salton sea management program phase i costing tool
play

SALTON SEA MANAGEMENT PROGRAM PHASE I: COSTING TOOL Internal Review - PowerPoint PPT Presentation

SALTON SEA MANAGEMENT PROGRAM PHASE I: COSTING TOOL Internal Review Draft February 6, 2018 1 OBJECTIVES Many alternative designs are possible that achieve State Board Stipulated Order Targets Need to estimate costs for a combination of


  1. SALTON SEA MANAGEMENT PROGRAM PHASE I: COSTING TOOL Internal Review Draft February 6, 2018 1

  2. OBJECTIVES  Many alternative designs are possible that achieve State Board Stipulated Order Targets  Need to estimate costs for a combination of projects  A realistic range of costs is needed for planning, as well as to anticipate future funding needs  A spreadsheet-based tool, based on prior work, was developed for this purpose 2

  3. PRIOR WORK  Performed for the Imperial Irrigation District as part of the Salton Sea Restoration and Renewable Energy Initiative (2015)  Performed for the Salton Sea Authority as part of the Funding and Feasibility Action Plan (2016) 3

  4. KEY COMPONENTS FOR COST ESTIMATE Deeper berms (10’) to hold water for overall management in habitat ponds,  shallower berms (6’) down-playa for additional habitat (expansion ponds) Assumes vinyl sheet pile for seepage control in a third of the berm length  Pump stations and pipelines, to move saline and freshwater to ponds  Levees to pass flood flows through rivers, to minimize damage to newly  created infrastructure Selected berms are designated as causeways for construction and maintenance  Dry dust mitigation in selected areas  4

  5. HIGH LEVEL ASSUMPTIONS  All of the ponds would be formed by constructing berms while working in the dry, using traditional earth-moving equipment.  Fill for the berm structures would be generated from excavating adjacent soil material directly from the sea-bed and near the berm alignment on the up slope side, and within 200’ of the berm.  No artificial islands, channels in ponds, or dredging is proposed as part of these cost estimates.  The New River, Alamo, and Whitewater Rivers would flow unimpeded into the Salton Sea with no dam or gravity conveyance into the project.  Earthwork items have been included with a 25% contingency. For pumping and backbone infrastructure, a 15% contingency was added to the cost.  Dust control areas would be utilized using tillage of the lake bed material with no import or export of materials associated.  Each phase of wetlands construction would need to be done at all three river deltas (New, Alamo, and Whitewater) concurrently, estimated at 2 to 3 years each phase.  All costs have been prepared in 2017 US Dollars. 5 5

  6. CONSTRUCTION PLANNED IN DRY CONDITIONS 6 6

  7. 10-foot High Berm for the Water Management Ponds 7 7

  8. River Flood Control Berm 8

  9. 6-foot High Berm for Expansion Ponds 9

Recommend


More recommend