this presentation is for a project on us 12 in the st
play

This presentation is for a project on US 12 in the St. Croix County - PowerPoint PPT Presentation

This presentation is for a project on US 12 in the St. Croix County towns of Hudson and Warren. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current


  1. This presentation is for a project on US 12 in the St. Croix County towns of Hudson and Warren. Rather than holding an in-person meeting, public involvement efforts have moved online as a precaution against COVID-19 based on the most current health information from state, federal and local health departments. All meeting materials, including the handout with a comment form, are posted on the design website for this project. https://wisconsindot.gov/Pages/projects/by-region/nw/us12scc/default.aspx If you have any questions, please contact WisDOT Project Supervisor, James Koenig at (715) 838-8391.

  2. Public Involvement Meeting US 12 Towns of Hudson and Warren County U to West Junction WIS 65 St. Croix County

  3. Project Team • James Koenig • WisDOT Project Supervisor • Brett Hollister • WisDOT Consultant Project Manager • Ashley Seibel • WisDOT Consultant Real Estate Specialist

  4. Presentation Agenda • Project Location • Project Purpose and Need • Proposed Improvements • Construction Staging • Real Estate • Project Schedule • Contact Information

  5. Project Location

  6. Purpose and Need • Purpose  Rehabilitate the US 12 driving surface and drainage structures • Need  Deteriorated pavement  Deteriorated drainage structures  Deteriorated beam guard  Narrow paved shoulder

  7. Proposed Improvements • Resurface US 12 with asphalt pavement • Remove or replace beam guard • Widen the paved shoulder • Replace and clean out culverts • Install centerline and shoulder rumble strips • Replace concrete approaches and add flumes at the bridge structure over the railroad tracks • Replace pavement marking

  8. Proposed Construction Staging • 2021 construction season (June-October) • US 12 closed to through traffic • Detour route: US 12 to I-94 to WIS 65 • US 12 will be open to residences and businesses located within the project limits • Temporary driveway closure will be coordinated with property owners

  9. Detour Route

  10. Real Estate • Real estate acquisition for US 12 improvements • Strip takings, both permanent and temporary • Real estate acquisition process • Contact: Ashley Seibel, (715) 830-0544, ext. 205, or ashley@rowpros.org

  11. Real Estate

  12. Project Schedule • Environmental Document July 2019 • Preliminary Plans September 2019 • Real Estate Plat June 2020 • Public Involvement Virtual Presentation August 2020 • Final Plans November 2020 • Construction Summer 2021

  13. What we need from you Share your concerns or comments https://wisconsindot.gov/Pages/projects/by-region/nw/us12scc/default.aspx Responses returned by Aug. 21, 2020 • By email: HollisterB@AyresAssocites.com • By mail: o James Koenig Wisconsin Department of Transportation 718 W. Clairemont Ave. Eau Claire, WI 54701 Thank you for your time

  14. Project Team • James Koenig • WisDOT Project Supervisor • (715) 838-8391 • james.koenig@dot.wi.gov • Brett Hollister • WisDOT Consultant Project Manager • (715) 831-7545 • HollisterB@AyresAssociates.com • Ashley Siebel • WisDOT Consultant Real Estate Specialist • (715) 830-0544 ext. 205 • ashley@rowpros.org