om roro pipelines project public meeting
play

Omroro Pipelines Project Public Meeting 15 August 2019 Agenda - PowerPoint PPT Presentation

Omroro Pipelines Project Public Meeting 15 August 2019 Agenda Introductions Wellington Water, Brian Perry Civil, WCC, GWRC Overview of project Wellington Water Progress report Brian Perry Civil Wallace St bulk main


  1. Omāroro Pipelines Project Public Meeting 15 August 2019

  2. Agenda  Introductions ─ Wellington Water, Brian Perry Civil, WCC, GWRC  Overview of project – Wellington Water  Progress report – Brian Perry Civil  Wallace St bulk main works / diversion options – Brian Perry Civil  Questions

  3. Overview  Omāroro Reservoir being built to address growth and improve resilience  Pipelines project is building the water network for the Omāroro Reservoir  Further renewal work being delivered at the same time – intent is no more major water network works in the area for many years

  4. Scope of pipelines work  A new bulk water main  (Hargreaves, Wallace, Howard)  Renewal of local water mains  (Hargreaves, Wallace, Finlay)  Upgrade of storm water pipe  (Rolleston, Wallace)  Renewal of existing sewer (Wallace, Finlay) 

  5. Progress report  Local water renewals on Hargreaves St completed  Bulk water on Hargreaves St underway  Local water renewals on Wallace St underway  Valve chamber at Hargreaves/Wright St corner underway  We’ll keep you informed about impact and progress of work

  6. Construction Plan – estimated dates bulk water main local water mains storm water sewer

  7. Wallace St traffic volumes  Weekday/weekend peak is ~1600/hr (~20,000/day)  10pm – 5am peak is ~400/hr (~1000/nght)  Wright St peak flow is ~200/hr (~1000/day)  June/July 2017, June 2018 traffic counts

  8. Wallace St traffic reduction  VMS boards encourage use of alternative routes  Advertising campaign on radio, social media and other online channels  Advising delivery co’s, taxis, ubers to use alternate routes We anticipate  significant reduction in flow along Wallace St  WCC will continue to monitor

  9. TM options for Wallace St bulk main work Options considered included:  Option 1 : Stop Go on Wallace Street  Option 2 : Partial Diversion, NB Wright St, SB Wallace St  Close Wallace St/ Wright St  Option 3 : Full diversion to Adelaide Rd  Option 4 : Full diversion to Tasman St  Option 5 : Close Wallace St, NB Wright St, SB Tasman St  Option 6 : Close Wallace St, full diversion to Wright St  This is by far the safest and least disruptive option

  10. Option 1: Stop / Go on Wallace St  Advantages ─ No diversion required ─ No changes to bus operations  Ruled out because ─ Stop / Go on Wallace St creates gridlock throughout the network due to tailbacks ─ The modelling confirms intolerable delays even outside of peak hours ─ This option is not feasible

  11. Wallace St bulk water challenge

  12. Option 2: NB Wright St, SB Wallace St  Partial diversion, northbound traffic only onto Wright St  Advantages ─ Only northbound traffic on Wright St  Ruled out because ─ Wallace St road width is insufficient to safely construct bulk water pipes from Hargreaves St to Howard St ─ Due to deep trenches, large diameter pipes leaves insufficient room to allow traffic flow past the work site ─ This option is not feasible

  13. Bus routing options  Divert via Adelaide Rd ─ Too far from current routes, large number of stops displaced ─ High impact on University and Schools  Divert via Tory St / Tasman St ─ Diversion leads to convoluted routes ─ Twice carparks affected & overhead services to resolve (cf Wright St) ─ Significant distance from current routes, stops displaced  Divert via Wright St ─ Short Diversion follows same route (1 stop relocated from Wallace St) ─ Some overhead wires need lifting for double-deckers

  14. Option 3: Full diversion to Adelaide Rd  Wallace St and Wright St both closed to through traffic  Advantages ─ No additional traffic on Wright St  Ruled out because ─ Very long diversion ─ Limited capacity on Adelaide Road for the additional traffic ─ Public transport impact too great – route changes and delays ─ Network resilience compromised if Wallace St + Wright St closed ─ This option is not feasible

  15. Option 4: Full diversion to Tory St/Tasman St  Wallace St and Wright St both closed to through traffic  Advantages ─ No additional traffic on Wright St  Ruled out because ─ Poor connection to road network, particularly north end ─ Very long diversion ─ Tory St / Tasman St ill-suited to anticipated traffic flows ─ More affected residents, more parking displaced ─ Public transport impact significant – long route change

  16. Option 5: NB Wright St, SB Tasman St  Wallace St closed between Hargreaves St and John St  Advantages ─ Only northbound traffic on Wright St  Ruled out because ─ Same reasons as Option 4 ─ Complex diversion due to diverse routes NB/SB ─ Max number of affected residents

  17. Option 6: Full Diversion Wright St  Wallace St closed between Hargreaves St and John St  Disadvantages ─ Significantly increased traffic on Wright St  Advantages ─ Shortest diversion length – least impact on residents/parking ─ Least impact on bus operations and bus users ─ Minimal infrastructure change required ─ This is by far the safest and least disruptive option

  18. Wright St diversion  Traffic diverted to Wright St at Hargreaves St and John St  Car parking removed on one side of Wright St  Buses will use the route  Travel times reliable  Work can proceed safely  Overall disruption shortened with this diversion  Wright St diversion route  Wallace St work area

  19. Wright St bus route  Testing/Investigations ─ Have modelled longest buses using vehicle tracking software ─ Have physically trialled the longest buses by driving the route ─ Wires lifted for double deckers ─ To do: Adjust road camber at corners in Hargreaves St ─ To do: Test drive double deckers ─ Buses will pass each other on Wright St ~16 times a day  Controls ─ Bus stop will be near the laneway to Wallace St ─ Signalised crossing for pedestrians as per Wallace St ─ Additional lighting if required

  20. Wright St diversion bus tracking John St / Wright St intersection Hargreaves St / Wright St intersection

  21. Impacts of diversion on Wright St residents  The additional traffic will be significantly greater than existing flows - expect reduction on current Wallace St traffic  Pedestrian crossing installed near alley through to Wallace St for safe passage across Wright St  Bus stop moved from outside Wallace St dairy to beside new pedestrian crossing in Wright St  Car parks removed on one side (uneven numbers) to provide space for two way traffic  Rubbish collection will be on a different schedule

  22. What can be done to reduce the impact?  Traffic calming measures such as reduced speed limits, traffic lights and minimum lane widths  VMS boards on feeder routes encouraging people to use Adelaide Road as an alternative  Advertising campaign on radio, social media and other online channels telling people to avoid the area  Asking delivery companies, taxis, ubers to use alternate routes  Coupon parking will be changed to residents’ parking in adjacent streets – surveys indicate unused parks exceed ‘lost’ parks

  23. Impacts of work on Wallace St residents  Access to properties from each end of the work site (no through traffic)  Work site moving along the street, different residents impacted as work progresses  No parking on street adjacent to work sites  Full communication with affected residents and businesses  1-1 engagement to address individual issues for access that arise (as we have been doing in Hargreaves St)  Pedestrians will need to use the formal crossing points, this will add distance to some people’s walks

  24. Time considerations in diversion options Alternative 1 – 43 week diversion onto Wright St 11 week full diversion (bulk main works) Nov 2019 – Feb 2020 + 32 week NB diversion (sewer/local water) Feb 2020 – Sep 2020 or Alternative 2 – 23 week diversion onto Wright St 23 week full diversion (bulk main/sewer/local water) Nov 2019 – May 2020

Recommend


More recommend