partial decoupling on 7 th june 2019
play

Partial decoupling on 7 th June 2019 Incident investigation report - PowerPoint PPT Presentation

MESC 17 th September 2019 Partial decoupling on 7 th June 2019 Incident investigation report Rafael Gmez-Elvira Gonzlez NEMO Co-chair SDAC organisational and contractual hierarchy SDAC Operation of the Single Day-Ahead Coupling as set


  1. MESC 17 th September 2019 Partial decoupling on 7 th June 2019 Incident investigation report Rafael Gómez-Elvira González NEMO Co-chair

  2. SDAC – organisational and contractual hierarchy SDAC Operation of the Single Day-Ahead Coupling as set forth in CACM and according to the DAOA (Single Day-Ahead Coupling Operations Agreement) involving NEMOs and TSOs MRC/SDAC 4MMC/SDAC Operating under MRC procedures (within DAOA/ Operating under 4M MC Master ANDOA) involving only MRC NEMOs and TSOs Agreement and 4M MC procedures involving only 4M MC Regional arrangement A NEMOs and TSOs Regional arrangement B Regional arrangement CWE Operating under: Local arrangements and Local procedures involving only CWE arrangement and procedure NEMOs and TSOs The decoupling incident on 7 th June 2019 only affected MRC, not the 4M MC. It was the first decoupling incident after 1948 successful couplings. The incident was handled by applying the MRC procedures (DAOA/ ANDOA) and the regional/local procedures (fallbacks), which are annexes to the above agreements. The investigation did not detect any gaps in those procedures; however it was discovered that the timings were not fully followed causing problems later in the process. 2

  3. Decoupling on 7 th June 2019 What happened? • Due to IT problems at EPEX, preventing the exchange to submit their order book to the MRC within the procedural timings, CWE and EPEX GB partial decoupling was declared • The following borders were affected: – CWE internal borders – CWE external borders • The “nearly” full decoupling was a consequence of the geographical location of the decoupled NEMO. No different procedural arrangements could have produced a different outcome. Note: MRC areas with same colours stayed coupled, borders labelled with were decoupled 3

  4. Decoupling on 7 th June 2019 Outcome of investigations in root cause and incident management (1/2) • The root cause was a defect in the Trading System of EPEX enabling an unsupported order to be entered by one of its market participants. • This led to technical issues on EPEX side, that prevented the participants to submit their orders and which could not be resolved in time to meet the critical deadline of the Partial Decoupling at 12:40. • The local problem was outside the control of other NEMOs/TSOs. • In the attempt to avoid the decoupling and minimize impacts on the market participants, the agreed procedures (especially timings) were not fully followed on 07/06: − The partial decoupling declaration was postponed by 9 minutes, following information from EPEX that local IT issues were being solved. − Finally the issue could not be solved within these 9 minutes. This led to a further chain of events where subsequent processes were triggered too late. 4

  5. Decoupling on 7 th June 2019 Outcome of investigations in root cause and incident management (2/2) • Following the partial decoupling of CWE and GB from MRC, – Shadow auctions for cross-zonal capacity were run by JAO  For DE-DK2 and NL-NO: Due to the 9 min delay, Shadow Auction results were received too late by market participants making it impossible to consider allocated capacity when bidding at Nord Pool.  Local auctions were run by EPEX for each local national market area. • Further IT issue at EPEX stemming from the technical issues experienced in the morning resulted in publication of erroneous market results in its local auctions. The results were only calculated based on a part of the order books. Therefore, EPEX had to cancel the published results, recalculate and publish final results at 15:38 (instead of 14:45 according to CWE procedure) and therewith after the 15:30 nomination deadline: – Some TSOs managed moving the deadline to 17:00 allowing market participants to nominate based on the final local market results. – Other TSOs could not adjust the 15:30 deadline, meaning that market participants had to nominate without knowing the market results. – In either case TSOs received information necessary for security calculations too late and/or in an inconsistent way 5

  6. Decoupling on 7 th June 2019 Communication with market during incident • As part of the MRC process, the following joint communication towards the market was made: – 12:20 risk of partial decoupling and opening of shadow auction window – 12:49 partial decoupling declared – Between 12:51-13:01 results of shadow auction were published – 13:20 further delay in market results

  7. Decoupling on 7 th June 2019 Lessons learned and investigation report (1/2) Lessons learned • Incidents do happen and parties must learn from them. Incident management procedures are in place and constantly improved based on operational experience. • Ensuring the integrity of IT systems utilized by individual Parties in the joint SDAC process is utterly important, monitoring centralized mapping of risk areas and centralized reporting of integrity testing to be evaluated. • Leading principle: procedures must be followed, as they are designed for the purpose to maintain the functioning of the market even in case of (partial) decoupling. Any derogation, even with good intention, can induce cascade consequences on other processes. If procedures are deemed too stringent, they should be reviewed. 7

  8. Decoupling on 7 th June 2019 Lessons learned and investigation report (2/2) Lessons learned (continuation) • Improvements of procedures are currently being looked at: – Adjust fallback procedures and deadlines to ensure they hold and can be met by all parties including market participants in exceptional circumstances. – Some extra time could be allocated to the ordinary process (calculation of market results) and deadlines to trigger partial and full decoupling could be postponed by overall 10 minutes without endangering other processes. Advanced assessment among the Parties is ongoing on the matter. – Shadow auction process timing is being reviewed and reinforced. • Training of operators (of NEMOs and TSOs) focusing on decoupling situations across MRC must be improved. • There is a need of better preventive communication and training for market participants. • Ensure all affected NEMOs and TSOs are invited to incident committee. Investigation Report A thorough report is about to be finalized for regulators and stakeholders. 8

  9. MESC 17 th September 2019 SDAC - MNAs update Rafael Gómez-Elvira González Co-chair of the SDAC JSC

  10. Overall plan Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2020 11 05 05 JSC 10 11 05 13 Legend: Into force Legal: DAOA 08 28/03 17 Approval proc. Call DD Meeting DD Process 11 Signature proc. 25 Scanned signature DD Completed Missed Contingency DD TSOs: amended proposal for Go-Live window SEC methodologies Proposed Go-Live mechanism: Partially completed DD Go-Live Meeting with EC and NRAs DD ICG SEC implementation MNA project by MNA project, on MNAs 27 Transition into new governance 29 13 27 10 24 07 21 07 21 05 19 03 17 31 04 02 29 14 18 16 13 27 11 08 28 12 25 26 Testing plan OPSCOM MRC CWE MNA MRC Test Elia ext. Cons. Procedures adaptation 02 Test Nordic MNA Harmon. Min max price ElecLink Italian BZs 01 COBRAcable Two additional NEMOLink 31 16 cables FR-GB COBRAcable Hard Brexit Testing plan 09 Procedures adaptation PCR CWE Testing 02/07 Procedures adaptation Nordic System adaptation Nov Procedures adaptation Regional Testing Hansa System adaptation Testing ? Procedures adaptation Polish System adaptation Impact assessment Nov Procedures adaptation Baltic Impact System adaptation ? assessment Procedures adaptation Procedures adaptation IBWT Impact assessment System adaptation 10/20 Testing Approval SEC methodologies NRAs Implementation plan Monitoring of approved SEC and CCM

Recommend


More recommend