The Futurist Theatre, Scarborough Methodology for demolition of the theatre, construction of new retaining wall & regrading of slope
The Futurist, Scarborough Overview of site This slide indicates the key features and Kings Street buildings in and around the site Kings Steps Current Futurist The Mermaid Bland’s Cliff
The Futurist, Scarborough Global stability works Removal of material from King Street car park to prevent risk of slip circle failure • Place protection on footpath to King street and remove 2 nr. bollards where the road narrows. • Form vehicle entrance into King Street car park for lorries to turn. See Bryan G Hall drawing 16/369/ATR/002 on next slide. • Backactor to be delivered to existing King Street car park via King Street.
The Futurist, Scarborough
The Futurist, Scarborough Works to King Street car park including grading the top of the slope • Saw-cut through the black-top surfacing to the car park on a line set out 10m from the wall to the properties on Prospect Place • Remove the blacktop surfacing and cart away via King Street. • Excavate material from the car park to form a slope commencing at the rear of the boundary wall to King Street and running down to the bottom of the first terrace working from the top of the slope downwards – see drawing below;
The Futurist, Scarborough Graphic showing line of earthworks cut through King Street car park
The Futurist, Scarborough Section showing profile of material to be removed during first phase of earthworks
The Futurist, Scarborough Graphic showing material removed from car park following first phase of earthworks
The Futurist, Scarborough Works to Foreshore Road • At the same time as the works to King Street car park are progressing, the street works to Foreshore Road will commence. The work involves the following; ➢ Relocation of an existing bus shelter ➢ Removal of two existing central islands to create a temporary pedestrian walkway and a path for vehicles exiting the site. ➢ Erection of temporary site hoarding complete with entrance and exit gates. ➢ Protection of the existing buried services in the public footpath by overlaying with timbers and road-plates.
The Futurist, Scarborough Works to Foreshore Road to create the one way servicing arrangement
The Futurist, Scarborough Global stability works Infill rooms with lean mix concrete to a depth of 1.5m
The Futurist, Scarborough Global stability works Infill room and staircore in south-west corner of building with lean-mix mass concrete
The Futurist, Scarborough Global stability works Infill room containing buttresses with lean mix concrete to a depth of 1.5m
The Futurist, Scarborough Global stability works Infill room containing buttresses with lean mix concrete to a depth of 1.5m Install temporary props to existing retaining wall to Blands Cliff
The Futurist, Scarborough Graphic showing counterweight and additional buttressing to existing retaining Install material to add wall counterweight and additional buttressing to existing retaining wall
The Futurist, Scarborough Demolition works Erect scaffold to give access to roof of building. Construct scaffold fan to provide protection to corner of shelter
The Futurist, Scarborough Demolition sequence Following the reduce level dig to the upper plateau on Kings Street and installation of the mass concrete ballast, we will commence ‘ of r p' to full internals of the structure with skips placed outside the main entrance for debris removal. Mechanical demolition will then commence to phase 1 working in from the north east corner using a specialist D-Rig Hy reach excavator with demolition attachments. When phase 1 is complete the high reach can remove the flat roof section of Phase 2 and then proceed to the front wall reducing it to first floor height . A scaffold platform will be built off the roof steel work to facilitate the removal of the asbestos roof sheets to the theatre.. When the roof sheets have been removed the trusses will be removed using a cherry picker, Hy-reach excavator and cutting tools to safely lower the trusses to the ground. Following the truss removal the outer walls to phase 3 and 4 will be taken down to first floor level this is where the transitional steel beam spanning the seating is located, the exactor will be used to remove the seating tier to level one removing all timbers and secondary steels to the seating level, once this is complete the walls will be reduced to allow a crane to access site and lift the main beam down to grade allowing it to be cut to size and removed from site. The same process will now be utilised to bring phase 5 and 6 to grade starting from the façade once again employing the crane to remove the 2 main steels spanning the seating section. All scaffold will then be removed from site and the remaining walls folded into the footprint of the structure, the crusher will be delivered to site to crush the material to 6F2 and stockpiled on site. Slabs and footings will be broken and also crushed to 6F2 and material re- laid to ensure no leading-edge hazards remain. All wastes will be removed form site at regular intervals and dust will be suppressed via the use of 2 Dust Cannons one at the rear and one on the working face of the demolition..
The Futurist, Scarborough Processing of material from demolished buildings Concrete crusher to be positioned on on footprint of Mermaid building. Stockpile of crushed hardcore to be created on footprint of buildings.
The Futurist, Scarborough Construction of new retaining wall Install temporary sheet piles on the inside of existing retaining wall to Kings Steps to enable excavation of new retaining wall base
The Futurist, Scarborough Construction of new retaining wall Reinforce shutter and concrete new retaining wall Drainage to be installed behind new retaining wall
The Futurist, Scarborough Backfill to retaining wall Backfill between existing retaining wall and new retaining wall and grade slope. Fix topsoil retaining mat, spread topsoil and seed.
The Futurist, Scarborough Drainage works Drains to be installed as shown on Arup drawing FUT-ARUP-ZZ-XX-DR-CD-003
Recommend
More recommend