Yale Science Building Town Hall Meeting June 28, 2018 Construction - PowerPoint PPT Presentation

Yale Science Building Town Hall Meeting June 28, 2018 Construction Progress southeast Pavilion Progress looking south Construction Progress Auditorium Construction Progress looking west Exhaust Stack Installation Setting AHU Relocation


  1. Yale Science Building Town Hall Meeting June 28, 2018

  2. Construction Progress southeast

  3. Pavilion Progress looking south

  4. Construction Progress Auditorium

  5. Construction Progress looking west

  6. Exhaust Stack Installation

  7. Setting AHU

  8. Relocation Management • Richard Hoffman & Associates has been retained as our relocation manager • Many end users have been contacted by Shellie Anello to meet & work with Hoffman to validate lab equipment

  9. Science Hill Chilled Water Site Logistics

  10. Project Site Logistics Summer 2018

  11. Temporary Wall in SCL 1 st floor

  12. KBT Logistics Summer 2018

  13. Project Construction Milestones Complete Curtainwall Installation: 6/11/18 • • Complete Pavilion Steel Erection: 7/9/18 • Start Install of Windows: 7/9/18 Start Setting Sunshades: 7/17/18 • • Start Drywall: 7/19/18 • Start Interior Finishes: 8/23/18 Begin Piping on Sachem Woods: 9/4/18 •  Dates are weather permitting and subject to change  Noise and vibration impacts will be minimized, monitoring vibration throughout science hill

  14. Get YSB Construction Updates

  15. Questions & Contacts Visit the YSB project website at http: / / yalesciencebuilding.yale.edu/ Sheri Miller Associate Director Project Management & Construction Yale University Office of Facilities sheri.miller@yale.edu

  16. Yale Science Building Town Hall Meeting June 28, 2018