POWER UPRATE PROGRAM Mohammed A. Shuaibi Office of Nuclear Reactor Regulation Commission Meeting July 10, 2002 1
• Status • Completed Initiatives • Ongoing Initiatives 2
TYPES OF POWER UPRATES • Measurement Uncertainty Recapture (MUR) • Stretch Power Uprates • Extended Power Uprates (EPUs) 3
NUMBER OF APPLICATIONS 90 80 70 EPU 60 50 Stretch 40 30 20 MUR 10 0 Approved Over Under Review As Expected Over Last 30 Years of May 2002 Next 5 Years 4
MEGAWATTS ELECTRIC 4500 4000 3500 EPU 3000 2500 2000 Stretch 1500 1000 MUR 500 0 Approved Over Under Review As Expected Over Last 30 Years of May 2002 Next 5 Years 5
PRIORITY • High Priority • Among Most Significant Licensing Actions • No Unnecessary Delays 6
ORDER OF PRIORITY • Plant-Specific Applications • Generic Topical Reports • Process Improvements 7
PLANNING/SCHEDULING • 6 Months for MUR Power Uprates • 9 Months for Stretch Power Uprates • 12 Months for EPUs 8
COMPLETED INITIATIVES • Improved Communication • Issued Regulatory Issue Summary for MUR Power Uprates • Improved Schedule Management 9
INITIATIVES IN PROGRESS • Review Standard • Assessment of Past Experience • Effective Utilization of Resources 10
INITIATIVES IN PROGRESS • Inspection Procedure for Extended Power Uprates • Schedules • Centralized Work Planning 11
CONCLUSION • Approved 81 Power Uprates (24 in the last 12 months alone) • Improved Power Uprate Program • Further Improvement Underway 12