northern line extension battersea community liaison group
play

Northern Line Extension Battersea Community Liaison Group 21 - PowerPoint PPT Presentation

Northern Line Extension Battersea Community Liaison Group 21 November 2019 1 1 # Actio ion Upda Update Ens nsur ure hi historical CLG m minut nutes This action is in progress and the target is to get website up to 1 and pres an


  1. Northern Line Extension Battersea Community Liaison Group 21 November 2019 1 1

  2. # Actio ion Upda Update Ens nsur ure hi historical CLG m minut nutes This action is in progress and the target is to get website up to 1 and pres an esen entat ations ar are e date by early December upload aded t to t the e TfL web ebsite PM1 0 an and PM2.5 d dust lev evel els 2 Update in today’s presentation for t the B e Bat atter ersea ea site Number er o of veh ehicle e movem emen ents r rel elat ating t to t the e 3 Update in today’s presentation NLE projec ect since e the s e star art o of cons nstruc uction i n in n 201 5 Regular independent monitoring shows that the levels and content of dust in LU’s infrastructure are within Health & Safety Whe hethe her TfL woul uld m moni nitor Executive limits (HSE). Monitoring shows that dust levels are the ai e air qual ality at y at Bat atter ersea ea well below the HSE workplace exposure limits for general dust 4 and nd othe her U Und nderground und (4 mg/m3 ). We also aim to achieve the stricter requirements of stat ations, once t e the s e ser ervice e is the Institute of Occupational Medicine to limit exposures to oper erat ational al respirable dust to below 1 mg/m3, and meet this target at the majority of locations Dat ates es for the n e nex ext f few ew These have been held January; April; July; October 5 Bat atter ersea C ea CLG meet eetings - Is this the right frequency? Should we make them every four circulat ate e to t the C e CLG months instead? Regular reminders are provided to the NLE team on Loit iterin ing outsid ide S Sain insbury’s - maintaining the highest behavioural standards. We expect our 6 rai aised ed at at t the s e site’ e’s reg egular ar team to uphold these high standards and to act as ambassadors ‘T ‘Toolbox’ m ’ meetings for FLO, TfL and the construction industry generally Sen end M May ay H a a copy o y of the e Could not see whether this action was completed so copy sent 7 pres esen entat ation today. Apologies for the delay (if this was not actioned)

  3. 2

  4. Battersea Power Station: Progress Update November 2019 3

  5. Battersea Power Station: Progress Update November 2019 4

  6. Battersea Power Station: Progress Update November 2019 Major Milestone Achieved early November with the handover of the Western Ramp land to Battersea Developers. Within the Western Ramp Structure Fans and large ductwork installed. 5

  7. Battersea Power Station: Progress Update November 2019 Internally • Finishes and Platforms starting to take shape. • Ongoing cladding/finishes , station system and railway systems fit out 6

  8. Battersea Power Station: Progress Update November 2019 Battersea Recognised by The Considerate Constructors Scheme as Excellent . The Team have achieved over 2million man hrs without a reportable injury. 7

  9. Environmental Monitoring Locations Noise Monitoring stations and sensitive receptors 8

  10. BT Monitoring Noise monitoring 9

  11. Environmental Monitoring Locations Glass slide locations 10

  12. BT Monitoring Dust slides results 11

  13. Complaints & Enquiries Summary Stats for Battersea between 16 July and 21 November 2019 Case Status: 3 cases • Active: 0 (0%) • Resolved: 3 (100%) 12

  14. Community Engagement and NLE Skills and Employment Look ahead : we will be supporting a business breakfast event at Sacred Heart 3 students completed work experience on the project from Southwark- 2 from Sacred Heart 1 from St Thomas the Apostle 4 site tours – 2 from St Thomas 2 from Sacred Heart 1 meet the professional event at the Southwark Construction Centre 1 Dragons den activity – Landsdowne school ( Lambeth) 13

  15. Ways to contact us • It is important that calls are logged through the NLE 24/7 helpdesk on 0343 222 2424 (Option 1) • Email nle@tfl.gov.uk • Drop In sessions • Please visit: https://tfl.gov.uk/northern-line-extension 14