Ma May 22, 22, 201 2018 M Meeti ting 5/17/18 Meeting Agenda - PowerPoint PPT Presentation

To be presented at Committee meeting scheduled for 5/22/18 Roberts Field Advisory Committee Ma May 22, 22, 201 2018 M Meeti ting 5/17/18 Meeting Agenda Public Input New Playground Project Update and Discussion DPW Update


  1. To be presented at Committee meeting scheduled for 5/22/18 Roberts Field Advisory Committee Ma May 22, 22, 201 2018 M Meeti ting 5/17/18

  2. Meeting Agenda • Public Input • New Playground Project Update and Discussion • DPW Update • “Natural Play Area” Design Discussion • Playground Signage Plan Update • Playground Elements • Fundraising Update & Discussion • Community Build Update & Discussion • Upcoming Committee Meeting Schedule • Meeting Minutes Approval • Adjourn 2

  3. Update From Steve Jahnle, DPW 3

  4. 4

  5. Natural Play Area Design Concept Plan • Climbing Rocks • Central Raised Garden • x’ wide center garden with 24” tall stone masonry wall Sensory plants (community donations) • • Metal kinetic wind sculpture • Hardscape Pathways • Natural hardscape (gravel, stone, pebbles) • Sensory segment (animal tracks) • Tree safe zones – gravel, sand, paver on top, about 4” total • Five Senses Gardens (teardrop shaped) • Phase 1: Grass • Phase 2: Sensory plants • Satellite Butterfly Garden “Five Senses Garden & Labyrinth” • Plants donated by Weston • 20” Gazing Ball • Grassy Meadow • Stone Benches 5

  6. New Playground Project Update and Discussion 6

  7. Roberts Field Advisory Committee Design and Construction Milestones Timing (2018) Project Milestones January 29 - Monday BOS Meeting: Award Contract – BOS/Town Manager Approval Feb 6 – Tuesday 10am Playground Design Working Session (DPW, RFAC, O’Brien and Sons) Feb 12 6pm-7pm Public Input Session – First Draft of the Playground Design Feb 12 – Monday 7pm Roberts Field Advisory Committee Meeting – Town Offices, Room 205 Feb 20 - Tuesday 7pm Roberts Field Advisory Committee Meeting – Town Offices, Room 205 Feb 27 – Tuesday 6pm Public Input Session March 9 - Friday Finalize Playground Design - Town Manager Approval March 16 - Friday Purchase New Equipment (4-6 weeks delivery) March 2018 Begin Corporate Sponsorship and Grant Writing May 6th End Carved Brick Fundraising Campaign May - Month Site Prep May 10 - 14 Equipment Delivery June 2 & 3 – Sat/Sun Community Build Week of June 11 PIP in place, Pathways installed June 23, 2018 - Saturday Playground Grand Opening 5/17/2018 7

  8. Playground Signage Update • Need Dimensions, Designs and Copy • Entryway sign • Kiosk • Welcome • Story/Rules/Playground Map • Park Map? • Bulletin Board • Sponsor & Volunteer Rock • Natural Play Area • Main Sign (double sided) • Small Signs (5x) – senses, Chelmsford Ma Rocks • Trail Signs (5x) 8

  9. Town of Chelmsford Friendship Park at Roberts Field Budget Estimate Construction Budget 5/2/2018 DPW Budget (Prepared by: Steve Jahnle, Assistant Director Chelmsford DPW) Shade Structure $ 10,199 not installed Wood chips $ 8,500 not installed Border $ 11,000 not installed tables $ 1,300 not installed benches $ 1,500 not installed abutter screening $ 5,000 est perimeter fence $ 15,000 est walkways $ 12,000 est O'Brien $ 381,160 equipment/partial install/PIP $ 445,659 Not Budgeted (Prepared by Roberts Field Advisory Committee) Covered Bridge Entryway $ 6,800 Spruce, cedar and pressure treated and sign Volunteer install Natural Play Area $ 20,000 pathway, edging, plants Volunteer install Center Garden Wall & Dirt $ 6,000 Wall=$5600, Dirt=$400 Volunteer install Climbing Rocks & Benches TBD DPW install Engraved Brick Pathway $ 25,000 estimated cost DPW install Signage Signage Kiosk TBD Sign/seat/bulletin board Volunteer install Donor Rock and Plaque $ 2,000 2'10"x2'4" plaque on 26 cu yd stone Volunteer install Natural Play Area $ 300 3' x 4' double sided sign on posts Volunteer install Five Senses Garden $ 100 5x mini signs in garden circle Volunteer install Nature Trail Scavenger Hunt $ 250 5x nature learning signs on trail Volunteer install Metal Kinetic Wind Sculpture $ 500 Materials for sculpture Volunteer install Buddy Bench $ - Girls Scouts buidling and funding Volunteer paid and install Two Sandbox Diggers $ 1,843 Volunteer install Original Picnic Table Rehab TBD DPW install Original Bench Rehab TBD DPW install 9 $ 62,793

  10. Fundraising Update & Discussion Freindship Park Fundraising Recap 5/17/2018 Campaign Amount Brick Campaign $ 29,611.65 Sponsorships Equipment $ 19,080.00 Premier $ 23,000.00 Go Fund Me $ 126.00 Restaurants $ - Merchandise $ - Existing* $ 10,042.00 Grants $ - Total Proceeds $ 81,859.65 *$2500 KDK Silver Sponsorship in Premier Sponsorship amount. 10

  11. Community Build Update & Discussion • June 2-3, 7am-4pm • Two shifts (7am-noon, noon – 4pm) • Volunteer Needs • 11 equipment assembly teams • Preview instructions (pdf available) • Registration and Support Volunteers (27 registrations so far) • Registration table – waiver, name tags • Equipment Needs • 3/8 ratchet driver, A frame ladder, level, metal wheelbarrows, round nosed shovels • Food and Water Needs • Registration Forms and Scheduling Portal Needed • Potential Teams Contacted • Police, Fire, CYB, CYL, Pop Warner, CTM, Towing 11

  12. Next Meeting Date • Next Steps: Site Prep (May), Natural Play Area Design, Signage Plan, Community Build (June 2 & 3), Maintenance Plan Document • Next Scheduled Meeting Date: • June meeting available dates 12

  13. Meeting Minutes Approval 13