Project Update Prepared and Presented by Toni Lombardozzi, CCPL Project Manager Library Board of Trustees Update, Main Library – June 25, 2020
June 25, 2020 Page 2 Location Updates Regional Library Renovations Completed review of 95% drawing set mid-June Cost estimates underway If schedule holds, expect to begin construction October 1 (tentative) Plan to complete three regionals in first round, then once those are complete, move on to the remaining two
June 25, 2020 Page 3 Location Updates R. Keith Summey North Charleston (RKSNC) Master Plan design work for Shipwatch Corridor still in progress Anticipate beginning design work on the library this fall CCPL and County are looking into options for temporary library space since a portion of the existing Cooper River Memorial Library must be incorporated into the new library due to its historic designation
June 25, 2020 Page 4 Location Updates Bees Ferry West Ashley (BFWA) Furniture installation delayed due to COVID-19, many pieces expected for delivery in June/July AMH installation week of July 6 th , Self-check installation July 14/15 th ODC mid-August (tentative) Anticipated Milestones Substantial Completion: July 2020 Opening: Fall 2020 (tentative)
June 25, 2020 Page 5 Location Updates St. Paul’s Hollywood (SPH) Virtual ribbon cutting held June 7 th Opened for curbside service along with other CCPL branches June 8 th
June 25, 2020 Page 6 Location Updates Baxter - Patrick James Island (BPJI) Working through correcting/finalizing some items + attention to warranty items County working through closeout process Wando Mount Pleasant (WMP) County working through closeout process
June 25, 2020 Page 7 Location Updates Support Services (SS) Temporary Certificate of Occupancy issued March 16 Certificate of Occupancy pending one final item: installation of an air grille and surrounding ceiling; installation of grille complete, ceiling installation wrapping up this week Furniture installation 98% complete; remaining items expected mid-July Anticipated Milestones Final Completion/Certificate of Occupancy: early July 2020 Move-in/Opening: July 2020 (last week June, first week July)
June 25, 2020 Page 8 Timeline Summary June 2020 Fall 2020 July 2020 • BFWA Open • SS Final • SS Move-in Completion • Regionals construction start • BFWA • SPH Open Substantial Completion
June 25, 2020 Page 9 Financial Status – Previous Reports Project Title Status Total Project Title Status Total Bees Ferry West Ashley Baseline* 14,441,665 Bees Ferry West Ashley Baseline* 14,441,665 Actual/Projected CWE 14,567,174 Actual/Projected CWE 14,567,174 Baxter – Patrick James Island Baseline* 13,131,000 Baxter – Patrick James Island Baseline* 13,131,000 Actual/Projected CWE 11,953,344 Actual/Projected CWE 11,953,344 Wando Mount Pleasant Baseline* 26,135,000 Wando Mount Pleasant Baseline* 26,135,000 Actual/Projected CWE 20,221,226 Actual/Projected CWE 20,221,226 R. Keith Summey N. CHS Baseline* 10,673,609 R. Keith Summey N. CHS Baseline* 10,673,609 Actual/Projected CWE 11,921,528 Actual/Projected CWE 11,921,528 St. Paul’s Hollywood Baseline* 10,946,000 St. Paul’s Hollywood Baseline* 10,946,000 Actual/Projected CWE 11,554,500 Actual/Projected CWE 11,554,500 Support Services Baseline* 7,669,549 Support Services Baseline* 7,669,549 Actual/Projected CWE 8,603,517 Actual/Projected CWE 8,603,517 Existing Library Upgrades Baseline* 25,503,177 Existing Library Upgrades Baseline* 25,503,177 Actual/Projected CWE 29,652,428 Actual/Projected CWE 29,652,428 LIBRARY TOTAL Baseline* 108,500,000 LIBRARY TOTAL Baseline* 108,500,000 CWE 108,473,717 CWE 108,473,717 Figures as of November, 2019 Figures as of January, 2020