WHITELEYS SHOPPING CENTRE COMMUNITY LIAISON GROUP PRESENTATION 01 4 th FEBRUARY 2018
PRESENTATION TOPICS • Site entrance arrangements • Works – Complete and Upcoming • Overview and Look ahead programme • Façade retention scheme • Tower cranes • Hoarding, parking bay and bus lane suspensions • Soft strip progress • Demolition • Contact information
SITE ENTRANCE ARRANGEMENTS • Pedestrian entrance for construction staff is via the rear Redan Place entrance • Pedestrian entrance for Whiteleys office staff and art exhibition is from central Queensway security door • Vehicle access in to the basement is via Redan Place
WORKS OVERVIEW • Completed works ‐ Scaffold and hoarding to Redan Place ‐ Phone box removal from Porchester Gardens ‐ Tree removal, Redan Place, Porchester Gardens and Queensway ‐ Queensway bus stop has been closed ‐ Queensway bus lane and footpath have been closed ‐ Minilith removal on Queensway (for reinstatement) ‐ Soft strip works to M&S
WORKS OVERVIEW • Upcoming works Street light removal along Queensway from Thursday 6 th Dec ‐ Road improvement works (humps) from Thursday 6 th Dec ‐ Queensway central crossing removal from Thursday 6 th Dec ‐ Footpath improvement works from W/C 10 th Dec ‐ ‐ Scaffolding and hoarding to existing entrances ‐ Soft strip of vacant units ‐ New welfare set up ‐ Temporary service installation ‐ Structural investigations ‐ Ongoing asbestos surveys
PROGRAMME OVERVIEW
PROGRAMME LOOK AHEAD
PROGRAMME LOOK AHEAD
FAÇADE RETENTION SCHEME • Final designs being drawn up now • Steel fabrication due to start 17.12.18 • Footpath substrate improvement works Dec/Jan 19 • Steel frame erection due to start Mid February 19 • Frame erection planned completion June 19
TOWER CRANES • Two tower cranes are to be erected TC1 (South) 23/24 th February 19 • TC2 (North) 9/10 th March 19 • • TC dismantles Sept/Oct 19
HOARDING AND ROAD WORKS • Hoarding has been erected along Redan Place • Hoarding to Queensway and Porchester Gardens to commence in Jan 19 • Queensway bus stop is closed and the bus lane has been suspended. • Road improvement works (hump removal) are to start from Thursday 6 th December for approx. 3 weeks • Footpath improvement works to Redan Place to start next week
ASBESTOS AND SOFT STRIP WORKS • Asbestos survey/investigations are underway ahead of the soft strip work • Currently no asbestos has been found • Soft strip works have started in the following vacant units ‐ Marks and Spencer ‐ GAP • New welfare preparation works have started on the GF of Queensway elevation
NOISE DUST AND VIBRATION • Real time monitors installed before Christmas • Monitoring regime developed with independent specialist • Monitoring plan submitted and agreed with WCC • Alerts sent if any trigger levels are breached • Onsite testing of dust suppression equipment
DEMOLITION • Demolition of the car park is due to start 07.01.19 • Demolition of the car park to be complete mid April 19 • Demolition of the car park basement slab March to end May 19 • Demolition of the main shopping centre May – Nov 19
COMMUNITY LIAISON Liaison Group Meetings will be held every Month Newsletters will be sent out on a monthly basis and information notices on a ad-hoc basis Complaints Procedure: The contact telephone number of the Erith Site Manager and Erith Communications Team will be displayed around the site boundary and contained in newsletters and notices. If you have any queries, problems or complaints during the works, please contact the Community Liaison Manager Cherrie O’Kane or Project Manager Paul Millar Paul Millar (Erith Project Manager) Mobile – 07584 233922 Email - paul.millar@erith.com Cherrie O’Kane (Erith Community Liaison/Conduct Manager) Mobile - 07894 259321 Email - cherrie.o'kane@erith.com Erith Tel No: 0370 950 8800 Email - enquiries@erith.com for out of hours enquires
NEXT LIAISON MEETING The next liaison meeting will be on 29 th January 2019 Location to be confirmed
Recommend
More recommend