a sustainable solution replacing an active and
play

A sustainable solution replacing an active and inefficient Dual - PowerPoint PPT Presentation

A sustainable solution replacing an active and inefficient Dual Phase Extraction System Joyce Cruz - Project Geologist joyce.cruz@ch2m.com Joo Marcellino Project Manager joao.marcellino@ch2m.com Olivier Maurer Senior


  1. A sustainable solution replacing an active and inefficient Dual Phase Extraction System Joyce Cruz - Project Geologist – joyce.cruz@ch2m.com João Marcellino – Project Manager – joao.marcellino@ch2m.com Olivier Maurer – Senior Technologist – olivier.maurer@ch2m.com Christian Nogueira – Senior Reviewer – christian.nogueira@ch2m.com Renata Moura – Petrom Contract Manager - renata.moura@petrom.com.br

  2. Schedule • Introduction • NAPL distribution model • Conceptual approach • Construction • Conclusions 2

  3. A sustainable solution replacing an active and inefficient Dual Phase Extraction System 3

  4. Introduction We ¡will ¡present ¡the ¡main ¡steps ¡of ¡a ¡Permeable ¡Adsorp5ve ¡Barrier ¡system ¡at ¡the ¡ a ¡chemical ¡facility ¡near ¡São ¡Paulo ¡Brazil ¡(Petrom, ¡Mogi ¡das ¡Cruzes). ¡: ¡ -­‑ to ¡design ¡ -­‑ construct, ¡ ¡ -­‑ and ¡operate ¡ • Dual-­‑Phase ¡ Extrac5on ¡ System ¡ in ¡ opera5on ¡ since ¡ 2007 ¡ to ¡ treat ¡ LNAPL, ¡ not ¡ sufficient ¡enough ¡and ¡not ¡sustainable. ¡ ¡ ¡ • APer ¡revising ¡the ¡Site ¡Conceptual ¡Model ¡(CSM) ¡a ¡Passive ¡Barrier ¡System ¡was ¡ viewed ¡as ¡a ¡more ¡sustainable ¡solu5on ¡to ¡prevent ¡poten5al ¡light ¡non-­‑aqueous ¡ phase ¡ liquid ¡ (LNAPL) ¡ (di(2-­‑ethylhexyl)phthalate ¡ (DEHP) ¡ and ¡ di-­‑n-­‑butyl ¡ phthalate ¡ (DBP)) ¡ from ¡ entering ¡ a ¡ channelized ¡ water ¡ stream ¡ crossing ¡ the ¡ facility, ¡the ¡main ¡environmental ¡receptor. ¡ ¡ 4

  5. Localization The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again. 5

  6. New Conceptual Site Model (CSM) • Provided the necessary support for the technical team to propose a modification on the remedial approach to CETESB, with the replacement of the existing MPE system for a permeable reactive barrier (PAB wall). Main receptor of concern, not yet impacted. Lost on MPE System efficiency Significant long term expenditures, without knowing the closure plan Company was looking for a consulting firm with exp. on Sustainable Remediation 6

  7. Petrom Study Case • 2013 – first steps, select a more sustainable solution and gain support from authorities Review and revision of existing conceptual site model (CSM) and Human Health Risk Assessment, – Presentation to CETESB of new remedial concept and approval – • 2014 – Barrier Construction • 2015 – Cetesb presentation Suggested that the free product plume was relatively stable with low mobility • 2015 – Dual system evaluation Narrow Valley NAPL containing di(2- ethylhexyl)phthalate (DEHP) and di-n-butyl phthalate (DBP) 7

  8. MPE System Loss of Efficiency � Product removed from1999 to sept/2006: 54.717L � Clear lost on efficiency � Heavy O&M scope, costs and energy consumption Volume of Extract Product 4500 12000 4000 10000 3500 Acumulated(Liters) Volume (Liters) 3000 8000 2500 6000 2000 1500 4000 1000 2000 500 0 0 8

  9. NAPL Distribution Model Presentation Title 9

  10. Bis[2-ethylhexyl]phtalate Soil Plume Barrier Wall Figure 1 Bis [2-ethylhexyl] phthalate Soil Plume 10 Petrom Mogi Das Cruzes, Brazil

  11. 0,1 % NAPL Saturation Plume Barrier Wall Culverted Stream Figure 2a 0.1% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil 11

  12. 0,5 % NAPL Saturation Plume Barrier Wall Figure 2b 0.5% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil 12

  13. 1,0 % NAPL Saturation Plume Barrier Wall Figure 2c 13 1.0% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil

  14. 2,0 % NAPL Saturation Plume Barrier Wall Figure 2d 2.0% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil 14

  15. Conceptual Approach Presentation Title 15

  16. New Remedial System (PAB) • Passive Adsorptive Barrier, using the natural GW flow to protect the primary receptor as well as collecting the free phase and treating the dissolved phase Added collection trench associated with 2 sumps and skimmers PMs to monitor and control the system performance 16

  17. Construction Presentation Title 17

  18. The Barrier System • 4 ¡main ¡components: ¡ 1. LNAPL ¡interceptor ¡and ¡a ¡recovery ¡trench; ¡ 2. Situated ¡immediately ¡upgradient ¡of ¡the ¡PAB; ¡ 3. Cement-­‑bentonite ¡(CB) ¡slurry ¡wall ¡sec5ons; ¡ ¡ 4. Sumps ¡ to ¡ recover ¡ and ¡ prevent ¡ LNAPL ¡ from ¡ accumula5ng ¡ at ¡ the ¡ upgradient ¡ faces ¡of ¡both ¡wall ¡sec5ons. ¡ • Design: ¡ – Based ¡on ¡nature ¡and ¡es5mated ¡quan55es ¡of ¡LNAPL ¡ ¡ – Three ¡key ¡issues ¡: ¡ ¡ 1. ¡Preven5ng ¡migra5on ¡of ¡the ¡LNAPL ¡through ¡the ¡PAB ¡wall; ¡ ¡ 2. ¡Clogging ¡of ¡the ¡PAB ¡wall ¡by ¡LNAPL; ¡and, ¡ 3. ¡Preven5ng ¡migra5on ¡of ¡dissolved ¡COCs ¡through ¡the ¡PAB ¡wall. ¡ ¡ 18

  19. Layout 19

  20. Cement-bentonite Barrier • Two ¡cement-­‑bentonite ¡barriers ¡were ¡built ¡in ¡order ¡to ¡drive ¡groundwater ¡flow ¡ to ¡the ¡Drainage ¡Barriers ¡to ¡the ¡Adsorp5ve ¡Permeable ¡Sec5on; ¡ • First ¡ barrier: ¡ 68 ¡ meters ¡ in ¡ length, ¡ depth ¡ of ¡ 4 ¡ meters ¡ and ¡ average ¡ width ¡ of ¡ 0.70 ¡meters; ¡ • Second ¡barrier: ¡25 ¡meters ¡long, ¡depth ¡of ¡4 ¡meters ¡and ¡0.70 ¡meters ¡width; ¡ • Preven5ng ¡that ¡the ¡supernatant ¡free ¡phase ¡contact ¡the ¡Tributary ¡of ¡Oropó ¡ Stream. ¡ 20

  21. Cement-bentonite Barrier 21

  22. Gravel Trench Draining ¡Barrier ¡ • The ¡Draining ¡Barrier ¡was ¡built ¡about ¡30 ¡meters, ¡average ¡width ¡of ¡0.80 ¡meters ¡ and ¡depth ¡of ¡2.70 ¡meters; ¡ • ¡Lined ¡with ¡geotex5le ¡(Bidim) ¡and ¡filled ¡with ¡graded ¡gravel ¡(#2); ¡ • Two ¡wells ¡to ¡extract ¡product ¡(with ¡skimmers); ¡ • To ¡ focus ¡ the ¡ groundwater ¡ flow ¡ (and ¡ free ¡ phase ¡ product), ¡ direct ¡ it ¡ to ¡ the ¡ collec5on ¡wells. ¡ 22

  23. Gravel Trench 23

  24. Permeable Adsorptive Barrier (PAB) Filtering ¡Barrier ¡or ¡Permeable ¡Adsorp5ve ¡Barrier ¡(PAB) ¡ Excavated ¡with ¡dimensions ¡of ¡4.6x3.50 ¡meters ¡with ¡depth ¡of ¡4 ¡meters, ¡forming ¡ a ¡filter ¡box, ¡"enveloped" ¡by ¡a ¡permeable ¡geosynthe5c. 24

  25. Barriers Section 25

  26. Conclusions Presentation Title 26

  27. Conclusions • The system has collected more than 10,000 liters of product. • Less O&M • Energy consumption • Carbon footprint, • Innovation in Brazil • Favorizing operation by local resources 27

  28. Thanks

Recommend


More recommend