the norwegian governance scheme for major public
play

The Norwegian governance scheme for major public investment projects - PowerPoint PPT Presentation

The Norwegian governance scheme for major public investment projects Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway 1 1 1 Public project failure Cost


  1. The Norwegian governance scheme for major public investment projects Gro Holst Volden, Research Director Concept research program Norwegian University of Science and Technology Trondheim, Norway 1 1 1

  2. Public project failure • Cost overruns, delays, benefits not realized, hidden agendas, etc. • Especially cost overruns have been a common problem across countries and over time. Well documented in the literature – e.g. Morris and Hough, 1991, MacDonald, 2002, Flyvbjerg et al., 2003. • Norwegian study (background for the scheme) – Berg et al., 1999 • Common explanations – technical – cognitive – Political/strategic 2 2 2

  3. Measuring Project Success Project Project Conceptual Delivery Effect plan solution Operational success Tactical and strategic success 3 3 3

  4. Project governance • “The term ”project governance” refers to the processes, systems and regulations that society (the financing party) must have in place to ensure that projects are successful ” (Samset and Volden, 2013) • Minimum requirements for a project governance scheme (Haanæs et al., 2006) – Clearly defined project phases – Clearly defined decision points – Quality assured basis for the decisions – Simplicity – A certain standardization and common terminology 4 4 4

  5. Project Governance in Norway Cabinet Parliament decision approval Project Pre-study Pre-project QA1 QA2 Quality assurance of Quality assurance of cost conceptual solution and steering frames • The Quality Assurance scheme introduced in year 2000/2005 applies to major public projects (> 750 mill. NOK) 5 5 5

  6. Documentation to be Conceptual Appraisal • Overall project Document CAD management document produced by Ministry/ • Needs analysis (steering document) agency responsible • Project goals and • Complete cost estimate requirements • Analysis of alternative for the project • Possibility study contract strategies • Cost-Benefit Analysis Project Pre-study Pre-project QA1 QA2 • Review the • Review the documentation The content of documentation, check • Independent the QA for consistency and uncertainty analysis exploitation of • Give opportunities recommendations • Independant regarding cost frame uncertainty analysis and steering frame and CBA 6 6 6

  7. Projects subjected to external quality assurance Number of projects Hereof completed Number of projects subjected to QA1 76 0 (2005-2015) Number of projects subjected to QA2 183 89 (2000-2015) Number of projects subjected to QA1 15 0 and QA2 (2005-2015) Total number of reviews 232 89 7 7 7

  8. Projects subjected to external quality assurance road rail defence ICT constuction other 8 8 8

  9. Lessons regarding QA1 • The evaluation of effects is years ahead. • CAD/QA1 has led to a more systematic approach to early project assessment. • The quality of the analyses have improved steadily over time • A shift from bottom-up process guided by local stakeholders, to more power to the administration and Cabinet • However, not many projects are rejected, despite low profitability, and when recommendations from an autority and the QA conflict, the Cabinet more often follows the agency. 9 9 9

  10. Lessons regarding QA1 CAD 10 10 10

  11. Lessons regarding QA2 The reviewers’ recommended cost frames are based on stocastic estimation techniques. Cost frame – P85 Target cost – P50 target cost 11 11 11

  12. Lessons regarding QA2 Cost deviation relative to the P85 budget (percentages) 50,0 40,0 Cost 30,0 overrun 20,0 (%) 10,0 0,0 -10,0 Cost -20,0 savings -30,0 (%) -40,0 N = 78 -50,0 • 17 cost overruns and the rest, about 80 % with cost savings. • The total net savings amount to 6 % of the total investments. 12 12 12

  13. Lessons regarding QA2 Cost deviation relative to P50 estimates (percentages) 50 40 Cost 30 overrun 20 (%) 10 0 -10 Cost -20 savings (%) -30 -40 N = 68 -50 13 13 13

  14. Construction Transportation N = 13 Defence N = 47 Cost deviation relative to P50 estimates in three sectors N = 7 14 14 14

  15. Cost overrun (%) Cost savings (%) Cost deviation relative to the size of the P50 budget (percentages) 15 15 15

  16. Cost deviation relative to the P50 budget for projects approved by Parliament 2001 ‐ 2011 16 16 16

  17. Spin-offs and broader benefits of the scheme • Ministries and agencies spend more resources in the front-end and invest in competence. • Some agencies exempted from the QA regime have voluntarily introduced variants of it. – Health sector investments – Electricity transmission line projects – Investments at municipal level – Other countries are inspired by the Norwegian scheme • Extensive research and education in the area of project governance at university level. 17 17 17

  18. A remaining challenge… • Cost creep between QA1 and QA2 QA1 QA2 18 18 18

  19. Other countries with similar schemes 19 19 19 Samset et al., 2016

  20. Conclusions • After QA2 was introduced, 80 % of public projects are completed within budget. Operational project success is definitely improved. • No QA1 projects have yet been completed. Its effect on tactical and strategic performance therefore remains to be seen   ? 20 20 20

  21. Thank you for your attention www.ntnu.no/concept 21 21 21

  22. References • Berg, P. et.al. (1999): Styring av statlige investeringer. Sluttrapport fra styringsgruppen, Finansdepartementet, 10 February 1999. • Flyvbjerg, B., M. K. Skamris Holm and S. L. Buhl (2003): “How common and how large are cost overruns in transport infrastructure projects?” Transport Review, 2003, Vol. 23, No. 1, 71 -88 • Haanæs, S., E. Holte and S. Larsen (2005): Beslutningsunderlag og beslutninger i store statlige investeringsprosjekter, Concept report No. 3 • MacDonald, M., 2002. Review of Large Public Procurement in the UK. London: HM Treasury. • Morris, P.W.G. and Hough, G.H. (1991): The Anatomy of Major Projects. A Study of the Reality of Project Management, John Wiley & Sons, Chichester, UK, ISBN 0-471-91551-3 • Samset et al., 2016, Governance schemes for major public investment projects: A comparative study of principles and practices in six countries, Concept report no. 47 • Samset, K. and Volden, G.H., 2013, Investing for impacts. Lessons with the Norwegian State Project Model and the first investment projects that have been subjected to external quality assurance, Concept report no. 36 22 22 22

Recommend


More recommend