steel city high rise
play

Steel City High-Rise Pittsburgh, PA Analysis 1: Ashley N. Bistline - PowerPoint PPT Presentation

Steel City High-Rise Pittsburgh, PA Analysis 1: Ashley N. Bistline Steel Fabrication Efficiency Analysis 2: Construction Option Unique Structural Members Breadths: Structural and Mechanical Advisor: Somayeh Asadi Analysis 3: Collocation


  1. Steel City High-Rise Pittsburgh, PA Analysis 1: Ashley N. Bistline Steel Fabrication Efficiency Analysis 2: Construction Option Unique Structural Members Breadths: Structural and Mechanical Advisor: Somayeh Asadi Analysis 3: Collocation in the Construction Industry Analysis 4: Vertical MEP Acceleration

  2. Steel City High-Rise Project Background Presentation Outline Statistics and Team  Size: 440,000 SF, 18 stories  Building Height: 220 LF  Project Delivery: GMP with CM at Risk  Cost: Occupancy Breakdown Offices  Overall Project: $100,000,000 Hotel  Construction: $67,000,000 Parking Garage  Construction Dates: Retail  1/13/14 – 12/10/15

  3. Steel City High-Rise Background Analysis 1: Steel Fabrication/Efficiency Presentation Outline Problem and Goals Project Background Analysis 1 // Steel Fabrication Efficiency Background Fabrication Drivers Structural Breadth Mechanical Breadth Analysis 3 // Collocation in the Construction Industry Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Acknowledgments

  4. Steel City High-Rise Fabrication Drivers Analysis 1: Steel Fabrication/Efficiency Presentation Outline Fabricator Expertise Project Background Analysis 1 // Steel Fabrication Efficiency Background Fabrication Drivers Structural Breadth Mechanical Breadth Analysis 3 // Collocation in the Construction Industry Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Acknowledgments

  5. Steel City High-Rise Fabrication Drivers Analysis 1: Steel Fabrication/Efficiency Presentation Outline Sequencing and Erection Project Background Analysis 1 // Steel Fabrication Efficiency Background Fabrication Drivers Structural Breadth Mechanical Breadth Analysis 3 // Collocation in the Construction Industry Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Acknowledgments

  6. Steel City High-Rise Structural Breadth Analysis 1 and 2: Fabrication/Unique Structure Presentation Outline Uniqueness vs Uniformity Project Background Analysis 1 // Steel Fabrication Efficiency Background Fabrication Drivers Structural Breadth Mechanical Breadth Analysis 3 // Collocation in the Construction Industry Steel Analysis 4 // Vertical MEP Acceleration Amount Unit 3,300.00 Pieces Conclusions and Recommendations 2,880.00 Tons Acknowledgments

  7. Steel City High-Rise Structural Breadth Analysis 1 and 2: Fabrication/Unique Structure Presentation Outline Old Floor System Structural Integrity Checks Item Weight (lbs) Deck (2VLI20) 55 Concrete (LW 3.25") 10,376 Beams (2 - W16x26) 5,702 Project Background Pool Water 74,358 Analysis 1 // Steel Fabrication Efficiency Pool Bowl 93,938 Background Total 184,429 Fabrication Drivers Structural Breadth New Floor System Mechanical Breadth Item Weight (lbs) Analysis 3 // Collocation in the Deck (2VLI20) 1,408 Construction Industry Concrete (LW 3.25") 22,267 Analysis 4 // Vertical MEP Acceleration Beams (2 - W16x26) 1,575 Conclusions and Recommendations Total 25,250 Acknowledgments

  8. Steel City High-Rise Mechanical Breadth Analysis 1 and 2: Fabrication/Unique Structure Presentation Outline Air Handling Reconfiguration Project Background Analysis 1 // Steel Fabrication Efficiency Unit Comparison Background Component RTU-5 RTU-6 New AHU Cooling Performance Fabrication Drivers AirFlow (CFM) 4000 3600 5000 Structural Breadth Refrigerant Type R-41 R-41 R-41 Tonnage 10 7.5 13 Mechanical Breadth Capacity (MBH) 123.4 93.1 154.3 Analysis 3 // Collocation in the Supply Air Blower Performance RTU Package Includes: Motor Rating (HP) 3 3 5 Construction Industry • Condenser/Refrigerant Cooling Static Pressure 1.44 0.92 2.6 • Gas Heating Analysis 4 // Vertical MEP Acceleration Drive Type Belt Belt Belt • 3 HP Total Unit Conclusions and Recommendations Weight (lbs) 1205 1005 2393 Acknowledgments

  9. Steel City High-Rise Mechanical Breadth Analysis 1 and 2: Fabrication/Unique Structure Presentation Outline Air Handling Reconfiguration Cost Comparison Item Weight (lbs) 3 HP (2 units) $ 3,878.94 5 HP (1 unit) $ 3,232.45 Old RTU $ 11,300.00 New AHU and Condenser $ 13,500.00 Project Background Analysis 1 // Steel Fabrication Efficiency • Rooftop vs Indoor AHU Background Fabrication Drivers • 2 Units vs 1 Unit Structural Breadth Mechanical Breadth Operational Costs Analysis 3 // Collocation in the Unit $/year Construction Industry Old $ 3,878.94 New $ 3,232.45 Analysis 4 // Vertical MEP Acceleration Savings $ 646.49 Conclusions and Recommendations Acknowledgments

  10. Steel City High-Rise Collocation in Construction Analysis 3: Collocation in the Construction Industry Presentation Outline Collocation at Steel City Project Background Analysis 1 // Steel Fabrication Efficiency Analysis 3 // Collocation in the Construction Industry At Steel City High-Rise Participant Diversity Best Applications Who Should Participate Conclusions Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Acknowledgments

  11. Steel City High-Rise Participant Diversity Analysis 3: Collocation in the Construction Industry Presentation Outline Participant Experience: 83% • 3% : < 1 Year Collocated Projects have worked • 3%: 1-3 Years Project Background on a collocated Analysis 1 // Steel Fabrication Efficiency project before • 6%: 3-5 Years 97% Analysis 3 // Collocation in the Construction Industry At Steel City High-Rise • 18%: 5-10 Years say that Participant Diversity • 25%: 10-15 Years working in a Best Applications collocated space • 9%: 15-20 Years Who Should Participate was a positive Conclusions • 36%: 20+ Years Analysis 4 // Vertical MEP Acceleration experience Conclusions and Recommendations Acknowledgments

  12. Steel City High-Rise Best Applications Analysis 3: Collocation in the Construction Industry Presentation Outline Collocated Projects Project Background Analysis 1 // Steel Fabrication Efficiency Analysis 3 // Collocation in the Construction Industry At Steel City High-Rise Participant Diversity Best Applications Who Should Participate Conclusions Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Acknowledgments

  13. Steel City High-Rise Who Should Participate? Analysis 3: Collocation in the Construction Industry Presentation Outline Choosing Partakers Project Background 94% Analysis 1 // Steel Fabrication Efficiency say that Analysis 3 // Collocation in the Construction Industry productivity At Steel City High-Rise and reliability Participant Diversity increase with Best Applications 71% collocation Who Should Participate Consider: say that value Conclusions  Risk  Duration Analysis 4 // Vertical MEP Acceleration is lost without full  Package Value Conclusions and Recommendations cooperation  Complexity Acknowledgments

  14. Steel City High-Rise Schedule Comparison Analysis 4: Vertical MEP Presentation Outline Accelerated Roof: Schedule Rework Project Background Analysis 1 // Steel Fabrication Efficiency Analysis 3 // Collocation in the Construction Industry Analysis 4 // Vertical MEP Acceleration Original Roof: Schedule Comparison Comparison Savings Original Rework Finish Date 10/16/2015 9/4/2015 Conclusions and Recommendations Duration 21 mos 20 mos Acknowledgments Does not impact: crew, durations, or equipment during construction

  15. Steel City High-Rise Savings Analysis 4: Vertical MEP Presentation Outline Schedule and Cost Impact Comparison Original Rework Finish Date 10/16/2015 9/4/2015 Project Background Duration 21 mos 20 mos Analysis 1 // Steel Fabrication Efficiency Analysis 3 // Collocation in the Construction Industry Acceleration Produces: 1 mos 3 mos Analysis 4 // Vertical MEP Acceleration General Conditions $ 173,155 $ 519,465 Schedule Comparison Revenue $ 167,000 $ 500,000 Savings Total Savings $ 340,155 $ 1,019,465 Conclusions and Recommendations Acknowledgments

  16. Steel City High-Rise Conclusions and Recommendations Ashley N. Bistline // Construction Management Presentation Outline [[ Analyses 1 & 2 ]] Steel Fabrication/Breadths Recommend More efficient units, prevents short cycling, extends life of units Project Background [[ Analysis 3 ]] Collocation in Construction Recommend Analysis 1 // Steel Fabrication Efficiency Prevents issues/swift conflict resolution, improves Analysis 3 // Collocation in the Construction Industry communication, establishing long-term relationships, increases innovation Analysis 4 // Vertical MEP Acceleration Conclusions and Recommendations Recommend [[ Analysis 4 ]] Vertical MEP Acceleration Acknowledgments Can save the project schedule an additional month and save between $340,000 and $1,020,000.

  17. Steel City High-Rise Acknowledgments Ashley N. Bistline // Construction Management Presentation Outline Academic: Industry/Professional: Special Thanks to:  Dr. Somayeh Asadi  Turner Construction Company  PACE Industry Members  Dr. Rob Leicht  Millcraft Investments  Family and Friends  Professor Parfitt  Amthor Steel  God  Dr. Charles Cox  Johnson Controls  AE Power Players  Professor Jim Faust  OPP 2015 Captains  Penn State Architectural Engineering Faculty  AE Class 2015

  18. Steel City High-Rise Ashley N. Bistline // Construction Management Presentation Outline Questions?

Recommend


More recommend