trans mountain expansion project
play

Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer - PowerPoint PPT Presentation

Presentation to WCGCE on Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer Oct. 23 Burnaby, BC Outline Overview of Trans Mountain Pipeline Proposed Expansion Project Technical Challenges Routing,


  1. Presentation to WCGCE on Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer Oct. 23 – Burnaby, BC

  2. Outline • Overview of Trans Mountain Pipeline • Proposed Expansion Project • Technical Challenges – Routing, Construction and Geotechnical – System Hydraulics – Facilities – Integrity Management – Automation, Measurement and Leak Detection

  3. Trans Mountain Pipeline – 60 Years of History

  4. TRANS MOUNTAIN PIPELINE TODAY

  5. Trans Mountain Pipeline • In operation since 1953 • 1,150 km from Edmonton to Burnaby • Transports refined products and crude oils: conventional, synthetic and dilbit • Regulated by the NEB • Last expansion completed in 2008 – Anchor Loop • Current capacity: 300,000 bpd Existing relationships along the Right-of-Way

  6. TMPL Throughput 2012 2012 Trans Mountain Pipeline Throughput by Product Type Refined Products Light Crude Heavy Crude Synthetic Crude 17% 16% 22% 45%

  7. Trans Mountain – Historical Throughput 8

  8. TRANS MOUNTAIN EXPANSION PROJECT OVERVIEW

  9. Proposed Scope of Expansion Project • Jan. 10, 2013: Scope update announced • Based on revised 15- and 20-year commitments from shippers to use the line • The proposed expansion to increase capacity to 890,000 barrels per day • Projected capital cost is approximately $5.4 billion

  10. Proposed Scope of Expansion Project • Result: a dual-line operation – twinned pipeline (approximately 980 km of new pipeline) with: – Existing line for lighter products – The proposed new line for heavier oils • 36-inch pipeline diameter • 11 new pump stations for a total of 35 pump stations along the route

  11. Proposed Scope of Expansion project • Estimated 21 new storage tanks at existing facilities in Edmonton, Sumas and Burnaby for a total of 61 tanks along the route • Three loading berths at the Westridge Marine Terminal

  12. Trans Mountain Expansion Schedule Application Preparation 1.5 years Regulatory Approvals 15 months Commercial (Tolling) Approvals Construction 2 years 2012 2014 2015 2016 2013 2017

  13. MARINE

  14. Marine Traffic Current traffic in Port Metro Vancouver related to Westridge Marine Terminal operations Current Estimated with Proposed Trans Mountain Expansion Project 8 vessels per month 37 vessels per month • Jet fuel barges: 1 • Jet fuel barges: 1 • Tankers: 5 • Tankers: 34 • Crude oil barges: 2 • Crude oil barges: 2 • Currently: less than 3% of marine traffic in Port Metro Vancouver Should the proposed expansion be approved, the number of vessels, including tankers and barges, being loaded at the Westridge Marine Terminal could increase to approximately 37 per month (34 of which could be tankers) in 2017, or about 14% of today’s total Port Metro Vancouver vessel traffic.

  15. TECHNICAL CHALLENGES

  16. ROUTING, CONSTRUCTION AND GEOTECHNICAL

  17. Routing • Key criteria in route selection – Follow existing 24” TMPL – Parallel other linear disturbances e.g. road, rail and power lines – Avoid environmentally/geotechnically sensitive areas where possible – Minimize number of major rivers that have to be crossed • Issues faced during routing – Hwy. 16, 5 and 1 were not there when pipeline was built in 1952/53 • Previous road expansions have left many pinch points between existing RoW, road, rail, mountainsides and rivers – Property development between Langley and Burnaby

  18. Routing • For example…

  19. Routing • Show map from Chilliwack to Burnaby • Close up map of Burnaby

  20. Routing • Show map from Chilliwack to Burnaby • Close up map of Burnaby

  21. Routing Outcome • TMEP study corridor (Facilities Application will be submitted to NEB late 2013) – 70% adjacent to or in existing TMPL easement (typically 18 m wide) – 20% adjacent to other linear disturbances – 10% greenfield • Uncertainty about 10% of the route, assessing alternative routes due to: – Landowner concerns – Aboriginal or Stakeholder concerns – Environmental reasons

  22. Construction • Rural vs. urban pipelining • Mountainous terrain – Blasting, backfill and pipe protection procedures, remediation – Will draw extensively on Anchor Loop experience

  23. Canadian Rocky Mountain Parks UNESCO World Heritage Site

  24. Regulatory Oversight DFO NEB Parks B

  25. Routing - Follow Existing Disturbances

  26. Congested Transportation Corridor

  27. Routing – Municipality of Jasper

  28. ROW Access Bridges

  29. Proximity to existing TMPL

  30. Winter Construction

  31. Steep Terrain – West Side Windy Point

  32. Steep Terrain – East Side Windy Point

  33. East Side Windy Point – 1952

  34. Steep Terrain – Stringing Operations

  35. Blast Rock Ditch

  36. Unsuitable Backfill Material

  37. Narrow ROW - Rainbow Hill

  38. Athabasca River Crossing

  39. Athabasca River Crossing

  40. 120+ Isolated Stream Crossings

  41. Wetlands Construction

  42. Rock Fall Hazard - Pallisades

  43. Restoration

  44. Restoration – Streambank Preparation

  45. Restoration – Geikie Wetland, 15,000 Plants

  46. Stream Restoration

  47. Geotechnical • Avoid areas prone to ground movement – Detailed seismic study underway – Complete geohazard inventory developed – Leverage 60 year operating history and detailed natural hazard database • River crossing design – HDD or micro-tunneling vs. conventional “open cut”

  48. SYSTEM HYDRAULICS

  49. System Hydraulics • New 36” pipeline loop (Line 2) – Sustainable annual average pipeline capacity of 540,000 bpd • Based on an assumed slate of heavy crude oils • Existing 24”/30” pipeline (Line 1) – Sustainable average annual pipeline capacity of 350,000 bpd • Based on an assumed slate of light crude oils and refined products • Burnaby to Westridge – Two new 30” pipelines  700,000 bpd – Existing 24” pipeline  500,000 – 700,000 bpd

  50. System Hydraulics • Steady state hydraulic studies completed to verify preliminary results • Pressure surge or transient studies needed to ensure adequate overpressure protection – Pressure surges must be < 110% of the MOP

  51. Liquid Pipeline Operations • Product quality – Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated • Slack flow – Static pressure = Dynamic pressure – Formation of vapour space

  52. Liquid Pipeline Operations • Product quality – Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated • Slack flow – Static pressure = Dynamic pressure – Formation of vapour space

  53. FACILITIES

  54. Burnaby Terminal Overview Existing Planned • 13 tanks • 14 new tanks • 1.6 million bbl capacity • 3.9 million bbl incremental capacity • 24-inch pipeline entering from • New 36 inch pipeline entering southeast from southeast • 24 inch pipeline to Westridge • Two new 30-inch lines to exiting to the northwest Westridge exiting to the northwest

  55. Burnaby Terminal – Existing & Planned

  56. Westridge Marine Terminal Overview Existing Planned • Dock capable of loading 1 • One new dock complex (2 docks Aframax-sizing or smaller vessel with 3 berths) each capable of loading vessels the same size we load today • Berth to be deactivated + • Aframax vessels subject to same demolished after new berths enter restrictions, including being service. loaded at 85% capacity, 550,00 bbls. • 4 PMV designated anchorage • No plans for additional anchorage locations locations • One 24-inch pipe from Burnaby • Two new 30-inch delivery lines Terminal to remain in service from Burnaby Terminal

  57. Westridge – Proposed Aerial view

  58. Westridge – conceptual design This image represents a conceptual design for Westridge Terminal, based on preliminary engineering. The design may change after further developmental and detailed engineering.

  59. Pump stations • # of stations, pumps, horsepower, etc… • Picture of TMPSE pump station

  60. Remote valve sites • # of stations, pumps, horsepower, etc… • Picture of TMPSE pump station

  61. INTEGRITY MANAGEMENT

  62. Integrity Management • Facilities and pipeline undergo hazard identification process and incorporate safeguards into design • If design fails, spills are prevented and/or mitigated by procedures, inspection and detection

  63. Design features • Facilities – Materials, site selection, earthworks, containment • Pipeline – Pipe grade and wall thickness, depth of cover, routing and valve spacing/automation

Recommend


More recommend