A Presentation to the Board of County Commissioners (BOCC) January 2015
Work Session Objective Kick-off the Eastside Terminal Environmental Assessment Discuss schedule, milestones and process Outline the proposed community involvement process
Project Background Master Plan recommended updates to the Eastside due to: Terminal Area and Eastside deficiencies Apron issues Operational issues Roadway/connectivity issues Master Plan described solutions to these issues The Environmental Assessment will analyze the potential environmental impacts
Proposed Action – Eastside Redevelopment Terminal Area Re-development, including new terminal building, transit center and ancillary auto parking, roadway improvements, apron improvements, FBO relocation, noise wall and other ancillary projects Will not change the classification of the airport Will not change type of aircraft operating at the airport Forecast of aircraft operations will be the same with or without project
Proposed Action – Eastside Redevelopment
Purpose of this Environmental Assessment (EA) The National Environmental Policy Act (NEPA) requires consideration of the environmental consequences of a federal action before the action is taken An Environmental Assessment is prepared to determine if an environmental impact may occur in any of the NEPA defined categories Provides an in-depth review of the potential environmental impacts for the proposed action and alternatives to those actions Provides disclosure of the alternatives, potential impacts and potential mitigation to the public and decision makers
Environmental Assessment Content The Environmental Assessment will consist of the following key chapters: Purpose and Need Alternatives — Including the Proposed Action Affected Environment Potential Environmental Consequences of the Proposed Action and the Feasible and Prudent Alternatives Potential Mitigation Measures
Environmental Considerations Categories to Evaluate Per FAA Order 1050.1E Include: Air Quality/Climate Historical, Architectural, Archeological, and Cultural Costal Resources Resources Compatible Land Use Light Emissions and Visual Impacts Construction Impacts Natural Resources and Energy Cumulative Impacts Supply Department of Transportation Act: Noise Section 4(f) Secondary (Induced) Impacts Farmlands Socioeconomics Impacts, Fish, Wildlife, and Plants Environmental Justice , and Children’s Floodplains Environmental Health and Safety Risks Hazardous Materials, Pollution Wetlands Prevention, and Solid Waste Water Quality Wild and Scenic Rivers
Responsible Parties John Kinney/Airport Director Aspen/Pitkin County Airport – (970) 429-2851 Ryk Dunkelberg/Project Director Mead & Hunt – (918) 586-7272 Kate Andrus/Project Manager Mead & Hunt – (303) 825-8852
Project Schedule
Unique Project Elements Extensive Community/Public Workshops Public Workshops, Coffee Chats/Small Group Meetings, Social Media Outreach Extensive Community Input Committee Involvement Detailed working sessions with the committee Extensive Visioning/Design Concept Process Maximum Allowable Architecture and Engineering Design, 25%
Next Steps Consider list of members for the Community Input Committee February 10 th work session to finalize committee list Team Kick-off to finalize first meetings Schedule Visioning Session and first Community Input Committee Meeting (Tentative Date: February 24 th )
Thank You! January 2015
Recommend
More recommend