Roadway Improvements Parkway Drive Area Public Information Centre Date: Thursday February 16, 2017 Location: Mountainside Recreation Centre 2205 Mount Forest Drive Time: 5:30 pm to 7:30 pm
Project Team Councillor John Taylor John.Taylor@burlington.ca City of Burlington Scott Hamilton, Manager of Design & Construction Dave Johnson, Project Manager Aaron Kuryluk, Senior Design Technician Tom Georgiadis, Contract Administrator Federal gas tax funds at work in your community. Les fonds de la taxe f é d é rale sur l ’ essence à l ’ oeuvre dans votre communaut é . Design and Construction – Capital Works
Project Limits - Parkway Drive, Moss Glen Road and Niels Avenue Design and Construction – Capital Works
Existing Conditions Design and Construction – Capital Works
Existing Conditions Design and Construction – Capital Works
Project Overview Roadway Improvements – Parkway Drive Area The proposed work includes the following: • Remove and replace existing road asphalt • Remove and replace concrete curbs and sidewalks • Storm sewer repairs where required • Replace concrete street light poles, complete with LED lighting Design and Construction – Capital Works
Project Overview Typical Road Reconstruction Design and Construction – Capital Works
Project Schedule Public Information Centre: February 16, 2017 Tender Period: April 2017 Construction Period: June through September 2017 (School block, July – August) Budget $ 1,725,000 Design and Construction – Capital Works
Project Team Contacts Councillor John Taylor Phone: 905-335-7600 ext. 7459 Ward 3 John.Taylor@Burlington.ca Email: Capital Works Dave Johnson Phone: 905-335-7600 ext. 7507 Design & Construction Project Manager Email: David.Johnson@burlington.ca Aaron Kuryluk Phone: 905-335-7600 ext. 7687 Senior Design Technician Email: Aaron.kuryluk@burlington.ca Tom Georgiadis Phone: 905-335-7600 ext. 7806 Contract Administrator Email: Tom.Georgiadis@burlington.ca Project updates can be found at: http://www.burlington.ca/en/services-for-you/parkway-drive-area-minor-reconstruction.asp To receive email updates about this project, please "Subscribe to this page...". on the project web page. Project updates will automatically be sent to you as the pages are updated. Design and Construction – Capital Works
Design and Construction – Capital Works
Roadway Improvements – Parkway Drive Area Comment Sheet Thank you for your participation in this project. please use next page if more space is required F Please deposit on departure Please return to: or mail/e-mail by March 2, 2017 Tom Georgiadis, Contract Administrator Name: City of Burlington, Capital Works Department Address: 426 Brant Street, P.O. Box 5013, Burlington ON L7R 3Z6 Fax: 905-335-7822 Email: Tom.Georgiadis@burlington.ca Telephone: Email: Design and Construction – Capital Works
Roadway Improvements – Parkway Drive Area Design and Construction – Capital Works