North Shore Wastewater Treatment Plant PROJECT UPDATE Joan Liu Tom Sadleir SENIOR PROJECT ENGINEER POLICY COORDINATOR, PUBLIC INVOLVEMENT North Shore Waterfront Liaison Committee, September 14, 2017
Lions Gate Secondary Wastewater Treatment Plant PROJECT UPDATE Andrea Winkler, Program Manager, Public Involvement Paul Dufault, P.Eng., Project Manager North Shore Waterfront Liaison Committee October 22,2015
Regulatory Driven • Integrated Liquid Waste and Resource Management Plan - 2011 • Wastewater Systems Effluent Regulations – 2012 • Secondary Treatment by December 31, 2020 3
3 Components: mponents: • North Shore WWTP • New Conveyance (Pump Station + Pipes) • Decommissioning of existing LGWWTP North Shore Wastewater Treatment Program 4
ADApT Consortium • Acciona Infrastructure Canada • Operating in Canada since 2001 • Head Office in Vancouver • 9 Major Infrastructure Projects in Canada including 5 P3 Projects worth over $ 4.3 Billion • Acciona Agua S.A. • Design, Build, Finance and Operation of Water and Wastewater Plants • Over 300 WWTPs • 35 P3 Type water sector projects 5
6
Remediation 7
Stone Column 8
NSWWTP Project Schedule 9
Conveyance 10
Pump Station 11
Pipes 12
Request for Qualification • The purpose is to invite interested parties to submit responses indicating their interest in, and qualifications for the Project. • Based on the responses a shortlist of up to 3 Proponents will be invited to participate in the Request for Proposals stage Closing Aug 17 2017 13
Request for Proposals • Shortlisted Respondents from the RFQ stage will be invited to submit proposals that will include technical and financial aspects of the project. • RFP Process is to include collaborative discussion relating to technical and commercial matters. • The objective is to select the Preferred Proponent who may be offered the opportunity to enter in to the Project Agreement Sep 27 2017 14
Overall Program Schedule Activity 2016 2017 2018 2019 2020 2021 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 NSWWTP Design Build Finance RFP NSWWTP Design Build Secondary Effluent NSWWTP Commissioning and Handover Conveyance Indicative Design Property Acquisition Conveyance Design Build RFQ Conveyance Design Build RFP Pump Station Design/Construction Pipeline Design/Construction Conveyance System Commissioning Decommissioning Existing Lions Gate WWTP
Consultation and Communications North Shore Wastewater Treatment Plant Metro Vancouver activity since October 2015 • Dec 2015 Education Workshop • Feb 2016 Norgate Open House – Project Update • Dec 2016 Newsletter – Project Update • Apr 2017 Letters to First Nations Lions Gate Public Advisory Committee – Phase 2 • 6 meetings to April 2017 (plant design and opportunities; tour of US facility; construction mitigation, traffic management)
Consultation and Communications North Shore Wastewater Treatment Plant (continued) April 2017: Project Agreement with ACCIONA • ACCIONA assumes responsibility for communications planning, community relations, consultation ACCIONA • Introduced at final LGPAC meeting • May 18, 2017 Open House – Public Impact Mitigation Plan • June 21, 2017 Open House – DNV Development Permit process • Pre-construction activity notification • Ongoing communications
Pump Station + Pipes 18