project presentation
play

Project Presentation EANC Meeting Nevada County Contractors - PowerPoint PPT Presentation

Banner Cascade Pipeline Project Presentation EANC Meeting Nevada County Contractors Association November 29, 2012 BANNER CASCADE PIPELINE ALIGNMENT Nevada County Airport BANNER CASCADE PIPELINE PROJECT Project Overview Second Phase


  1. Banner Cascade Pipeline Project Presentation EANC Meeting Nevada County Contractors Association November 29, 2012

  2. BANNER CASCADE PIPELINE ALIGNMENT Nevada County Airport

  3. BANNER CASCADE PIPELINE PROJECT  Project Overview  Second Phase – Following Cascade Upper Bench Replacement – 2000  Take Pressure off Lower Cascade Canal with installation of 6.8mi of 48 inch steel pipe  Project began in 2001 with EIR Process  Seven years to EIR certification and approval  Design began in January 2008

  4. BANNER CASCADE PIPELINE PROJECT

  5. BANNER CASCADE PIPELINE PROJECT

  6. BANNER CASCADE PIPELINE PROJECT  Project Overview  Second Phase – Following Cascade Upper Bench Replacement – 2000  Take Pressure off Lower Cascade Canal with installation of 6.8mi of 48 inch steel pipe  Project began in 2001 with EIR Process  Seven years to EIR certification and approval  Design began in January 2008

  7. BANNER CASCADE PIPELINE PROJECT  Design Overview  RFP Process for the Design Consultant  Design concept: Stakeholder Involvement  Hosted Three Public Workshops during the design at 10%, 50% and 90% completion  Gathered Public Input from property owners from workshops and numerous 1 on 1 meetings and incorporated into design  Design began in January 2008 and concluded January 2010 with a Contractor RFQ process

  8. BANNER CASCADE PIPELINE PROJECT  Bid Overview  Contractor RFQ process used a matrix to select qualified contractors prior to bidding the project  Bid project knowing that the contractors would perform to District standards  Included in the bid process a local bidders preference  Teichert Construction awarded the contract

  9. BANNER CASCADE PIPELINE PROJECT  Pre-Construction Overview  Easement Acquisitions - continued  Well Monitoring Program - continued  Pre-construction Environmental Surveys  Environmental Monitoring for Creek Crossings (before and during construction)  Removal of approx. 600 trees from alignment staged over two year period

  10. BANNER CASCADE PIPELINE PROJECT

  11. BANNER CASCADE PIPELINE PROJECT

  12. BANNER CASCADE PIPELINE PROJECT  Pre-Construction Overview  Easement Acquisitions - continued  Well Monitoring Program - continued  Pre-construction Environmental Surveys  Environmental Monitoring for Creek Crossings (before and during construction)  Removal of approx. 600 trees from alignment staged over two year period  Scotch Broom Removal

  13. BANNER CASCADE PIPELINE PROJECT

  14. BANNER CASCADE PIPELINE PROJECT  Pre-Construction Overview  Easement Acquisitions - continued  Well Monitoring Program - continued  Pre-construction Environmental Surveys  Environmental Monitoring for Creek Crossings (before and during construction)  Removal of approx. 600 trees from alignment staged over two year period  Scotch Broom Removal

  15. BANNER CASCADE PIPELINE PROJECT

  16. BANNER CASCADE PIPELINE PROJECT  Construction Overview  Started a communication process to inform the neighborhoods of the upcoming work  Had Ombudsman working as a direct link between the property owners and NID  Installed seven Project Information Boards in strategic locations along the alignment  Held several Public Workshops with the neighborhoods prior to start of construction

  17. BANNER CASCADE PIPELINE PROJECT

  18. BANNER CASCADE PIPELINE PROJECT

  19. BANNER CASCADE PIPELINE PROJECT  Construction Overview  Started a communication process to inform the neighborhoods of the upcoming work  Had Ombudsman working as a direct link between the property owners and NID  Installed seven Project Information Boards in strategic locations along the alignment  Held several Public Workshops with the neighborhoods prior to start of construction

  20. BANNER CASCADE PIPELINE PROJECT  Construction Overview ( con’t )  Weekly Monitoring of the Mitigation Monitoring and Reporting Program (MMRP)  Environmental Monitoring for Creek Crossings (before and during construction)  Monitoring and Compliance with the Storm Water Pollution and Prevention Plan (SWPPP)  Provided Dust Claim form

  21. BANNER CASCADE PIPELINE PROJECT  Construction Overview ( con’t )  Tree Restoration Program followed pipeline installation.  NID personnel met with each property owner to determine the type, quantity, and location of tree replacement.  MMRP required a two for one tree replacement in a 15 gallon container.

  22. BANNER CASCADE PIPELINE PROJECT

  23. BANNER CASCADE PIPELINE PROJECT

  24. BANNER CASCADE PIPELINE PROJECT

  25. BANNER CASCADE PIPELINE PROJECT

  26. BANNER CASCADE PIPELINE PROJECT  Banner Lava Cap Road

  27. BANNER CASCADE PIPELINE PROJECT

  28. BANNER CASCADE PIPELINE PROJECT

  29. BANNER CASCADE PIPELINE PROJECT

  30. BANNER CASCADE PIPELINE PROJECT

  31. BANNER CASCADE PIPELINE PROJECT

  32. BANNER CASCADE PIPELINE PROJECT

  33. BANNER CASCADE PIPELINE PROJECT

  34. BANNER CASCADE PIPELINE PROJECT

  35. BANNER CASCADE PIPELINE PROJECT

  36. BANNER CASCADE PIPELINE PROJECT

  37. BANNER CASCADE PIPELINE PROJECT

  38. BANNER CASCADE PIPELINE PROJECT

  39. BANNER CASCADE PIPELINE PROJECT

  40. BANNER CASCADE PIPELINE PROJECT Questions?

  41. BANNER CASCADE PIPELINE PROJECT Project Objectives:  Safety First  Install the pipeline system and minimize impacts of construction on the residents and community  Provide and make available treated water, raw water and fire protection along the pipeline alignment  Put the raw water system into service as soon as possible

  42. BANNER CASCADE PIPELINE PROJECT Expectations During Construction:  School Bus, Mail Delivery, Garbage and Emergency have been notified of Project  Tree Removal and Clearing  Traffic Detours and Delays  Noise / Dust Control  Minimize Driveway Blockage – Owners Notified Minimum 72 hours Prior to Work  Trench Restoration Followed by Final Overlay

  43. BANNER CASCADE PIPELINE PROJECT Expectations During Construction (con’t):  Restoration Contractor – To Meet with Each Owner Regarding Replacement Tree Location  For everyone’s safety - Residents need to stay out of construction zones during the working hours  Please be Patient – We also want this work completed as soon as possible

  44. BANNER CASCADE PIPELINE PROJECT Miscellaneous:  Use of Local Contractors, Suppliers and Consultants  NID tank site will be used for job trailers and equipment and material storage for project  Waterline from meter to house is the home owners responsibility  Taking treated water and currently have a well – need backflow device or need to abandon well  Mainline extensions can be started after the treated line is in service. Speak with Shannon Bradley for information  Project Website: www.nidbannercascade.com

Recommend


More recommend