pins update september 2013 consultation
play

PINS Update - September 2013 Consultation Place your chosen image - PowerPoint PPT Presentation

PINS Update - September 2013 Consultation Place your chosen image here. The four image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Hinkley Point C


  1. PINS Update - September 2013 Consultation Place your chosen image here. The four image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Hinkley Point C Connection project

  2. Agenda � September Consultation � PEIR – update on EIA since scoping request � Update on other work � Draft DCO � Shadow HRA � Shadow HRA � Work with Local Authorities (PPA) � Other Consents 2

  3. Updated SOCC and Consultation Strategy � Formal Section 42 /47 consultation � 8 week consultation from 3 rd September to 29 th October � Newsletter sent will be sent to � Newsletter sent will be sent to 40,000 people in consultation zone � Letters & info to PILS � Letters & info to other Statutory Consultees and non statutory consultees 3

  4. Consulting and engaging Exhibitions Community Consultation Q&As PILs forums vehicle � Events events Information Information Inspection Inspection hubs points boxes � Static information Local Parish MP authority � Briefings clusters briefings briefings Dedicated meetings � Statutory consultees 4

  5. Consultation Documents (1) 5

  6. Consultation Documents (2) 6

  7. 7

  8. The proposals 8

  9. Feedback � Seeking feedback on � Route of overhead lines � Design of pylons (T or lattice) � Route of underground cables � Layout of cable sealing end compounds � Layout of cable sealing end compounds � Layout of substations � Construction and operation arrangements � Responses by geographical area 9

  10. Draft DCO � Early draft shared with PPA authorities � Draft DCO and explanatory memorandum in suite of documents available. � Draft DCO plans in suite of documents available.

  11. The Proposed Development (1) • Works to construct a new 400kV Teed circuit at Horsey Level including the construction and installation of two new transmission pylons VQ 43R and VQ 44R, the installation of new 400kV electricity conductors between pylons VQ 42, VQ 43R, VQ 44R and connections into the new CSE compounds. • Construction of two 400kV cable sealing end (CSE) compounds at Horsey Level • The installation of approximately 300m section of 400kV underground cables between two CSE compounds on Horsey Level near Bridgwater to allow the circuit to pass beneath existing overhead lines. • • New 400kV overhead line (ZGA) from the existing 275kV overhead line (which would be uprated to 400kV) on New 400kV overhead line (ZGA) from the existing 275kV overhead line (which would be uprated to 400kV) on Horsey Level to the existing 400kV overhead line north of Woolavington. The route is approximately 4.5km in length. • New 400kV overhead line (LD) from a point on the existing 400kV overhead line near Huntspill to a proposed cable sealing end (CSE) compound south of the Mendip Hills adjacent to the M5. The route is approximately 12.5km in length. • Construction of one Cable Sealing End Compound south of the Mendip Hills. • The installation of two 400kV underground cable circuits approximately 8.5km in length from the from the proposed CSE compound south of the Mendip Hills to a proposed 400/132kV substation constructed on land adjacent to Nye Road, Sandford, North Somerset (Sandford Substation).

  12. The Proposed Development (2) • Construction of a 400/132kV Substation on land adjacent to Nye Road, Sandford, North Somerset (Sandford Substation). • Construction of a 132kV connection between Sandford 132kV Substation and the existing 132kV AT Route. The connection consists of approximately 600m of underground cable from Sandford 132kV Substation and 2.3km of overhead line commencing at pylon AT 25R together with the removal of a 1.1km section of the existing AT 132kV overhead line. • Works to connect Sandford 132kV Substation to the existing 132kV N Route overhead line including a 132kV overhead line approximately 250m in length from the existing N Route together with the removal of a 400m section of the existing N Route overhead line. • Construction of 132kV overhead line and underground cable connections from the existing W and Y 132kV Routes into Churchill 132/33kV Substation. • Small extension at Churchill 132kV Substation to accommodate W and Y Route connections.

  13. The Proposed Development (3) • New 400kV overhead line between the proposed Sandford Substation and Seabank Substation. In sections F & G there are two options for the overhead line: a proposed route via Portbury (Option A); and an alternative via Portishead (Option B). The route is approximately 29.6km (Option A) or 30.5km (Option B) in length. • Removal of existing 132kV overhead lines between Bridgwater and Avonmouth substations comprising 47.8km of the F Route between Bridgwater Substation and Portishead 132kV Substation and 5.4km of the G Route between Portishead 132kV Substation and Avonmouth 132kV Substation. • Removal of 8.7km of an existing 132kV overhead line (the W Route) between Nailsea and Portishead 132kV Substation. • • Installation of approximately 10km of 132kV underground cables between a cable sealing end platform pylon Installation of approximately 10km of 132kV underground cables between a cable sealing end platform pylon (CSEPP) south west of Nailsea and Portishead 132kV Substation. • Removal of a short section of an existing 132kV overhead line (the BW Route) at Portishead/Avonmouth (2 options depending upon the route of the 400kV overhead line) and installation of 132kV underground cables in its place together with connections to cable sealing end platform pylons. • Removal of 1.7km of existing 132kV overhead line (the G Route) between Avonmouth 132/33kV Substation and 132kV pylon G31 and installation of approximately 2km of 132kV underground cables in its place together with connections to a cable sealing end platform pylon (CSEPP) and installation of single overhead line span from CSEPP G31R to existing pylon G32. • Removal of each of the existing 132kV overhead lines (the G, DA and BW Routes) in the immediate vicinity of Seabank Substation and installation of 132kV underground cables in their place together with connections to a CSEPP on the G, DA and BW Routes.

  14. The Proposed Development (4) • Modifications at Portishead 132kV Substation to allow replacement of existing overhead line connections into the substation with cable connections. connections into the substation with cable connections. • Modifications at Avonmouth132kV Substation to allow replacement of existing overhead line connections into the substation with cable connections. • Modifications to Seabank 132kV Substation to accommodate the G, DA and BW Route 132kV undergrounding. • Extension of the existing 400kV substation at Seabank to connect the new 400kV overhead line. • Construction of a 400kV substation at Aust , South Gloucestershire.

  15. The Proposed Development (5) • Modifications to existing overhead lines in the vicinity of the proposed Hinkley Point C Power Station consisting of: • The construction and installation of a 400kV overhead line between pylon ZZ 7 and Shurton substation. The route is approximately 1.8km in length. Removal of 1.4km of existing ZZ overhead Line. • The construction and installation of a 400kV overhead line between pylon VQ 4 and Shurton substation. The route is approximately 1.7km in length. Removal of 0.9km of existing VQ substation. The route is approximately 1.7km in length. Removal of 0.9km of existing VQ overhead line • The construction and installation of a new 400 kV overhead line between Hinkley B substation and Shurton substation. The route is approximately 1km in length. • Construction and installation of temporary overhead line diversions including the construction of temporary masts to facilitate the construction of the Proposed Development. • Associated works, including temporary access roads, highway works, construction compounds, (with office accommodation, material, plant and equipment storage and welfare facilities), work sites and ancillary works.

  16. PEIR � Issues raised in Scoping Opinion � NG response documented in PEIR � Schedule at start of each PEIR topic area chapter- explains how the issue has been considered.

  17. Documents � Draft DCO Plans � Project split into 65 sheets � Section 42 – total 585 sheets (land, works, environmental etc) � Application – circa 775 sheets � PEIR � PEIR � Main Document - 1540 pages � Figures - 1473 pages � Appendicies 2972 pages (+ 7466 pages of geology) � Total: 5994 (13,460 including geology)

  18. Shadow HRA � Draft HRA document available as part of PEIR � Discussions ongoing with Natural England

  19. Local Authorities � Ongoing discussions regarding proposed development and EIA. � Extended PPA work packages up to DCO submission, including statements of common ground and section 106 agreements. 106 agreements. � Bristol City Council to now join the PPA

  20. Other Consents Other issues we are currently looking at include. � EA - Flood Defence Consents � IDBs – permanent and temporary ditch crossings � Natural England – working in SSSI � Natural England – working in SSSI � MMO – marine licence (for River Avon) � Natural England - Protected species licences

Recommend


More recommend