cbd community reference group february 2019
play

CBD COMMUNITY REFERENCE GROUP FEBRUARY 2019 CROSS YARRA - PowerPoint PPT Presentation

CBD COMMUNITY REFERENCE GROUP FEBRUARY 2019 CROSS YARRA PARTNERSHIP We acknowledge the land on which the Metro Tunnel Project is being delivered, is the traditional land for the People of the Kulin Nation. We respect their spiritual beliefs


  1. CBD COMMUNITY REFERENCE GROUP – FEBRUARY 2019 CROSS YARRA PARTNERSHIP

  2. We acknowledge the land on which the Metro Tunnel Project is being delivered, is the traditional land for the People of the Kulin Nation. We respect their spiritual beliefs and acknowledge their ongoing connection with their Country. We would also like to pay our respect to Elders past, present and future. ACKNOWLEDGEMENT TO COUNTRY

  3. AGENDA 1. Bluestone recycling update 2. Town Hall Station update 3. State Library Station update 4. CBD Tunnelling 5. CBD truck numbers and routes 6. Town Hall Station waste strategy update

  4. BLUESTONE RECYCLING STRATEGY

  5. BLUESTONE RECYCLING UPDATE The Metro Tunnel Creative Program has found a use for three cubic metres of bluestone. • Melbourne Design Week: it will be used in an event that focuses on historic bluestone in Melbourne by two artists (note this program is not out yet) • Two other artists are interested in using the stone for another exhibition later in the year • Bluestone will also be used by artists for an exhibition scheduled for 2020

  6. BLUESTONE RECYCLING UPDATE The Creative Program also reached out to: • Yarra View Nursery – social enterprise nursery • Orchard Designs – small local business specialising in bluestone • Men’s Sheds Interest shown but specified difficulty how to store or use Other bluestone that has been removed as a part of the project (e.g. street kerbs etc) will be used in future legacy design

  7. TOWN HALL STATION UPDATE

  8. CITY SQUARE UPDATE

  9. CITY SQUARE – INTERNAL SITE WORKS Activity Involves Timing • Ongoing – late March 2019 Piling 55% piling complete • Ongoing concrete and cage deliveries, crane lifts • Capping beam construction/concreting Piling demobilisation – • Removal of piling rigs Late March TBC • Flinders Lane temporary 72hr closure night works • Delivery of 300T crane • April – August TBC Delivery and installation of prefabricated Deck construction steel to be installed and bolted together onsite • May – October TBC 20mt high Acoustic shed • Precast concrete cladding panels construction • Concrete slab removal, 25T excavator with hammer attachment - May TBC • Ongoing extended hours concrete and 7am to 10pm Monday to Out of hours works cage deliveries, crane lifts Friday, 7am to 4pm Saturday • Capping beam concreting 7am to 6pm Saturday 9 February

  10. CITY SQUARE – EXTERNAL WORKS Activity Involves Timing • Collins Street Modification of the footpath to allow for a February - March 2019 driveway into site footpath works • Relocating services – nightwork ongoing 4 - 18 February • Removal of hoarding, realignment of the footpath construction of driveway • Swanston Street Modification of the footpath to allow for a April TBC driveway into site footpath works • Location and methodology TBC

  11. FLINDERS QUARTER UPDATE

  12. FLINDERS QUARTER – INTERNAL SITE WORKS Activity Involves Timing • KFC Building – basement slab Ongoing – late March 2019 Demolition completion and footings • Port Phillip Arcade – suspended slab and basement slab • Piling preparation works – piling Ongoing – late 2019 Piling platform, material delivery and compaction • Piling rig delivery 1 March TBC • Piling to start 6 March TBC • Out of hours works Piling preparation works including February/March 2019 • 6pm to 10pm excavation, concrete pours and spoil removal.

  13. FLINDERS QUARTER – EXTERNAL SITE WORKS Activity Involves Timing • Swanston Street – dayworks Hoarding and February 2019 gantry modifications • Stabilisation Scott Alley and Cocker Alley Mid February works pending works • Utility diversion stakeholder • Fencing agreement 2019 • Excavation and spoil removal • Reinstatement • Hoarding placement • Out of hours Driveway installation works on Complete Flinders Quarter external site works Swanston Street – complete works • Flinders Street - Yarra Trams February 2019 to complete pole removal works and wiring works from 11 Feb

  14. FEDERATION SQUARE UPDATE

  15. FEDERATION SQUARE Activity Involves Timing • Ongoing – March 2019 Demolition Ongoing demolition of the former Melbourne Visitor Centre basement • Strutting support installation • Piling preparation Material delivery and compaction March 2019 • Piling rig delivery – 6 March TBC • Concrete and reinforcement March – July 2019 Piling deliveries • Piling works • Capping beam construction/concreting • Excavation to commence July – Late Nov TBC Excavation and • Deck installation to commence Deck/Shed • Shed construction to commence Construction

  16. GEOTECH UPDATE Groundwater well Recharge Testing installation • • What Installing four groundwater Recharge testing occurs at wells existing well locations • • Temporary worksites Connection to a water supply • Localised traffic and will need to be established • pedestrians changes Localised traffic and during works pedestrian changes during works • 7am – 6pm • When 24/7 for 1-2 weeks • 10pm – 6am For certain well locations, out Out of hours work is required in of hours work is required to order to complete the tests minimize disruption

  17. STATE LIBRARY STATION UPDATE

  18. FRANKLIN STREET EAST UPDATE Activity Involves Timing • Site Lifting staff facilities into December 2018 – February 2019 site (three levels) establishment • Scrubber install • Alimak install • Decking planks • Steel delivery for stairs and ramps • February – Roadheader delivery Excavation of • Lowering the shaft October 2019 shaft and adit • Excavating the adit Franklin Street West, with Franklin Street East Acoustic Shed under Swanston Street in the background, October 2018

  19. FRANKLIN STREET WEST UPDATE Activity Involves Timing • Ongoing – March Piling 50% complete at approx. 35-45 m 2019 • • 7am – 6pm Reinforcement and • 6pm – 10pm concrete delivers (concrete pouring)* *if required • March – June Excavation Capping beam works • Excavating 2 metres 2019 preparation • Building a deck • Excavating 30m below From June 2019 Excavation ground Franklin Street West, October 2018

  20. A’BECKETT STREET SITE UPDATE • Jane, the roadheader, has completed the top portion of the underground passenger connection (adit) for State Library Station • Jane has excavated more than 30 metres towards Swanston Street • The adit will be lowered five metres as the roadheader makes its way again towards Swanston Street as it A’Beckett Street Shed, January 2019 takes the first bench of the adit

  21. LITTLE LA TROBE STREET SITE UPDATE Activity Involves Timing • Ongoing – March Demolition of two Demolition buildings remaining 2019 • Changed traffic conditions in Little La Trobe and Literature Lane • Service Service works in From March 2019 Literature Lane and Little relocation La Trobe Street prior to works piling • April – June 2019 Using a small excavator Archaeology and hand tools to excavate the area 12 – 16 Little La Trobe Street, October 2018

  22. LITTLE LA TROBE STREET SITE UPDATE Little La Trobe and La Trobe Street site map

  23. LA TROBE STREET SITE UPDATE Activity Involves Timing • February 2019 – Piling preparation (crushed rock Piling (Stage 2) - deliveries) Q2 2020 perimeter • Piling rig delivery • Reinforcement deliveries • Concrete deliveries • Excavation Excavating down 37 metres for From February cavern access 2019 (Stage 1) • Service Stormwater, water main, low April 2019 for voltage, telecom relocations approx. 2 relocations on La • Various closures (e.g. slow lane, months La Trobe Street piling stage map Trobe Street fast lane, full) over two month period

  24. TUNNELLING

  25. GROUND CONDITIONS Ground conditions: • Fill, over • Colluvium of Quaternary age – Elizabeth Street Formation, over • Residual soil developed on the Melbourne Formation, over • Weathered bedrock – Melbourne Formation (Sud). • Melbourne Formation Levels 1 and 2 Melbourne formation

  26. Franklin Street West ground conditions

  27. La Trobe Street site ground conditions

  28. ROADHEADERS AND TBMS Jane, the Roadheader Tunnel Boring Machine A’Beckett Street Shed, January 2019 Example of tunnel boring machine tunnelling

  29. WHY WE’RE USING ROADHEADERS FOR CAVERN EXCAVATION Town Hall Station Concept Image State Library Station Concept Image

  30. TUNNELLING Roadheaders • November 2018 - tunnelling in the CBD commenced with roaderheader #1 ‘Jane’ • 2019 - additional roadheaders 4 Tunnel Boring Machines (TBMs) • 2 start in the West section and head further West then towards the CBD • 2 start in the East section and head further East then towards the CBD

  31. TBM INDICATIVE TIMELINE 2019/20 West TBMs • Early 2019 - delivery to site in North Melbourne for assembly • Mid 2019 - launch from North Melbourne towards Kensington • Late 2019 - arrive Kensington for retrieval then launch from North Melbourne towards Parkville • 2020 – arrival at Parkville then towards CBD East TBMs • Mid 2019 – delivery to site in Domain for assembly • Late 2019 - launch from Domain towards South Yarra • Mid 2020 – arrival at South Yarra for retrieval then launch from Domain towards CBD