phase 2 new building
play

PHASE 2 NEW BUILDING JOHN TYLER COMMUNITY COLLEGE MIDLOTHIAN CAMPUS - PowerPoint PPT Presentation

PHASE 2 NEW BUILDING JOHN TYLER COMMUNITY COLLEGE MIDLOTHIAN CAMPUS Midlothian, VA Dennis Walter Jr. Construction Management AE Senior Thesis Final Presentation, Spring 2010 The Pennsylvania State University Presentation Outline Project


  1. PHASE 2 NEW BUILDING JOHN TYLER COMMUNITY COLLEGE MIDLOTHIAN CAMPUS Midlothian, VA Dennis Walter Jr. Construction Management AE Senior Thesis Final Presentation, Spring 2010 The Pennsylvania State University

  2. Presentation Outline • Project Overview • Introduction of Analyses • Analysis I – Brick Façade • Analysis II – Roofing System • Analysis III – Transformer • Final Conclusions • Questions & Answers

  3. Presentation Outline Client Information Project Location • Project Overview Virginia Community College Systems • Introduction of Analyses John Tyler Community College • Analysis I – Brick Façade Midlothian Campus • Analysis II – Roofing System • Built in 2000 • Single Academic Building • Analysis III – Transformer • Fast expansion � additional academic space • Final Conclusions • Campus-wide green initiative • Questions & Answers 800 Charter Colony Parkway, Midlothian, VA ~16 miles to Richmond, VA

  4. Presentation Outline Project Overview Building Features: Construction Manager: • 8 Laboratory Classrooms Gilbane • 10,000 SF College Library • • Project Overview Architect: • Green Roof Burt Hill • • LEED Certified • Introduction of Analyses Size: • Analysis I – Brick Façade 3 Stories • 60,000 SF • Analysis II – Roofing System • Cost: • Analysis III – Transformer $18.5 million • • Final Conclusions Delivery Method: CM @ Risk; GMP Contract w/ contingency • • Questions & Answers Construction Schedule: May 2008 – July 2009; 14 Months; Classes begin August 24, 2009 •

  5. Presentation Outline Introduction of Analysis Analysis I – Brick Façade • Hand-Laid Brick Exterior Façade vs. Precast Architectural Panels • Project Overview • Structural Calculations to check design of typical exterior bay • Introduction of Analyses • Analysis I – Brick Façade Analysis II – Roofing System • Green Roof and IRMA system vs. “Cool” Roof system • Analysis II – Roofing System • LEED and Heat Transfer comparison • Analysis III – Transformer • Final Conclusions Analysis III – Transformer • Research into building transformers • Questions & Answers • Electrical Calculations to size building transformer

  6. Presentation Outline Analysis I – Brick Façade Structural Breadth • Project Overview Problem Statement: • Hand-Laid Masonry � time and space for construction • Introduction of Analyses • Problems with through wall flashing and drip edge details & • Analysis I – Brick Façade application of spray-on hot fluid applied vapor barrier. • Analysis II – Roofing System • Alternative systems may eliminate problems and ease construction • Analysis III – Transformer Goal: • Matching quality & performance • Final Conclusions • Cost-effective • Questions & Answers • Reduce site congestion and staging area

  7. Presentation Outline SlenderWall Architectural Precast Concrete & Steel Stud Panel Wall System: • Project Overview • Exterior Surface – Thin Architectural Brick Veneer • Introduction of Analyses • Veneer cast into 2 inches of reinforced precast concrete • Inside Surface – 16 gauge, 6 inch steel studs @ 2 ft on center • Analysis I – Brick Façade • Connected with shear studs • Analysis II – Roofing System • Analysis III – Transformer SlenderWall Panel Replaces: • Brick Veneer • Final Conclusions • Spray-on Hot Fluid Applied Vapor Barrier • Questions & Answers • Exterior Sheathing • Exterior Metal Studs

  8. Presentation Outline SlenderWall Panel Sizes: 122 Panels • Project Overview • Most economical at 10’ x 35’ for shipping • • Introduction of Analyses Not recommended over 13’ x 40’ • Connection to Structure: • Analysis I – Brick Façade Welded anchor or plate to exterior spandrel beams of floor above • • Analysis II – Roofing System Bolted connection as soon as panel is set by crane • • Analysis III – Transformer • Final Conclusions • Questions & Answers

  9. Presentation Outline Structural Implications Check W 16x26 Beam for Moment: φ M n = 234 ft*kips > M u = 59.5 ft*kips √ OK • Project Overview Check W 16x26 Beam for Deflection: • Introduction of Analyses Construction Live Load: • Analysis I – Brick Façade Δ C-LL = 0.0827 inches < L/360 = (21*12)/360 = 0.7 inches √ OK • Analysis II – Roofing System Live Load: Δ LL = 0.0647 inches < 0.7 inches √ OK Total Load: Δ Total = 0.251 inches < 0.7 inches √ OK • Analysis III – Transformer Check W 10x45 Column for Axial Load: • Final Conclusions P u = 174.9 kips • Questions & Answers W 10x45 � φ c P n = 306 kips > P u = 174.9 kips √ OK

  10. Presentation Outline Schedule Hand-Laid Brick – Building Enclosure Schedule: • 79 days (start to finish) • Project Overview • Constructed while elevated floor slabs being poured • Introduction of Analyses • Site congestion and large prepping area required • Analysis I – Brick Façade SlenderWall – Building Enclosure Schedule: • Analysis II – Roofing System • Fast erection time � 19 minutes per panel average • 48 days (start to finish) • Analysis III – Transformer • Allows construction to begin after superstructure is complete • Final Conclusions • Saves 16 total days in Building Enclosure Schedule • Questions & Answers • Reduces site congestion • Not on critical path � allows room for unforeseen delays or issues

  11. Presentation Outline Cost Hand-Laid Brick Wall System: • $40.97/SF • Project Overview • Includes: • Introduction of Analyses • Utility brick • Analysis I – Brick Façade • Exterior sheathing • Fluid applied vapor barrier • Analysis II – Roofing System • Exterior studs • Analysis III – Transformer • Miscellaneous finishing • Final Conclusions • Precast sills SlenderWall Precast System: • Questions & Answers • $40.00/SF

  12. Presentation Outline Quality Comparison Quality Comparison Hand-Laid Brick Wall System: SlenderWall Precast System: • Cavity wall system • Project Overview • Barrier wall system • Proven quality in construction and appearance • High Quality Architectural Class “A” Brick Veneer • Introduction of Analyses • Mortar joints wear over time � re-working required • Mock-up • Analysis I – Brick Façade • 100% water-tight and acts as vapor barrier • No leaking or wearing mortar joints • Analysis II – Roofing System • ¾” joint between panels: • Analysis III – Transformer • ¾” backer-rod • Final Conclusions • ½” caulking layer • Joints wear over time � re-working required • Questions & Answers

  13. Presentation Outline Conclusions SlenderWall Precast System: • Project Overview • Building Enclosure Schedule reduction � 16 days • No Structural impact � reduction possible • Introduction of Analyses • Less staging & begins after superstructure • Analysis I – Brick Façade � Reduced site congestion • Analysis II – Roofing System • Cost savings � $15,883 • Analysis III – Transformer • Final Conclusions • Questions & Answers

  14. Presentation Outline Analysis II – Roofing System M.A.E. Requirements • Project Overview Problem Statement: • Inverted Roof Membrane Assembly (IRMA) & Green Roof • Introduction of Analyses installed was expensive • Analysis I – Brick Façade • Alternative systems � may offer similar LEED requirements & upfront cost savings • Analysis II – Roofing System Goal: • Analysis III – Transformer • Similar quality & weatherproofing • Final Conclusions • Cost-effective • Questions & Answers • Meet LEED requirements and provide positive impact

  15. Presentation Outline “Cool” Roof Single-Ply Thermoplastic Polyolefin (TPO) Membrane: • Project Overview • Exterior Surface � White reflective “cool” TPO membrane • Fully adhered to closed-cell poly. iso. insulation • Introduction of Analyses • Poly. Iso. Insulation � R-6/inch • Analysis I – Brick Façade • Fully adhered to composite concrete slab • Analysis II – Roofing System Replaces: • 11,300 SF � Ballasted IRMA Roofing • Analysis III – Transformer • 8,300 SF � Extensive Green Roof over IRMA • Final Conclusions • 19,600 SF � Hot Rubberized Asphalt Waterproofing • Questions & Answers membrane

  16. Presentation Outline “Cool” Roof Design Firestone Building Products: • Project Overview • 60 Mil UltraPly TPO Membrane • UltraPly Adhesive • Introduction of Analyses • 5” Closed-cell Poly. Iso. Insulation (R-6/inch) • Analysis I – Brick Façade • Insulation Adhesive • Analysis II – Roofing System Design: • Analysis III – Transformer • R-30 � 5” of R-6/inch Insulation • Final Conclusions • 10-ft rolls overlapped and heat-welded at seams for continuous waterproof layer • Questions & Answers

  17. Presentation Outline Thermal Properties Design Temperatures � Richmond, VA: • Project Overview • Summer: 75°F Indoor, 95°F Outdoor • Introduction of Analyses • Winter: 70°F Indoor, 14°F Outdoor • Analysis I – Brick Façade • Analysis II – Roofing System • Analysis III – Transformer • Final Conclusions TPO “Cool” Roof: • Questions & Answers • 37% Increase in Summer Heat Gain • 16% Increase in Winter Heat Losses

Recommend


More recommend