SPE LONDON MEETINGS 2013 SUBSEA PRODUCTION AND FLOW ASSURANCE BY; SACHA SARSHAR,CALTEC www.caltec.com
SUBSEA PRODUCTION &FLOW ASSURANCE • WHY SUBSEA PRODUCTION ? • KEY PARAMETERS • SUBSEA PROCESSING OPTIONS • FLOW ASSURANCE IN WELLS • FLOW ASSURANCE IN SUBSEA PIPELINES/RISERS • HISTORY OF SS SEPARATION & BOOSTING SYSTEMS • FIELD EXAMPLES • THE FUTURE NEEDS AND ASPIRATIONS • TECHNOLOGY GAPS/CONCLUSIONS
DEEP WATER APPLICATION A TYPICAL SUBSEA PRODUCTION Production, manifolding, gas lift, water injection, SYSTEM ,separation, pumping, compression 22 February, 2013 Presentation title 3
A TYPICAL SUBSEA PRODUCTION SYSTEM 22 February, 2013 Presentation title 4
WHY SUBSEA PRODUCTION?,KEY PARAMETERS • DEEP/DEEPER WATER FIELDS,HIGH COST OF MORE THAN ONE DEDICATED PRODUCTION PLATFORMS • SHALLOW TO MEDIUM WATER DEPTH; TRANSPORT OF FLUIDS FROM SATELLITES OR NEW FIELDS TO A HOST PLATFORM • HOSTILE ENVIRONMENTS, LONG DISTANCE TRANSPORT TO A MORE BENIGN ENVIRONMENT • DEEP WATER/LONG DISTANCE PIPELINES, PRESSURE LOSS RESTRICTING PRODUCTION &RECOVERY+OTHER FLOW ASSURANCE PROBLEMS • RISER GENERATED PROBLEMS
SUBSEA PRODUCTION,MAIN BENEFITS • INCREASED TOTAL RECOVERY • ENABLING PRODUCTION FROM DEEP WATERS AND HOSTILE ENVIRONMENTS • LOWER CAPEX/OPEX-CONVENTIONAL PRODUCTION PLATFORMS IN DEEP WATERS HAVE MUCH HIGHER CAPEX &OPEX • ENABLES LONG DISTANCE TRANSPORT OF FLUIDS TO EXISTING HOST PLATFORMS • HSE BENEFITS 22 February, 2013 Presentation title 6
MAIN CAUSES OF RESTRICTIONS TO PRODUCTION & TOTAL RECOVERY • Low reservoir pressure/aging field • Tight, fragmented resevoirs,poor Permeability /PI • Deep reservoirs/deep wells-long flow path • Low GOR /liquid loading • Rising water cut • Long distance transport (Satellites) • High density and viscosity oil • Poor well inflow characteristics • Topside Process system pressure requirements • Hostile environments ,e.g. Arctic A boosting system is therefore needed to maintain or increase production and total recovery
HOW TO MAINTAIN PRODUCTION AND IMPROVE RECOVERY Primary recovery Rate of Recovery (RR) Less than 35% Artificial Surface boosting Natural flow lift systems RR 30%-50% Secondary recovery SS Production/boosting Pressure Maintenance WATER FLOODING IOR Tertiary recovery RR 50% to 80% Others Steam, Hot water, Chemical Gas injection combustion EOR CO2,N2,etc. Microbial, Acoustic, Alkali,Surfactant, Thermal Electromagnetic Polymer
SOLUTIONS TO MAINTAIN OR BOOST PRODUCTION AND TOTAL RECOVERY • MAINTAIN RESERVOIR PRESSURE. E.G. WATER INJECTION • IOR and EOR TECHNIQUES • ENHANCE INFLOW CONDITIONS E.G. ACIDIZE/FRACKING. • DOWNHOLE ARTIFICIAL LIFT;GAS LIFT,ESPS, FOAM INJECTION ETC. PROBLEMS OF HORIZONTAL WELLS • SUBSEA PRODUCTION &BOOSTING-DEEP OR HOSTILE WATERS • EXTENDED REACH HORIZONTAL WELLS • LOWER FLOWING WELLHEAD PRESSURE (FWHP)-VARIOUS METHODS ,INCLUDING SURFACE JET PUMP (SJP)SYSTEMS SOLUTIONS DICTATED BY ECONOMICS ,RISKS AND FIELD/PLATFORM CONSTRAINTS. Combined solutions are often needed 22 February, 2013 Presentation title 9
PRODUCTION FLOW PATH MANIFOLD PIPELINE WELLHEAD RESERVOIR WELL BORE - PRESSURE LOSS - CONNECTORS IOR/EOR - ARTIFICIAL - XMAS TREE - FLOW REGIME/SLUGS -VALVES 4D- LIFT -INJECTION -TEMPERATURE -INSTRUMENTS SESMICS - EXTENDED SYSTEM -CORROSION -METERING REACH -EROSION -FRAME - FLOW -NASTIES;WAX,SCALE.. ENHANCING ,ETC SOLUTIONS -PIPELINE INTEGRITY TOPSIDE SS SLUG EXPORT PIPELINE RISER PROCESS BOOSTING CATCHER -PUMPING - MPH PUMPS - SLUGGING AS - PROCESS - SLUG CATCHER COMP`N -SS SEP`N+ -DP ABOVE -BOOSTING -L.PUMPING PUMP. -INTEGRITY SYSTEMS -GAS COMPRESSION 22 February, 2013 Presentation title 10
COMMON SS COMPONENTS/ISSUES • MODULARISATION • CONNECTORS • INSTRUMENTS • POWER SUPPLY (ELECTRIC,EH,HYDRAULIC) • DATA TRANSMISSION • ACCESS • IMR/SERVICE VESSEL REQUIREMENTS 22 February, 2013 Presentation title 11
MODULARISATION February 13 Presentation title
SUBSEA TEMPLATE AND MOON POOL MODULES INSTALLATION AND RETRIEVAL 22 February, 2013 Presentation title 13
MULTI-BORE SS CONNECTOR KEY FEATURES; • MULTIBORE • SEALS • ACTUATORS • ELECTRIC/HYDRAULIC POWER • SHOULD BE RETRIEVABLE • SEALS IN RETRIEVABLE SS MULTIBORE CONNECTOR PART • PURGING FEATURE • HORIZONTAL OR VERTICAL 22 February, 2013 Presentation title 14
EOR OPTIONS TO ENHANCE RECOVERY STATE OF ART 22 February, 2013 Presentation title 15
WELL BORE FLOW ASSURANCE • MINIMISE PRESSURE LOSS • FLOW REGIME /PREVENT LIQUID LOADING • PROBLEM OF HORIZONTAL WELLS • ARTIFICIAL LIFT SOLUTIONS ( ESP,JET PUMP,GAS LIFT,FOAM, ETC.) • VELOCITY STRING (GAS APPLICATION) • CHEMICALS-SALINITY REDUCING,VISCOSITY REDUCING ETC. • REDUCE WELLHEAD PRESSURE 22 February, 2013 Presentation title 16
WELLBORE, FLOW REGIME MAP • ARTIFICIAL LIFT METHODS • GAS LIFT Superficial Liquid Velocity • ESPs Slug • CHEMICAL (m/s) Annular Mist INJECTION (FOAM ) Bubble • VELOCITY STRING (GAS ) Froth • JET PUMPS SUPERFICIAL GAS VELOCITY (m/s) 22 February, 2013 Presentation title 17
22 February, 2013 Presentation title 18
SUBSEA LIUHUA FIELD ,S-CHINA SEA 25 SS ESPs IN OPERATION FOR NINE YEARS 22 February, 2013 Presentation title 19
FLOW THROUGH SS PIPELINES • PRESSURE LOSS (H.HEAD+FRICTION) • FLOW REGIME,SLUGGING,LIQUID BUILD-UP • TEMPERATURE/HYDRATES • NASTIES; SAND,SCALE,WAX,ASPHALTENE ETC • CHEMICALS,INHIBITORS,DRA, ETC. • PIGGING REQUIREMENTS • CORROSION/EROSION • PIPELINE INTEGRITY • METERING 22 February, 2013 Presentation title 20
PRESSURE&TEMPERATURE PROFILE FOR GAS LINE 22 February, 2013 Presentation title 21
EFFECT OF TURN DOWN IN GAS RATE 22 February, 2013 Presentation title 22
Chevron, USA (GOM) Solution ; HP gas from the existing compressor on recycle used to power the jet pump (Php/Plp=4.9.Qhp/Qlp= 2.11,Pd/Plp=2 ) Benefits Lowered arrival pressure at the platform by 200 psi enabling loaded wells to produce consistently • Higher gas velocities, lowered liquids accumulated in the pipeline, causing a further 140psi drop at the wellhead 40MMSCFD 200 psig Export Sales 400 psig • Production increased by 24% due to wellhead pressure reduction and lower pipeline loss. 1250 psig process Ejector • 2.5 Bscf of otherwise lost reserves recovered. Recycle gas 7.4 MMSCFD GEMINI 850 psig Sub sea manifold 22 February, 2013 Presentation title 23
PRESSURE LOSS DISTRIBUTION-SS GAS PRODUCTION 100 90 80 % OF TOTAL PRESSURE DROP 70 60 ELEVATION 50 FRICTION 40 30 20 10 0 0 10 20 30 40 50 60 GAS FLOWRATE (MMSCFD) WATER DEPTH 2,000m 22 February, 2013 Presentation title 24
22 February, 2013 Presentation title 25
TYPICAL PRESSURE LOSS ALONG PIPELINES 22 February, 2013 Presentation title 26
HIGH PRESSURE DROP DEMANDS SS BOOSTING SYSTEMS TO IMPROVE PRODUCTION &RECOVERY 22 February, 2013 Presentation title 27
TYPICAL HYDRATE FORMATION CURVE 250 HYDRATE FORMING 200 REGION PRSSURE (BAR) 150 100 STABLE NON FORMING 50 REGION 0 0 5 10 15 20 25 TEMPERATURE ( ⁰C)
IF YOU CANT MEASURE, YOU CANT CURE OR IMPROVE • THE NEED FOR DATA COLLECTION, DOWNHOLE,INDIVIDUAL WELLS, SUBSEA LINE AND SUBSEA EQUIPMENT • RELIABLE INSTRUMENTS ARE NEEDED • RELIABLE DATA TRANSMISSION IS NEEDED • RELIABLE AND EFFICIENT DATA MANAGEMENT SYSTEM IS NEEDED 22 February, 2013 Presentation title 29
SUBSEA METERING/WELL TESTING • KNOWLEDGE OF PRODUCTION RATE OF G/W/OIL IS IMPORTANT FOR MANAGEMENT OF PRODUCTION • METERING PRODUCTION FROM SATELLITE WELLS IS ALSO NEEDED • NO RELIABLE SS MULTIPHASE METERING SYSTEM EXISTS, BUT SOME HAVE BEEN USED • FOR TESTING SS WELLS A TEST MANIFOLD + METRING SYSTEM IS NEEDED • ACCURACY OF METRING MAY HAVE TO BE COMPROMISED FOR THE TIME BEING 22 February, 2013 Presentation title 30
CHEMICAL INJECTION A variety of chemicals are introduced at wellhead to achieve flow assurance, including; • HYDRATE INHIBITOR • CORROSION INHIBITOR • DRAG REDUCING AGENT There are also chemicals injected downhole; • CORROSION INHIBITOR/SCALE INHIBITOR • WATER TO REDUCE SALINTY OF PRODUCED WATER • FOAMING AGENT/OTHER COCKTAILS&SOLVENTS 22 February, 2013 Presentation title 31
PIGGING REQUIREMENTS • MOST PIPELINES REQUIRE PIGGING TO CLEAN THE LINE OR TO INSPECT THE LINE INTERNALLY • SS PIG LAUNCHER AND RECEIVER ARE NEEDED • THERE IS A REASONABLE TRACK RECORD • INCREASE IN OPEX & CAPEX IF ALL PIGGING SYSTEM IS SUBSEA ; • THERE IS EXPERIENCE IN SS PIGGING 22 February, 2013 Presentation title 32
RISER GENERATED PROBLEMS • SLUG GENERATION –EFFECT OF RISER PROFILE • PRESSURE LOSS/ FLOW SURGE/SLUGGING • GAS LIFTING AT BASE OF RISER • SLUG CATCHER AT THE BASE OF RISER • RISER STRUCTURAL INTEGRITY-SLUG EFFECT • NEW TECHNIQUE TO MINIMISE RISER GENERATED SLUGGING 22 February, 2013 Presentation title 33
1984 22 February, 2013 Presentation title 34
General Slug Control Structure Cranfield university Actuator Selection PC • Measurement candidates: Measurement – Different pressures Selection FT DT FT – Different flow rates PT PT – Density LT – Levels • Alternative actuators FT LC – Riser outlet choke – Gas outlet choke – Gas injection PT
Recommend
More recommend