule Update/ Status CURENT HIGHLIGHTS ➢ All abatement complete ➢ Old School 100% deconstructed ➢ New Kitchen is fully enclosed ➢ Interior electrical, mechanical, structural ongoing ➢ Mechanical and Kitchen equipment arriving daily. December 17, 2018 8

  9. Wrap Up ➢ OPA portable classrooms occupied. Final gym/ classroom fire alarm system procurement ongoing. ➢ All kitchen interior work ongoing ➢ Kitchen and mechanical equipment arriving on site ➢ Racing to January 2019 completion…no sacrifice on quality December 17, 2018 9

  10. A big Thank You to our Partners December 17, 2018 10

Recommend


More recommend