section 8 committee
play

Section 8 Committee 14 March 2017 Presented by Steven Neave and - PowerPoint PPT Presentation

Section 8 Committee 14 March 2017 Presented by Steven Neave and Tom Hallam GM, Electricity Networks, (Powercor) GM Regulation and Network Strategy (AusNet) 14 March 2017 COMMERCIAL IN CONFIDENCE REFCL Trials Current Status Woori Yallock


  1. Section 8 Committee 14 March 2017 Presented by Steven Neave and Tom Hallam GM, Electricity Networks, (Powercor) GM Regulation and Network Strategy (AusNet) 14 March 2017 COMMERCIAL IN CONFIDENCE

  2. REFCL Trials – Current Status

  3. Woori Yallock Progress: Energy Released During Fault 1000000 *All values are Effect of Arc indicative only. suppression Coil 100000 Energy Released (joules) 10000 Effect of REFCL in service and initial network balancing 1000 100 Effect of final network balancing 10 2019 regulatory requirement 1 Neutral Earthing Arc Suppression Target WYK Sensitivity Target WYK Sensitivity Resistor Coil 16/17 17/18 1983-2015 page 3 COMMERCIAL IN CONFIDENCE

  4. Technical Issues Impacting To Date Issue Nature of problem Response Impact Gisborne REFCL Issue Underrated components caused Swedish Neutral re designed 2 month delay failure of control circuitry correctly rated hardware now installed Woori Yallock REFCL Inverter tripping continuously on its Ramp and timing setting optimised overcurrent protection to prevent inverter injecting large 4 month delay putting REFCL into transient currents service as all four of these problems were impacting on the ability to diagnose either of them and it Woori Yallock REFCL Hardware Problem – Intermittent Fault found to be an optical fibre require Swedish Neutrals specialist communication fault caused communications module that knowledge of their bespoke system. inverter’s main contactors to open required an earthing connection. randomly during inverter operation Redesign required. Software freezing The communication module Woori Yallock REFCL discussed above caused these issues. Earthing this module also fixed this problem Software Problem- GFN Backup Issue only present during fault Woori Yallock REFCL function not working consistently simulation. This will be fixed in next SN Software release LV Capacitors (PAL) 22kV Transformer issue due to Returned to manufacturer for 3 month delay to supply unusual use of transformer on a rectification. compensated network Woori Yallock REFCL Intermittent Inverter issue. Works ok Under investigation Currently one month delay for permanent faults but trips occasionally for transient faults 4 page 4 COMMERCIAL IN CONFIDENCE

  5. GSB/WND Trial Sites GSB REFCL WND REFCL • Commissioned September 2016 • Network stress testing complete on all 22kV buses without major incident • Two cable failures during commissioning • Two blown surge arrestors (only 1 found – Bowthorpe 24kV) • 75% availability since switched into service 24/7 • Out of service until balancing works can be completed • Fire risk mode trialled for the 2016/17 summer • Dependent on three phase balancing solution • Compensate, soft fault confirm and direct trip CB for permanent faults • Anticipated full commissioning date is late May 2017 • Assessing the reliability impact of this mode • Two sensitivities available • 12.7k Ω (1.0A) selected for TFB days • 8k Ω used at all other times Gisborne in service since September 2016, but not at required capacity page 5 COMMERCIAL IN CONFIDENCE

  6. GSB Balancing Units Capacitive Balancing Product Issues Transformers • Failure of grid balancing phase selector due • Three phase balancing units are to incorrectly specified changeover switch instrumental in the overall balancing strategy • Failure of auxiliary contact on RCC/ • Obtaining the required sensitivity is not balancing circuit due to poor design possible without finite control • Approximately three weeks out-of-service for redesign and repair • Typical transformer design has not been successful • Failure of latching relay in tuning circuit • A prototype has recently been tested • Remained in service at reduced capacity successfully • Awaiting the production of extra units • Reliability of soft fault confirmation algorithm such that the third phase of testing • Suspected false positives leading to large can commence outages • Management and testing of GFN firmware Critical project milestone (fine balancing) in coming weeks page 6 COMMERCIAL IN CONFIDENCE

  7. Operating Mode Fire risk mode = TFB days (min), plus trial for full fire season (Oct to March) Normal mode = low fire risk days Bypass mode = non-TFB days when fire risk and normal mode not deployed page 7 COMMERCIAL IN CONFIDENCE

  8. Timeline & Contingent Project

  9. REFCL Program - Timetable 10 HV customers 10 Tranche 1 Zone substations commissioned 60 HV customers Tranche 2 Wonthaggi - 1 8 Ringwood North Myrtleford - 3 - 2 Barnawartha - 3 Eltham - 2 6 Tranche 3 Kilmore South - 3 Ferntree Gully - 2 Initial Commissioning Rubicon A - 4 Lang Lang - 1 Kalkallo - 3 4 Kinglake - 4 Moe - 3 Sale - 1 Design Commenced Wangaratta - 5 Belgrave - 3 Mansfield - 2 2 Seymour - 5 Lilydale - 3 Benalla - 2 Wodonga 22 kV - Woori Yallock - 5 Bairnsdale - 4 3 30 April 2019 30 April 2021 30 April 2023 33 points 22 points 9 points In-service date page 9 COMMERCIAL IN CONFIDENCE

  10. REFCL Program - Timetable 10 20 HV metering points, incl EHK Zone substations commissioned Tranche 3 Tranche 1 Tranche 2 8 Merbein- 1 Design Hamilton- 2 Castlemaine - 4 Geelong - 4 Commenced 6 Ballarat Nth - 4 Terang- 2 Maryborough- 5 Winchelsea - 5 Ballarat Sth - 5 Koroit- 2 4 Camperdown - 4 Bendigo - 1 Corio - 1 Colac - 5 Charlton- 2 Waurn Ponds- 4 2 Woodend - 4 Bendigo TS - 5 Ararat- 1 Gisborne - 3 *Eaglehawk- 5 Stawell - 1 30 April 2019 30 April 2021 30 April 2023 30 points 26 points 14 points (regulations 30 points) (regulations 55 points) In-service date page 10 COMMERCIAL IN CONFIDENCE

  11. Contingent Project Powercor Tranche 1 (9 x GFNs) Submission date targeted for 31 March 2017: • Surge Arrestor replacement approach reviewed by external consultants GHD • Expenditure estimation had to be completed before confirmation that compliance can be achieved at the GSB and WND initial trial sites. • As no anticipated changes to the allowed voltage limits at HV customer connection points in the Distribution Code, isolating substations have been costed into the Application to maintain voltages within the Code. • The Eaglehawk (EHK) project funding has been brought into the Tranche 1 Contingent Project Application to help mitigate penalties from any delayed projects. • AER has 100 business days to assess the Application. The businesses aim to ensure the revenue requirements can start to be included in the 2018 Tariffs. page 11 COMMERCIAL IN CONFIDENCE

  12. Contingent Project Powercor Tranche 1 (9 x GFNs) page 12 COMMERCIAL IN CONFIDENCE

  13. Civil Penalties Bill

  14. Civil Penalties Bill Technical challenges in Unintended Distribution code and achieving “required Single supplier consequences HV customers capacity” of 0.5amps may not be achievable, even more leverage for both are critical paths potential for a “deliver no recognition of R&D single supplier to call to the commencement at all costs” mindset nature of trials the shots of commissioning R&D works; isolating lead-times for realistic bring-forward works transformers, kiosk significant risk with customer-side place more pressure regulators, capacitive procurement of product solutions are on timeline balancing significant bring-forward works support to HV reduces opportunities customers is unfunded for alternate suppliers and unclear page 14 COMMERCIAL IN CONFIDENCE

  15. Distribution Code & HV Customers

  16. Electricity Distribution Code  REFCL operation is outside distribution code voltage range  ESC has decline to act on ‘no action’ request or code change › Consider REFCL regs trump distribution code; but › Distributors continue to be liable for HV customer equipment damage and economic loss page 16 COMMERCIAL IN CONFIDENCE

  17. AusNet HV Customers 70 Customer Sites with approximately 360 HV transformers of which • Infrastructure Owners (5 Customers with 218 Tx) - Jemena (Off Kalkallo, 3 entire feeders, 76 Tx) - Australian Defence Force (6 sites, 87 Tx) - Metro Rail (13 sites, 38 Tx) - Melbourne Water (7 sites, 12 Tx) - United Energy (off 2 Feeders, 10 Tx) • Large Customers (4 or more Tx) (10 Customers with 94 Tx) - Murray Goulburn, Leongatha (17 Tx), - Nestle (Uncle Tobys), Barnawartha (13 Tx), Thales Australia, (12 Tx) - Murray Goulburn, Maffra( 9 Tx), Australian Textile Mills, Wangaratta ( 7 Tx) <7 Tx and >4 Tx - Wonthaggi Windfarm, D&R Henderson, Carter Holt Harvey, - AGL, Olex, Central Gipps Water, Nestle (Simplot) • Small Customers (23 Customers with 46 Tx) Potential Costs – Site Report, $20k/site ($1.2m), HV Testing, average $70k/site ($3.5m) and Customer Asset Replacement average $50k/Tx (Includes all assets $18m). Total <$23m verses $105m for Isolating Transformers page 17 COMMERCIAL IN CONFIDENCE

  18. AusNet HV Customers Tranche 1 Infrastructure = 2, 39 Tx (Melb Water and Dept of Defence) Large Customers = 4, 30 Tx (Woolworths, Nestle, AGL, Wonthaggi WF) Small Customers = 4, 7 Tx (Pacific Hydro, Nat’ Paper Ind, Aus’ Textile Mill) Tranche 2 Infrastructure = 20, 121 Tx (71 Tx Jemena, Melb Water, Metro, United) Large Customers = 4, 25 Tx (Olex, Murray Goulburn, Gipps Water) Small Customers = 16, 33 Tx Tranche 3 Infrastructure = 8, 58 Tx Large Customers = 8, 39 Tx Small Customers = 3, 6Tx page 18 COMMERCIAL IN CONFIDENCE

Recommend


More recommend