visit to project allenby connaught by bondholders 15
play

Visit to Project Allenby/Connaught by Bondholders 15 March 2011 - PowerPoint PPT Presentation

Visit to Project Allenby/Connaught by Bondholders 15 March 2011 Programme 10:30 Arrive at Wellington House, Aldershot 10:45 - 12:15 Project briefing & presentation 12:15 - 13:15 Walking Tour of St Omer Barracks 13:15 - 14:00 Q & A


  1. Visit to Project Allenby/Connaught by Bondholders 15 March 2011

  2. Programme 10:30 Arrive at Wellington House, Aldershot 10:45 - 12:15 Project briefing & presentation 12:15 - 13:15 Walking Tour of St Omer Barracks 13:15 - 14:00 Q & A session and lunch 14:00 Close/Return to Farnborough 2

  3. Strategic Importance to MoD • The Project covers approximately 35% of Army UK Based Trained Manpower (20% of total manpower) • Salisbury Plain is the principle All Arms Manoeuvre Training Area in UK • The Project delivers two key objectives of the 1998 Strategic Defence Review: • Improving working and living accommodation • Identified as a major factor in morale, effectiveness, recruiting and retention • Providing accommodation for Units returning from Germany and reorganising within UK • 2nd Royal Tank Regiment in July 2007, a key deliverable which was met on time • 5 major units moving onto Salisbury Plain (2,500 soldiers) 3 Source: MOD

  4. 2010 Strategic Defence & Security Review • New Defence-wide organisation from April 2011 • Will include this contract, but detailed arrangements still to be determined • Means contract will no longer be answerable to Land Forces • Our joint intent is to ensure that well established working procedures are maintained • Detail of SDSR and its impact on the Project being considered 4

  5. Shared Purpose and Vision Purpose Together, MoD and Aspire will manage and deliver a modern, flexible living and working environment for soldiers in the Aldershot and Salisbury Plain area that will support military fighting power, enhance Army recruitment and retention and provide long-term value for the MoD and for Aspire Vision We will improve the quality of life of soldiers by delivering best in class service 5

  6. History • January 2002 Formed Aspire Joint Venture • 2002-2003 Bidding • July 2003 Selected as Preferred Bidder • January 2004 Pre-Contract Activities Letter – mobilised • April 2006 Financial Close • July 2006 Service Commencement • July 2007 2RTR delivered • 2014 Funding availability period • 2014 Construction complete • 2016 Benchmarking/market testing • 2041 End of contract 6

  7. 7 A 35 year contract to provide a service What is the Contract?

  8. 8 Project Locations

  9. Key Facts • £8Bn [£11.9Bn] 35 year PFI contract with Aspire Defence. • Construction Value £1.5Bn, Steady State Unitary Payment £240M pa • Provides living & working accommodation to 18,700 military personnel, with total dependency more that 21,000 • Originally 10 year, now 8 year construction phase. 375 new buildings and a further 192 refurbished. 457 buildings demolished • Previously 50+ support contracts. Aspire Defence Services manage/operate service provision – 50% self delivered 50% sub- contracted • Local Help Desks, available 24/7 365 days a year 9

  10. 10 Organisation and Structures

  11. Contractual Framework HSBC KBR Innisfree Carillion Infrastructure 45% 37.5% 12.5% 5% Aspire Defence Holdings 100% 100% Project Collateral Contract Aspire Defence Aspire Defence Lenders MoD The Authority Finance Limited Deed Services Works 50% 50% KBR KBR Subcontract Subcontract 50% KBR KBR Aspire Defence Services Aspire Defence 50% Capital Works Lifecycle Hard FM Lifecycle Lifecycle Hard FMSoft FM Hard FMSoft FM Soft FM Utilities Carillion Carillion Mowlem 50% Major FM Utilities Capital Works Utilities Infrastructure Upgrade Subcontract Sub-subcontracts Sub-subcontracts Service Subcontract Living Transport 11 Hard FM/some Soft FM Transport Thames Water/EDF Energy MUJV MUJV (Veolia/UKPNS Other Accommodation Other Sub Corus - Management Services (ADSL) (ADSL) Services( Sodexho ) Management ( Lex ) (Integrated Services & Works Utility) Sub-subcontractors (Babcock Land) (Sodexo)

  12. Working Relationships ADL ADS ADCW 12

  13. 13 Aspire Defence Capital Works

  14. Construction Overview • £1.5bn, 8 year construction programme • Construction of:- • large number low/medium rise low • not technically complex risk • but geographically spread accommodation • Management of Transition Programme key 14

  15. Three Pricing Categories • Firm, Fixed and Competed: • Firm – £481m • Fixed – uplifted for inflation/change in law – £296m • Competed – subject to benchmarking or competition in the market with agreed multiplier – £670m • Appropriate allocation of risk over 8 year construction period (2006 - 2014) 15

  16. Capital Works – number of units, by building type New Build, Demolished, 375 457 Refurbished/ Altered, 192 16

  17. Capital Works - building space by type and use Dining 13% Technical 21% Other Living 5% 61% 17

  18. Pre-Construction Progress to 31 January 2011 Scheme Design Reports Full Design Assets Completed, 512 Complete, 502 Assets to Remaining, 2 complete, 12 Planning Consents Procurement Granted, 366 Procured, 435 Remaining , 79 Required, 4 18

  19. Construction Progress to 31 January 2011 180 160 140 120 100 Assets 80 Remaining 60 In Progress 40 20 0 h d n l r t l e o t r w i r h o h o t o k s f s w l n u D r r a i e d B L m m d i T r l a a A Construction h W r e P AIS, 347 In Progress 61 Remaining 106 19

  20. Construction Summary • Construction not complex • Lessons learned/continuous improvement • Appropriate pricing risk – Firm, Fixed and Competed • Shorter programme • On programme • 65% complete 20

  21. 21 Aspire Defence Services

  22. Hard and Soft FM Services • £4.2bn over 35 years • Management and administration • Assets facilities maintenance • Living accommodation services • Transport services • Stores services • Office services • Welfare services • Support to security 22

  23. Services Support to Supply, Transport Living Management & Assets and Office Welfare Security and Equipment Accommodation Services Administration Facilities Services Services Support Services Services Performance Maintenance: Mailroom Leisure Security Weapons & Domestic Monitoring M&E Services Passes Ammunition Services Building Fabric Archiving Management QA Admin Grounds Civilian Reception Parking Space Ducting Admin and Catering Stores Management Helpdesk Civil Eng Clerical Vetting Furniture Fuel & Mess MIS Fixtures & Typing Lubricants Management Fittings HS&E PA Services Laundry & Dry Military Estate Cleaning Catering HR Management Media Services Tailoring Bar Services Reporting Pest Control Model Making Shoe Repairs Function Data Utilities Reprographics Services Management Maintenance & Travel Booking Management Visitor Fleet Management Cleaning Management Black – Self delivered Red – MUJV Waste Logistics Management Green – Sodexo Vehicle Blue – Babcock 23 Window Cleaning Servicing

  24. Direct Delivery/Sub-Contract Revenue – averages over years 1- 10 at Financial Close prices Sodexo, £28m ADSL, £54m VT Land, £9m MUJV, £13m 24

  25. Service Delivery • High customer satisfaction • 24/7 Help Desks successful • 100% of Retained Estate now in availability regime • 4 year transitional period has now ended • Minimal performance/availability deductions • 0.06% of revenue since FC • Changes in ownership in supply chain but no material impact • IiP accreditation (top 3%) 25

  26. 26 Lifecycle

  27. Lifecycle • ProjCo budgetary risk, except for utilities • Pre FC surveys and due diligence • Cyril Sweet pricing model:- • Gross Floor Area • Cost /m 2 • Age of building • E C Harris opinion as to adequacy 27

  28. Lifecycle Catering Equipment External Areas New & Refurbished Buildings FF&E Retained Buildings Total £613 million Real 2004 28

  29. Lifecycle • Post FC • Retained Estate (circa ⅓ of total) • Extensive surveys • 69 assets • 16 space types • Detailed pricing :- • Individual quantities • Cost per element • Remaining life of each component • Extrapolated 29 • Reconfirms adequacy of Retained Estate estimate

  30. Lifecycle 1,400 1,200 1,000 £M nominal 800 600 400 200 0 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 0 0 1 1 1 1 1 2 2 2 2 2 3 3 3 3 3 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 year 30 Estimate Actual

  31. 31 6 1 0 2 5 1 0 2 4 1 0 2 3 1 0 2 Actual 2 1 0 2 year Estimate 1 1 Lifecycle – early years 0 2 0 1 0 2 9 0 0 2 8 0 0 2 7 0 0 2 6 0 0 2 140 120 100 80 60 40 20 0 £M nominal

  32. 32 Financial

Recommend


More recommend