building johnson county government s largest project
play

Building Johnson County Governments Largest Project Tomahawk Creek - PowerPoint PPT Presentation

Building Johnson County Governments Largest Project Tomahawk Creek Wastewater Treatment Facility Why Wastewater Treatment 2 About JCW Located in northeast Kansas Established in 1945 Enterprise funded 220 employees 6


  1. Building Johnson County Government’s Largest Project – Tomahawk Creek Wastewater Treatment Facility

  2. Why Wastewater Treatment 2

  3. About JCW • Located in northeast Kansas • Established in 1945 • Enterprise funded • 220 employees • 6 WWTFs • 32 pump stations • 2,200 miles of sewer • 500,000+ residents served • 60 million gallons treated each day

  4. About Tomahawk Creek WWTF • Leawood. Mission Rd and Lee Blvd • Established in 1955 • Trickling Filter Facility • 1980s Linking Interceptor • 7 mgd onsite/10 mgd to KCMO • 150,000 – 190,000 residents

  5. Blue River Basin Kansas Missouri

  6. Drivers for Upgrade • Age of equipment • New regulations for water quality • Increasing operational costs

  7. Planning Process • Previous Studies 2006 and 2013 – Evaluated 8 Alternatives – Evaluated 0 MGD, 10 MGD, and 19 MGD – Recommend 19 MGD Option • Project Definition Phase 2014-2015 • Design and GMP Development 2017 – 2018 • Construction 2018 - current

  8. Missouri River Load Reductions Relative to Existing Condition Baseline 9

  9. Financial Evaluation of Options No Flow Some Flow All flow

  10. Operating Cost Comparison Reduced Costs: $453 Million

  11. Goals for Long-Term Investment • Preserve high quality of life • Improve water quality • Provide the most cost- effective long-term solutions for customers

  12. Existing Tomahawk Creek WWTF

  13. Preliminary Design Concept • Reuse Influent Pumping Station and Digester Complex • IFAS BNR Basins & Blower Building • Separate Sludge Processing • Dual Purpose Compressible Media Filters • Disinfection and Reaeration Facilities • Concrete Lined Excess Flow Holding Lagoon

  14. Dual Purpose Compressible Media Filters

  15. Tomahawk Creek Proposed Delivery Methods

  16. Why CMAR for this Project • Collaboration between All parties • Signiant Pre-design already completed • High risk, complicated project • Earlier cost certainty • Optimize design

  17. Tomahawk Creek Proposed CMAR Schedule

  18. Value Engineering led to Design Evolution

  19. Evolution of the Site April 2017 July 2017

  20. Facility Protection Without Flood Rise

  21. Bedrock is at Different Elevations at Site Rock Fill Only Piers Only Piers with Rock Fill

  22. Power Limitations were Addressed

  23. BIM / VR Tools were Utilized for Project

  24. Bluebeam was Used to Review Documents

  25. VE Analysis Continues during Construction

  26. Construction Statistics 250,000 CY of Earth to Move • 53,000 CY of Structural Concrete • 3 Miles of Electrical Ductbank • • 110,000 LF of Pipe (Above & Below Grade)

  27. Plant Flow Diagram

  28. Startup Process Overview

  29. BNR Basin & Basin Blower Building

  30. Filter Disinfection Complex

  31. Solids Processing Building

  32. Administration Building

  33. Construction Challenges • 2018 & 2019 - Wettest Water Calendar Year in Kansas (57.88 inches) • Adjusting to COVID-19 Procedures • Tight Construction Footprint • Unforeseen Rubbish During Excavations

  34. Project Successes MOPO: Collection System Diversion Evergy Substation Energized

  35. Facility Startup Coordination Meetings w/ Key • Personnel Energization & LOTO Plan • System Startup Plans • • Key Construction Milestones

  36. Lessons Learned • Know your site and existing facilities • Exploratory digging • SCADA Screen Development – Big project – a lot to take on at once • Engage CMAR early • Communication, Trust, Teamwork

  37. For Updates: www.jcwtomahawk.com

  38. Exp xpec ectation ions

Recommend


More recommend