luas cross city
play

Luas Cross City Why? Background to Luas Cross City (LCC) What? - PowerPoint PPT Presentation

TII National Roads Conference 2016 28 th September 2016 Luas Cross City Why? Background to Luas Cross City (LCC) What? The works involved in delivering LCC How? Key Issues for the delivery phase Where? ..have we got to so


  1. TII National Roads Conference 2016 28 th September 2016 Luas Cross City

  2.  Why? Background to Luas Cross City (LCC)  What? The works involved in delivering LCC  How? Key Issues for the delivery phase  Where? …..have we got to so far

  3. NTA Transport Strategy 2016 - 2035 Luas Finglas Luas Cross City Luas Lucan Luas Poolbeg Luas Red Luas Line Green Line 2035 Metropolitan Light Rail Network (Source: NTA Draft Transport Strategy 2016 – 2035) Luas Bray

  4. Benefits of LCC

  5. What does LCC involve?

  6. What does LCC involve? Luas Cross City Aerial Map Total route length 5.6km - equating to approximately 13.3km of single track • equivalent 6 km off-street between Broadstone and Broombridge • 2.1 km at Broombridge depot for tram stabling • 5.2 km of embedded on street track in city centre •

  7. LCC Programme

  8. Heritage Works – KN Networks Services

  9. Cellar Works – KN Networks Services

  10. Utility Works – GMC Utilities • c.70km of new ducting and pipe-work • 2 km of Sewer re-lining • Construction of 50 no. new drainage manholes • Building Service connections

  11. Utility Works

  12. Main Infrastructure Works – Sisk-Steconfer Joint Venture - HV and LV ducting and chambers - Track installation - Ballasted - Embedded Rails - Structural Works - Depot Construction - Stop Construction - Traffic Signalling - OCS Installation

  13. Typical Methodology Overhead wires erected at night Installation of facade at end of program Install Traffic Management fixings and fencing Works Completion Remove Traffic Management Access Crossings maintained Isolated works for pole installation Replace road surface New Road Surfacing with new Plane out carriageway Concrete Excavations Track Assembly & rebar Secondary ducting trackslab & Pipelaying works and new Concrete foundation granite paving Hardcore Fill

  14. Key Issues for Delivery Site Access / Traffic Management LCC Traffic Forum (~Monthly) NTA/DCC/TII/Dublin Bus/ Bus Eireann / An Garda Síochána LCC Traffic Group (Weekly) NTA/DCC/TII/Dublin Bus/ Bus Eireann / An Garda Síochána Contractors’ Traffic Management Application to DCC Roadworks Control Unit

  15. Key Issues for Delivery KEY PILLARS Communications Public Office • Web-site - Traffic • updates, works progress, maps CRM database – • members of public and other interested parties Local liaison officers – • direct contact with retailers/shops/reside nts Sponsorships – Local • communities, Dublin Town events

  16. Works Progress – end of August 2016 NORTH SIDE OF LIFFEY SOUTH SIDE OF LIFFEY

  17. Works Progress – end of June 2016

  18. Works Progress – end of June 2016

  19. Works Progress – end of June 2016

  20. Works Progress – end of June 2016

  21. Works Progress – end of June 2016

  22. Works Progress – end of June 2016

  23. Works Progress – end of June 2016

  24. Works Progress – end of June 2016

  25. Works Progress – end of June 2016

  26. Thank you

Recommend


More recommend