BREWER ROAD BACKBONE EXTENSION PROGRAM
Introductions Scott Miller, Director Division 3 Gary King, Engineering Manager Doug Hobbs, Project Manager Shannon Matteoni, Business Development Coordinator
Why are we having this meeting • Provide background of the BEP program • Inform the residents of Phase 2 that we are bidding the project with the intent to construct • Clarify any concerns of the potential future construction • Request emails addresses to provide communication as we begin construction • Resolve any issues or concerns for the construction phase • Discuss any restoration concerns
Backbone Extension Program • Extend waterline for needs of the District • Extend waterlines into areas currently not served by the District • Provide treated water in areas that are needing water – District’s Strategic Goal #1
Alta Sierra to Lake of the Pines • Provides connection between Loma Rica and the Lake of the Pines system • Indicated as an area of need for water service • Project is part of District’s Goal #1 to extend waterlines for water service
E. Hacienda and Pioneer (Phase 1) • E. Hacienda section had 32 out of 35 homes signed up for water • Fire Hydrants installed approximately every 700 feet • Project complete and residents have water
Brewer Road (Phase 2) • 2015 Proposed Backbone Extension Project • Upper section replaces an existing six inch line and provides necessary hydraulics • Lower section is construction of new pipeline that will be available to future residential connections • New fire hydrants
Phase 3 and Phase 4 • 2016 and 2017 Phases of this Backbone Extension Program • Final connection between the two systems • Available for future connections by residents • Fire Hydrants
Future Meetings • Prior to construction, we will offer any resident to join us during the videotaping of the construction area and to meet the contractor • During construction, District staff will be handling construction management of the project • At the end of construction, we will walk the roadway with any interested residents to create a completion list for the project • After construction, we will summarize costs and meters can be set upon payment of fees
Pavement Restoration
Question or Concerns