real property institute of canada
play

Real Property Institute of Canada 2014 RPIC Federal Contaminated - PowerPoint PPT Presentation

Real Property Institute of Canada 2014 RPIC Federal Contaminated Sites National Workshop April 2014 2 / 37 Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B) Confirmatory Sampling, Analysis and Evaluation Plan (CSAEP)


  1. Real Property Institute of Canada 2014 RPIC Federal Contaminated Sites National Workshop April 2014

  2. 2 / 37 Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B) Confirmatory Sampling, Analysis and Evaluation Plan (CSAEP) Implementation and Dredging Residuals Management Stream H: Contaminated Sites Management for Aquatic Environments and Sediment Presenter: David McKeown (SLR Consulting) Collaborators: Jeff Nyman (SLR), Andrew Mylly (PWGSC), Rae Ann Sharp (PWGSC), Tom Wang (Anchor QEA), Dan Berlin (Anchor QEA), Matt Woltman (Anchor QEA)

  3. 3 / 37 Project Background • The EGD is a federally owned, operated and maintained facility. • Ship repair and maintenance facility for military and civilian vessels since 1927. • Industrial activities at the EGD have resulted in contamination of the surrounding sediments. • PWGSC managed the remediation project through FCSAP funding. • The Waterlot Remediation Program aimed to clean up the site to meet federal and provincial environmental standards.

  4. 4 / 37 Project Background (Cont’d) • Primary CoCs in sediment included Metals, PAH, and PCB. • Other contaminants included TBT, Dioxins/Furans, and Pesticides. • Contaminant levels identified as IL+ for disposal considerations. • Contaminated sediments were removed through remedial dredging and off-site disposal. • Confirmatory sediment sampling program designed and implemented to verify that remedial targets were met. • Decision criteria developed to determine potential re- dredging and/or Remedial Management Cover (RMC) placement requirements.

  5. 5 / 37 Project Location Esquimalt Graving Dock

  6. 6 / 37 Project ¡Boundary ¡

  7. 7 / 37 Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡

  8. 8 / 37 Objectives • CSAEP developed to outline standardized procedures for collection of post-dredge sediment samples. • Establish methods to characterize and assess post-dredge sediment quality. • Provide an evaluation process to verify whether remedial targets were met through dredging activities. • Provide project staff with a guidance tool to conduct sampling, assess resulting information, and determine whether additional actions were required. • Also used as a baseline planning tool for cost estimates to implement the sediment quality assessment program.

  9. 9 / 37 Study Design • Waterlot divided into 11 dredge zones based on pre-dredge contaminant profiles. – Zone 10 further broken into sub-zones • Dredge zones sampled after completion of dredging activities using a 25 x 25 m grid spacing. • Locations identified in field using sub-metre accuracy GPS • Vibracore samples collected at each location with concurrent surface grab samples (petite ponar). • Diver cores collected where unable to obtain vibracore samples. • Test pit samples collected during low tide in Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡ intertidal area of Munroe Head.

  10. 10 / 37

  11. 11 / 37 Study Design • Sediment quality assessment conducted for each dredge zone and sub-zone individually. • Confirmatory sediment cores and concurrent grab samples collected at each location for analytical testing. – Cores were sampled at 0.5 m intervals to identify missed inventory contamination. – Surface grab samples were used to identify dredge residual contamination. • Slope samples also collected prior to slope armouring to aid in future risk assessment updates. – Not included in re-dredge decisions due to geotechnical considerations. • Over 200 post-dredge locations sampled.

  12. 12 / 37 Remedial Objectives • Numeric Remedial Action Objectives: – Based on most stringent and previously accepted applicable marine environmental quality guidelines, including: • CCME Marine Sediment PEL • BC CSR Sediment Criteria for Typical Contaminated Sites • Puget Sound Dredge Disposal Analysis & Site-specific TBT assessment (Golder) • NRAOs derived for: – Metals – PAH – PCB – Dioxins & Furans – TBT – Select Pesticides

  13. 13 / 37 Sample Collection, Handling and Processing • Core samples collected by vibracoring vessel. • Cores advanced in to sea floor 2 to 3 m or until refusal. • Core tubes cut open to facilitate sample processing. • Core compaction corrections applied based on penetration depth vs. recovery core length. – Minimum recovery targets established for acceptance of cores.

  14. 14 / 37 Sample Collection, Handling and Processing • Samples collected at 0.5 m intervals along cores. – Upper 1.0 m samples submitted for analysis. – Remaining samples archived. • Samples homogenized within each interval to ensure representative samples.

  15. 15 / 37 Sample Collection, Handling and Processing Diver assisted grabs/cores collected Concurrent grab samples collected where vibracoring was not possible (e.g., using petite ponar sampler. dry dock sill area, hard substrate areas).

  16. 16 / 37 Sample Collection, Handling and Processing All grab, core, test pit samples Munroe Head intertidal area homogenized to be representative. (Zone 9) sampled by test- pitting during low tides.

  17. 17 / 37 Laboratory Coordination and Submissions • Prepared Laboratory Statement of Requirements to define: – Required detection limits to meet NRAO levels. – Turn-around-times for specific parameters. – Detailed schedule for samples and analysis requirements on a daily, weekly and monthly basis. – Communication requirements. – Data management and QA/QC requirements. • Electronic COC submissions. • Sample pick-up/delivery coordinated through laboratory.

  18. 18 / 37 Data Management • Dedicated web-based Environmental Management Tool (EMT) developed to provide accessible and up to date data repository. • Remote access for project personnel. • Laboratory results loaded automatically to the EMT. • Data manager included on project to provide QA/QC review, data tabulation and management, and statistical analysis. • Sediment quality compared to NRAOs

  19. 19 / 37 Data Management (EMT)

  20. 20 / 37 Confirmatory Sample Assessment • Post-dredge compliance decision framework generated for assessment of sediment quality. • Post-dredge sediment quality was assessed using two methods: – Overall dredge zone compliance with NRAOs based on statistical approach (surface samples only). – Single point compliance assessment. • Surficial samples compared to 4X NRAO threshold to assess dredge residual contamination. – Considered eventual mixing of upper sediment layers (up to 10 cm) with placed RMC layer (30 cm) • Core samples compared to 1X NRAO to assess missed inventory contamination.

  21. 21 / 37 Re-Dredge Decision Process • Initial re-dredge decision based on 3-day TAT parameters (metals, PAH, PCB). – These parameters were drivers in most zones and other contaminants (i.e., pesticides, TBT, dioxins/furans) were generally shown to co-locate. – Pesticides, TBT, dioxins/furans analyzed on a 7-day TAT. – Where other parameters were drivers within a zone, results were re- assessed once they became available. – Modifications to the re-dredge decision were then provided to the contractor. • 10-day turn around requirement in specifications to provide re- dredge decision to contractor. • Consultant design team and PWGSC personnel reviewed information from each zone in accordance with decision framework. – Re-dredge decisions formally relayed to contractor through PWGSC. 21 / 37

  22. 22 / 37 Re-Dredge Decision Process • Contingency re-dredge depths determined based on whether residual or missed inventory contamination was present within dredge zone and/or each sampling grid. • Additional surface grab samples collected following re-dredging. • Sediment quality from second sampling round was re-assessed in accordance with the post-dredge Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡ compliance decision framework. – Residuals assessment only.

  23. 23 / 37 Post-Dredge Compliance Decision Framework ZONE DREDGING COMPLETED CONFIRMATORY SAMPLING (Vibracore and Surface Sampling) CORE SAMPLING SURFACE Archive Samples (0 – 2.0 m with min 75% recovery) below 1.0 m SAMPLING Composite samples to lab (in 0.5 m intervals) (0 – 0.1 m) (0-0.5 m and 0.5-1.0 m) Analytical Data Receipt, Tabulation and Review Lab analysis (3-7 working days)

  24. 24 / 37 Post-Dredge Compliance Decision Framework COMPLIANCE UNIT ASSESSMENT (based on surface samples only) Method 1 – Single Sample Assessment Method 2 – Statistical Approach Are the surface Are there any Is the 90 th Percentile or sample surface sample 95% UCLM surface sample concentrations concentrations concentrations below NO ¡ YES ¡ less than NRAO? >4X NRAO? NRAO? YES ¡ NO: ¡<4X ¡NRAO ¡ NO: ¡>4X ¡NRAO ¡ RESIDUAL RE- RESIDUAL RE- If ¡<4X ¡NRAO ¡ DREDGE DREDGE PLACE RMC YES ¡ NO: ¡<4X ¡NRAO ¡ (0-0.3 m) (0-0.3 m) 2 nd Round Surface Sampling 2nd Round Surface Sampling If ¡<NRAO ¡ Is the 90 th Percentile or 95% UCLM surface sample concentrations NO FURTHER YES ¡ ACTION below NRAO? If No, RMC thickness REQUIRED to be evaluated based on in-situ concentrations

Recommend


More recommend