PROPOSITION O Argo Drain Sub-Basin Facility Project Construction Update Neighborhood Council of Westchester/Playa Tuesday, November 6, 2018, 6:30 pm 1
Prop O Argo Drain Sub-Basin Facility Construction Update Agenda Allen Wang, Project Engineer, Bureau of Engineering Alvaro Prada, Construction Manager, Bureau of Engineering Geoff Thompson, LAX Community Liaison, Council District 11 Discussion Topic Argo Project Background (BOE) Argo Project Construction Update (BOE) Open Space Opportunities (Council Office) General Discussion (All Participants) 2
ARGO PROJECT SCOPE • The Project will treat stormwater runoff from a 2320-acre drainage area, including areas of LAX, that discharges to Dockweiler Beach with a capture capacity of 8.1 million gallons. • Completion of the Project will help meet stormwater pollution regulations. 3
SCHEDULE UPDATE • Construction Schedule: • Construction Start: October 2018 • Construction End: Winter 2020 4
DRAINAGE AREA Project SANTA Location MONICA BAY 5
AERIAL VIEW 6
CONTRACTOR PARKING 7
HAUL ROUTE 8
ANTICIPATED TRAFFIC CONTROL • Falmouth Ave: 92 nd St to Jet Pet Driveway • Street narrows from 38’ to 24’ (600’) • Traffic remains 1 lane in each direction • West sidewalk will be closed • No street parking at the narrowed street section 9
FINAL PROJECT RENDERING 10
FUTURE OPEN SPACE OPPORTUNITIES • Council District 11 will lead a process to determine the preferred community uses for the green space in and around the Prop O site. • This will include soliciting feedback on the site. Work has already begun on this initiative. Reach out to Geoff Thompson, LAX Liaison, for further detail. 11
OPEN SPACE OPPORTUNITIES 12
GENERAL DISCUSSIONS QUESTIONS & ANSWERS 13