aei team 2013 02
play

AEI Team 2013-02 3 April 2013 - PowerPoint PPT Presentation

AEI Team 2013-02 3 April 2013 http://content.asce.org/studentcompetition/index.html Brian LaChance | Mike Palmer | Rachel Barrow Alex Byard | Melanie Fonner Brad Frederick | Pat Allen Competition Challenge N N N Project Background


  1. AEI Team 2013-02 3 April 2013 http://content.asce.org/studentcompetition/index.html Brian LaChance | Mike Palmer | Rachel Barrow Alex Byard | Melanie Fonner Brad Frederick | Pat Allen

  2. Competition Challenge N N N Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Project Background

  3. Reading School District PA Average- $14,535 Reading- $12,989 openpagov.org https://www.google.com/imghp?hl=en&tab=wi https://www.google.com/imghp?hl=en&tab=wi Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Project Background

  4. Delivery Method CM Agent with Multiple Primes Design/Build https://www.google.com/imghp?hl=en&tab=wi Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Project Background

  5. Goals Owner Core Values Nexus Goals Safety & Security Integration Reduce, Reuse, Recover Lifecycle & Maintenance Learning Tool Cost Effective Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Goals

  6. BIM Execution Plan Structural Engineering Mechanical Engineering Lighting/Electrical Engineering Construction Management Integration Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation BIM Execution Plan

  7. Collaborative Progression www.integraspec.ie www.konvekta.com Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation BIM Execution Plan

  8. Collaborative Progression N Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation BIM Execution Plan

  9. Site Plan Pool Congregation Area Bus Lane Parking Relocation N New Main Entrance N Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Site Plan

  10. Main Entrance N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  11. Entry Walkthrough N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  12. Second Floor Lobby N N Second Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  13. Multipurpose Room N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  14. Pool N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  15. Classroom N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  16. Classroom N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  17. Classroom N N First Floor Plan Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  18. Constructability Structural Steel Members Member (ft) (lbs) Type 60DLH18 84 1512 Pool roof truss 40LH15 60 900 Gym roof truss W18X46 42 1932 Typical floor beam W24x68 42 2856 Largest girder W18X35 35 1225 Typical east wing floor beam W18X40 42 1680 Typical roof beam W12X87 42 3654 Typical column HSS6X6X1/2 20.5 718 Typical brace member N Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  19. Safety • Traffic Baluster Nexus' School Security and Occupant Safety Checklist Traffic Direction Level of Integration Significant Acceptable Park Street Secure Main Entrance √ Safe Main Entrance √ Pool Alternative Parking Lot Balusters √ Public Address System √ 13 th Street . . . Security Alarms √ . . . . . . . Intrusion Detection System √ . . Lockdown Security Doors √ 3 Story Elementary Laydown Area Manual Window Shades √ Video Surveillance √ First Floor Bullet-Resistant Glass √ N N Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Building Analysis

  20. Site Logistics Park Street Pool Alternative 13 th Street 3 Story Elementary N Zone 1 Excavation - 6/16/14 to 7/18/14 Zone 2 Zone 3 Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Site Logistics

  21. Site Logistics Park Street Pool Alternative 13 th Street 3 Story Elementary Laydown Area N Zone 1 Superstructure Erection - 8/29/14 to 1/23/15 Zone 2 Zone 3 Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Site Logistics

  22. Schedule Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Schedule

  23. Schedule Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Schedule

  24. Navisworks Project Background Goals BIM Execution Plan Site Plan Building Analysis Site Logistics Schedule Cost Estimate Sustainability Analysis Conclusion Supporting Documentation Schedule

Recommend


More recommend