cbd community reference group meeting 15
play

CBD COMMUNITY REFERENCE GROUP MEETING 15 26 OCTOBER 2018 JOHN - PowerPoint PPT Presentation

CBD COMMUNITY REFERENCE GROUP MEETING 15 26 OCTOBER 2018 JOHN HOLLAND EARLY WORKS UPDATE TOWN HALL STATION TIMELINE EARLY WORKS KFC & PORT PHILLIP ARCADE DEMOLITION & NICHOLAS BUILDING WORKS Port Phillip Arcade Demolition


  1. CBD COMMUNITY REFERENCE GROUP MEETING 15 26 OCTOBER 2018

  2. JOHN HOLLAND EARLY WORKS UPDATE

  3. TOWN HALL STATION TIMELINE – EARLY WORKS

  4. KFC & PORT PHILLIP ARCADE DEMOLITION & NICHOLAS BUILDING WORKS Port Phillip Arcade Demolition • Ground slab removal underway Former KFC building Demolition • Works to separate the Nicholas Building from the former KFC building will be ongoing until late November • KFC demolition works ongoing until December Nicholas Building works • Internal works completed • Scaffolding in place around building, to be removed following completion of KFC demolition

  5. STATE LIBRARY STATION TIMELINE – EARLY WORKS

  6. FRANKLIN STREET & A’BECKETT STREET SHAFT UPDATE • A’Beckett Street shaft in final stage of handover to CYP, all John Holland facilities and materials now removed • Franklin Street shaft still being excavated with handover to CYP anticipated in late November

  7. FRANKLIN STREET & A’BECKETT STREET SHAFT UPDATE

  8. GROUNDWATER MONITORING UPDATE Completed works • Boreholes • Watermain relocation • Boring works and connection Underway • Drilling works to establish three new wells in the westbound lanes on Victoria Street • Investigate works for new wells in Franklin and Therry Streets • Trenching works in Bouverie Street to connect wells into system requiring occupation of kerbside carparks • Commissioning ground water monitoring system – until December

  9. QUESTIONS?

  10. CROSS YARRA PARTNERSHIP UPDATE

  11. AGENDA 1. Creative Program Update 2. Piling 3. State Library Station Update 4. Town Hall Station Update

  12. CREATIVE PROGRAM UPDATE

  13. METRO TUNNEL CREATIVE PROGRAM Presented by Mary Parker October 2018

  14. CULTURAL PROGRAM ACTIVITIES – COMPLETED • July 2018: Metro Tunnel Walking Tours for Open House • July 2018: Signed community partnership with Koorie Heritage Trust • July 2018: Partner of ‘ Blak Design Matters’ at KHT • August 2018: Creative Practitioner site visit to archaeology dig

  15. COLLINS ST – MELBOURNE FASHION WEEK

  16. CITY SQUARE – MOMA

  17. CITY SQUARE – RAILWAY

  18. SWANSTON ST – RMIT – JOSH MUIR

  19. CULTURAL PROGRAM ACTIVITIES – TO COME • Nov 2018: Tunnel / Vision as part of Melbourne Music Week • Dec 2018: Christmas in the city

  20. FED SQUARE HOARDINGS

  21. indicative

  22. ACOUSTIC SHEDS • Purpose to reduce noise and dust • Currently in place at Franklin and A’Beckett streets • Will be constructed in 2019 at City Square, Federation Square and Domain • Visual treatment options currently being explored with internal and external stakeholders • Visual options will be integrated with the hoardings

  23. 2019 – STORYTELLING (ALL INDICATIVE) • CBD South – Visit Victoria collaboration • CBD South – White Night participation • CBD South - Melbourne Fashion Week • CBD South - Melbourne Music Week – Tunnel Vision stage 2 • CBD South - Koorie Heritage Trust – walking tours for NAIDOC week • CBD South – Nicholas building tenant photo essay • CBD North – storytelling activation in Urban Square in collaboration with RMIT • CBD - Open House – stories of the past and the future • CBD – YIRRAMBOI – collaborative programming with City of Melbourne for City Square • Precinct wide: City of Literature collaboration – writers site visit to prompt concepts

  24. PILING

  25. PILING PROCESS • Piling is required prior to excavation to create a support structure to allow the safe excavation of the shafts

  26. PILING AT PARKVILLE

  27. PILING UPDATE – STATE LIBRARY Complete Commencing mid- November 2018 Commencing late Oct 2018 Commencement 2019 Complete Indicative

  28. PILING UPDATE – TOWN HALL STATION In Progress – 25% Commencement Q1 2019 Commencement Q1 2019

  29. STATE LIBRARY STATION UPDATE

  30. FRANKLIN STREET WEST Activity Involves Timing • Ongoing – November 2018 Set up construction shaft site and Pedestrian covered walkway installation, laydown area requiring Franklin Street southside footpath closure • Service investigations • Installing barriers • Ongoing – late October 2018 Piling platform and support works Piling rig delivery • Crane delivery • Late October 2018 – Q2 2019 Piling at shaft site Piling (72 piles) at approx. 35-45 m • Reinforcement deliveries • Concrete deliveries Indicative

  31. A’BECKETT STREET SITE Activity Involves Timing • 22 October – December 2018 Site establishment / handover Line-marking • Investigating underground services • Delivering site sheds, materials and equipment • Constructing a covered walkway over Stewart Street for workers • Installing hoarding, and barriers around the work sites • Removing and installing traffic signs • Material delivery Road header delivery Early-mid November • Excavation 24 hour excavation Ongoing Indicative

  32. A’BECKETT STREET TRAFFIC CHANGES • Daytime closures for Stewart Street • Stewart Street will open at night • In late November, following site establishment works, Stewart Street will re-open as a one-way street, running southbound direction. Indicative

  33. LITTLE LA TROBE STREET Activity Involves Timing • 29 October 2018 – February 2019 Demolition of three buildings Demolition • Changed traffic conditions in Little La Trobe and Literature Lane • Up to 30 minute closures of Literature Lane to allow for safe removal of material for Doki Doki demolition • February – June 2019 Using a small excavator and hand tools Archaeology to excavate the area • Further relocation works Service works in Literature Lane prior to Sewer relocations: January 2019 piling Gas proving: Mid-late November • Sewer relocations Gas relocation: Mid-2019 • Gas proving and relocation: Literature Lane traffic changes Indicative

  34. LITERATURE LANE – WORKS MAP Indicative

  35. LA TROBE STREET SITE Activity Involves Timing • Using a small excavator and hand tools Ongoing – November 2018 Archaeology to excavate the area • Driveways installed Driveway installation Completed • Tram stop shelter removal (awaiting Yarra Trams to remove) • Slab and basement demolition (ongoing) Ongoing – mid November 2018 Piling preparation • Intermittent footpath closures on La Trobe • Piling platform (crushed rock deliveries compaction) • Piling rig delivery Piling From mid November 2018 • Reinforcement deliveries • Concrete deliveries Indicative

  36. LA TROBE STREET – PILING Indicative

  37. TOWN HALL STATION UPDATE

  38. CITY SQUARE SITE UPDATE Activity Involves Timing • Material removal Using a conveyor to load trucks Ongoing • Some hammering may be required • Out of hours spoil removal required up to 7pm • Ongoing – February Piling Reinforcement deliveries • Piling works 2019 • Concrete deliveries • Collins Street civil Adjusting hoarding to install a new End November TBC works gate that accommodates larger vehicles • Utility relocations on the southern Collins Street footpath Indicative

  39. CITY SQUARE – OUT OF HOURS DELIVERIES Oversized deliveries are required at this time due to relevant traffic permits • Conveyor belt: Monday 29 October, 10pm – 6am • Piling rig mobilisation: Wednesday 7 – Friday 9 November, 10pm – 6am • Traffic changes: Flinders Lane will be closed between Swanston Street and Russell Street during these deliveries

  40. COLLINS STREET CIVIL WORKS What: • Creating a new crossover into the City Square site • Adjusting hoarding to install a new gate that accommodates larger vehicles • Relocating utilities on the southern Collins Street footpath When: • Nightworks (10pm – 5am), from late November for 3 weeks • Dayworks (7am – 6pm) and nightworks (10pm- 5am), from early January for 1 week TBC Traffic/Pedestrian changes: • Collins Street southern footpath and road closure during working hours TBC

  41. FLINDERS QUARTER UPDATE Activity Involves Timing • Ongoing – December Archaeology Using a small excavator and hand tools to excavate 2018 the area • Ongoing – December Demolition of Using jackhammers, archaeology excavators, and a tipper 2018 footings* truck to remove previous building footings • Ongoing – November Port Phillip Arcade Using jackhammers and basement excavators 2018 • demolition Removal of rubble (JHEW) • Ongoing – January 2019 Piling preparation Crushed rock deliveries • works Rock compaction • Perimeter cutting • Piling rig deliveries (nightworks) • Late January – August Piling Piling works • Reinforcement deliveries 2019 • Concrete deliveries Indicative

  42. SWANSTON AND FLINDERS STREETS – OUT OF HOURS WORKS What: • Removal and trimming of trees • Tram pole relocations • Gantry removal and installation • Footpath crossovers When: 8pm – 6am, Sunday to Thursday from 7th – 30th November 2018 Pedestrian changes: • Swanston Street western footpath closure between Young & Jackson and the Nicholas Building • Flinders Street footpath closure

Recommend


More recommend