tsilhqot in solar farm
play

Tsilhqotin Solar Farm Clean Energy BC - GENERATE November 6, 2019 - PowerPoint PPT Presentation

Tsilhqotin Solar Farm Clean Energy BC - GENERATE November 6, 2019 Solar Farm Team Michel deSpot Head Engineer Gabe Pukacz Construction Manager Dolly Kershaw Economic Development Officer FROM FEASIBILITY TO REALITY OUR STORY 2014


  1. Tsilhqot’in Solar Farm Clean Energy BC - GENERATE November 6, 2019

  2. Solar Farm Team Michel deSpot – Head Engineer Gabe Pukacz – Construction Manager Dolly Kershaw – Economic Development Officer

  3. FROM FEASIBILITY TO REALITY OUR STORY 2014 - 2019

  4. Where we are located

  5. WL Substation End of the line Solar Farm The Chilcotin is served by a weak 250 Km-long power line that runs from Williams Lake to Tatla Lake. The low capacity of the grid throttles economic activities and must be supplemented by diesel generators.

  6. WHERE IT ALL STARTED Nits’il’in Russel Myers Ross – Yunesit’in Government Considering a small scale solar farm in the community

  7. Yunesit’in commissioned a 2014 Feasibility Study to look at two projects: 1. A large scale solar farm at the former Riverwest Mill site – 1 MW 2. A small scale solar farm in the community of Yunesit’in Feasibility Study

  8. • Generation of clean energy; • Improvement to local electrical grid; • Redevelopment of a closed sawmill and adjacent brownfield into a solar farm; • Support to the local communities; • Creation of jobs and business opportunities; • Ongoing revenue source. Why a Solar Farm?

  9. • Locations • Solar irradiation in region • Terrain • Shading • Distance to transmission line • Amount of electricity to be produced • Environmental • Costs • Risks Considerations

  10. 35 Kv Distribution Line beside hwy. BIRDS EYE VIEW OF THE SITE

  11. Geotechnical and Pile Testing – November 2017

  12. Racks

  13. First Modules installed – April 13, 2019

  14. Concrete Ballasts – October 2018

  15. New Power Poles – July 2019

  16. Wiring and Modules

  17. Substation Installation

  18. Electrical Installation

  19. Solar Farm Time Line March - BC Trainees Order Hydro Council of August 8 hired equipment announces to Chiefs Pre work and Dually Rack Site and pursue Pre- approve the seek signed Installation officee construction negotiations development Government EPA completed Feasibility repair period with 5 First of a 1MW Funding received Study Internet Ballasts Nations clean Solar Farm Completed energy projects 2014 2016 2017 2018 ➢ Clarifications for land usage ➢ Land ownership ➢ March BC Hydro Application Accepted ➢ Summer BC Hydro SOP under review ➢ December BC Hydro notifies us that no more EPA’s will be issued ➢ Dialogue and Discussions between both parties

  20. Solar Farm Time Line - 2019 Substation Start Installing Construction Trenching Installation High PV modules Construction Lots of PV Modules Construction And voltage Continues Elementary Repair Winter Cables Completed Electrical installation School visits damage Wiring Installation April May June July August September

  21. Financing – Estimated cost $2.8 Million ➢ Proposal Writing and securing grants ➢ Bank Loan Contractors ➢ Expression of Interest – Engineering, Construction, Electrical ➢ RFP – Main equipment suppliers: PV modules, inverters, racks, substation ➢ Conflict of Interest

  22. Mother Nature

  23. October – November 2018 Trainees

  24. April – July 2019 Trainees

  25. Once connected the Tsilhqot’in Solar Farm will be the first large-scale solar power plant 100% owned and operated by First Nations in Western Canada and the largest in BC.

  26. Sechanalhyagh

Recommend


More recommend