ANACOSTIA RECREATION CENTER AT KETCHAM ANC 8A UPDATE July 7, 2020 ANACOSTIA / KETCHAM REC CENTER 1
PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT OVERVIEW 2
PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT OVERVIEW 3
PROJECT GOALS • Communication • Safety and Staffing • Connection to Community • Positive Addition to Neighborhood • Improved Outdoor Spaces • Improved Traffic / Parking • Flexibility & Durability ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT GOALS 4
PROJECT INTRODUCTION • PROJECT BUDGET : • $15M • PROJECT SCOPE : • New Stand Alone Facility (10-12,000 SF) • Gymnasium • Fitness Center • Demonstration Kitchen • Technology Lounge • Classrooms • Spaces for Multigenerational Programming / Workforce Development • Exterior Upgrades • Multi-functional playing field equipped with a new irrigation system • New running / walking track • Basketball court • Playground and Splash Pad • Parking for both school and new facility • Lighting and Security ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT INTRODUCTION 5
MILESTONE SCHEDULE • ANC8A Update July 7, 2020 • Online Survey Aug – Sep 2020 • Community Meeting to Introduce Architect Sep – Oct 2020 • Project Design Phase Fall 2020 – Summer 2021 • Construction Documents, Permitting Summer – Fall 2021 • Construction Kickoff Winter 2021 • Construction Completion Winter 2022 * Schedule subject to change pending weather, unforeseen conditions, etc. ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 MILESTONE SCHEDULE 6
NEXT STEPS • This presentation will be placed on the project website for reference: www.dgs.dc.gov/page/anacostia-recreation-center-new-construction (or simply do a web search for “DGS Ketcham Recreation Center”). • DPR will be issuing community survey to collect programming information. • To be included on our distribution list, please send an email to Brent Sisco at brent.sisco@dc.gov ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 NEXT STEPS 7
POINTS OF CONTACT Brent Sisco Capital Projects Officer DC Department of Parks and Recreation brent.sisco@dc.gov 202.615.9824 David Wooden Landscape Architect DC Department of Parks and Recreation david.wooden1@dc.gov Project Website: https://dgs.dc.gov/page/anacostia-recreation-center-new-construction ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 POINTS OF CONTACT 8