Redwood Road in Saratoga Springs Project Update November 1, 2018 Phase 1 (Completed in 2017): Newly paved road from Village Parkway to the south 10 miles. Phase 2 (Completed in 2018): Five-lane roadway and bike lanes from 400 South


  1. Redwood Road in Saratoga Springs Project Update November 1, 2018

  2. Phase 1 (Completed in 2017): • Newly paved road from Village Parkway to the south 10 miles. Phase 2 (Completed in 2018): • Five-lane roadway and bike lanes from 400 South to Lake View Terrace Road. • Dual left-turn lanes at Grandview Boulevard. • Multiuse trail from Pioneer Crossing to 400 South.

  3. Phase 3 (Complete in 2019): • East-west Continuous Flow Intersection (CFI) at Pioneer Crossing. • Five-lane roadway and bike lanes from Lake View Terrace Road to Village Parkway. • Traffic signals at Ring Road and Stillwater Drive.

  4. Residential to Commercial Connection: • Approximately two miles of a new multiuse trail connects over four miles of existing trail. • This missing trail segment connects residents to a fast growing commercial area.

  5. Continuous Flow Intersection (CFI) Overview Video:

  6. Continuous Flow Intersection (CFI) – Active Transportation Features Green Thermoplastic Bike Turn Box Bike Ramp Pedestrian Refuge

  7. Questions and Comments