southern california edison epic update november 8 2019
play

Southern California Edison EPIC Update November 8, 2019 Highlights - PowerPoint PPT Presentation

Southern California Edison EPIC Update November 8, 2019 Highlights from EPIC 1 & 2 EPIC 1 & 2 have helped with our analytics and transportation electrification efforts Analytics 1. Storm Impact Prediction Demonstration to predict


  1. Southern California Edison EPIC Update November 8, 2019

  2. Highlights from EPIC 1 & 2

  3. EPIC 1 & 2 have helped with our analytics and transportation electrification efforts Analytics 1. Storm Impact Prediction Demonstration to predict estimated asset damage by district to pre-stage resources. Technology transferred to Grid Ops & Business Resiliency • 2. Distribution Transformer Early Failure Detection analyzes customer meter voltage data to identify transformers with internal damage that will lead to premature failure and allow for proactive planned replacement. Technology transferred to the Reliability Operations Center • 3. Transmission Volt-VAR Optimization (VVO) developed to assist grid operators to eliminate voltage violations on the transmission system, reduce the total system losses, and improve the overall voltage profile. The tool resides on a server at the SCE’s grid control center and interacts with the energy • management system (EMS) to monitor the transmission system. Transportation Electrification 1. DC Fast Charger Impact Demonstration assessed the grid impacts of 13 DC fast charger sites to validate compliance with standards, determined SCE infrastructure supports current demand, and informed development of future demand management. 3

  4. EPIC 1 & 2 have advanced our Grid Modernization efforts Technical Findings 1. Informed Advanced Distribution Management System (ADMS) technical requirements and DER Management System (DERMS) contract plan 2. Identified best approach for grid controls and communications Informed SCE’s thinking on the right mix of centralized and decentralized approach • 3. Developed SCE standards for substation IT network design 4. Advanced development of Distribution Automation devices and High Impedance Fault Detection Informing Grid Modernization capital deployment decisions and supporting wildfire mitigation • Process Findings 5. Determined that DER contracts need to allow resource dispatch both at the individual and aggregate level Engagement with DER acquisition organizations to ensure feasibility and viability of DER services • 6. Demonstrated that cyber assessments and methodologies are not standard Engagement with IT needed to ensure cyber and IT/OT integration challenges can be mitigated • 4

  5. EPIC 3

  6. EPIC 3 Overview Portfolio Highlights 1. ​EPIC 3 application included 24 projects 2. Proposed 2 replacement projects in the RAP filing ( May 1, 2019 ) Cancelled Projects Replacement Projects 1. Reliability Dashboard Tools 1. Wildfire Prevention & Resiliency Technology Demonstration 2. Beyond the Meter Phase 2 2. Beyond Lithium-Ion Energy Storage Demonstration ​Portfolio is balanced across project types 1 and electric utility value chain 3. Renewables & DER Grid Modernization & Customer-focused Cross Cutting/ Integration Optimization Products & Services Foundational Grid Operations/ 4 Market Design Generation Generation projects are only performed by the CEC Transmission 1 Distribution 9 9 Demand-side 1 Management Highest Priority Projects 1. SCE identified 13 projects for the first wave of execution 2 2. All 13 are currently in planning and expected to commence in Q1 2020 6 1. Many projects span multiple project types and positions within the value chain. This table identifies the primary categories for each. 2. These projects have the highest alignment with the joint IOU framework and potential to create customer benefits.

  7. Smart City Demonstration ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Partner with a city to deploy a Demonstrate how a utility could use Timing Expected to launch Q1 2020 front-of-the-meter microgrid that customer- and utility-owned DERs supports a significant portion of to operate a microgrid to enhance Customer Benefits the city’s essential facilities (e.g., resiliency while maintaining safety Increase Improve Reduce Costs fire and police stations, and reliability through minimally- Safety Reliability community and senior centers, disruptive islanding and   and emergency shelter) using reconnection. Project Type | Value Chain SCE-owned energy storage and Renewables & DER Integration | customer-owned DERs. Distribution 7

  8. Power System Voltage & VAR Control Under High Renewables Penetration ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Demonstrate the capabilities and Perform hardware-in-the-loop Timing Expected to launch Q1 2020 features of a blackstart-capable simulation and demonstration of BESS on the SCE system and volt/VAR management and system Customer Benefits analyze new control methods to restoration plans following a Increase Improve Reduce Costs enable inverter-based resources to blackout event utilizing grid- Safety Reliability address inertia loss issues, and grid- forming inverter-based resources    forming controls through the (BESS, PV or wind). Project Type | Value Chain blackout and subsequent Renewables & DER Integration | restoration. Distribution 8

  9. DER Dynamics Integration Demonstration ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Engage utility partners, inverter Better understand the impacts of Timing Expected to launch Q1 2020 manufacturers and software high DER penetration on the vendors to demonstrate and distribution and bulk power system. Customer Benefits validate DER dynamics using real- This should help to optimize SCE’s Increase Improve Reduce Costs time hardware in-the-loop testing integration capacity analysis (for Safety Reliability (distribution circuit and substation bulk system constraints) and inform    level testing). Lab testing data will technical requirements and Project Type | Value Chain be validated against field standards discussions in the Renewables & DER Integration | measurements. industry. Distribution 9

  10. Control and Protection for Microgrids and Virtual Power Plants ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Evaluate control and protection Identify control and protection Timing Expected to launch Q1 2020 schemes for behind-the-meter schemes that can ensure the safe microgrids and virtual power and reliable operation of Customer Benefits plants at the distribution level. distribution systems with behind- Increase Improve Reduce Costs This will include assembling a the-meter microgrids and virtual Safety Reliability microgrid testbed using a real- power plants (VPP). Such methods    time simulator and performing could also support system Project Type | Value Chain hardware-in-the-loop testing. This operations under high renewables Renewables & DER Integration | testbed will be used for design, penetration and highly variable grid Distribution testing, and for an eventual field topology. Cybersecurity testing is demonstration. another primary goal. 10

  11. Distributed Plug-in Electric Vehicle Charging Resources ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Pair plug-in electric vehicle (PEV) Demonstrate how fast charging Timing Expected to launch Q1 2020 fast charging stations with energy stations and energy storage can be storage to mitigate the grid used to improve grid reliability Customer Benefits impacts of fast charging. The while supporting customer PEV Increase Improve Reduce Costs project will also evaluate using adoption and fast charging. The Safety Reliability energy storage for grid services. project also aims to demonstrate    the use of second-life PHEV Project Type | Value Chain batteries to support fast charging Renewables & DER Integration | by reducing demand. Distribution 11

  12. SA-3 Phase III Field Demonstrations ❶ Overview ❷ Objective ❸ Profile What does the project consist of? What is the project trying to achieve? What are some relevant project details? Perform field demonstration of Demonstrate a modern substation Timing Expected to launch Q1 2020 SA- 3 technologies at SCE’s Viejo automation system that Substation (220/66/12 kV). This Customer Benefits meets the high availability needed will introduce IP-based for SCE’s critical bulk power (>220 Increase Improve Reduce Costs communications to a transmission kV) substations, and demonstrate Safety Reliability substation (for the first time). This and evaluate the benefits of new    project will also evaluate new substation automation Project Type | Value Chain substation technologies at other technologies. Grid Modernization & distribution substations. 1 Optimization | Transmission 12 1. SCE will demonstrate a resonant ground fault interrupter, an IEC 61850 protection automation controller, process bus (in a field demonstration, and a virtualized protection system.

Recommend


More recommend