LONG-RANGE FACILITIES PLANNING UPDATE E L E ME NT ARY SCHOOL - PowerPoint PPT Presentation

LONG-RANGE FACILITIES PLANNING UPDATE E L E ME NT ARY SCHOOL S NE WT ON, MASSACHUSE T T S 3, 2015 Se pte mbe r UPDATE OF LONG-RANGE PLAN Pla nning is dyna mic & re spo nsive to ne w info rma tio n/ o ppo rtunitie s F


  1. LONG-RANGE FACILITIES PLANNING UPDATE E L E ME NT ARY SCHOOL S NE WT ON, MASSACHUSE T T S 3, 2015 Se pte mbe r

  2. UPDATE OF LONG-RANGE PLAN • Pla nning is dyna mic & re spo nsive to ne w info rma tio n/ o ppo rtunitie s • F Y16 Re c o mme nda tio n fo c use s o n Aq uina s Pro pe rty Re -use a nd the c ha ng e s to the pro je c t se q ue nc e • Re visio n o f time line fo r Mid -Ra ng e Pro je c ts due to e xpa nde d c a pa c ity o n the no rth-side & e xte rna l fa c to rs

  3. SCHOOL PROJECT TIMELINE Fiscal School Pre-K and Swing New School / Major Renovation Renovations / Additions Year Year Ed Center Space Lincoln- Carr / Angier Cabot Lincoln-Eliot Ward Horace Eliot as Memorial- Under- Ed Center Zervas NECP (PreK) Countryside Franklin Mason-Rice Burr Peirce Bowen Williams Lincoln- (MSBA) (MSBA) (MSBA) (MSBA) Mann Swing Spaulding wood and NECP Eliot Space 1919 1954 1929 Aquinas 1928 Aquinas 1965 1939 1953 1939 1959 1967 1951 1952 1950 1954 1924 1928 FY12 2011-12 Start MSBA +2 Classrooms +1 Classroom +1 Classroom Plans to Vacate FY13 2012-13 Feasibility Feasibility FY14 2013-14 Design Feasibility +1 Classrooms +1 Classroom; +4 Classrooms +1 Classrooms +3 Classrooms Construction PreK to EDC (NET) Start MSBA FY15 2014-15 Construction Design Feasibility +1 Classroom; Angier PreK to EDC Students FY16 2015-16 Design Feasibility +1 Classroom; PreK to EDC Completed: +3 Construction Start MSBA Replace Zervas Classrooms Windows Students FY17 2016-17 Feasibility Design NECP Move to JAN '16 Aquinas PreK at Aquinas CURRENT CIP GROUP - CITY FUNDING SEP '16 FY18 2017-18 Completed: +8 Construction Construction Cabot Students Classrooms Design SEP '17 FY19 2018-19 PreK Complete Completed: +4 Lincoln-Eliot SEP '19 Classrooms FY20 2019-20 Construction Moves to Carr: Feasibility JAN '19 +1 Classrooms SEP '19 FY21 2020-21 Start MSBA Design Feasibility FY22 2021-22 Completed: +6 Feasibility Construction Design Not Available Classrooms SEP '21 NEXT CIP GROUP - CITY FUNDING FY23 2022-23 Design Completed: +0 Construction Countryside Classrooms Feasibility SEP '22 FY24 2023-24 Construction Completed +0 Ward Classrooms Design Feasibility SEP '23 FY25 2024-25 Design Feasibility FY26 2025-26 Completed: +4 Construction Franklin Design SEP '25 FY27 2026-27 +0 New Construction Feasibility Mason-Rice Classrooms SEP '26 NEXT CIP GROUP - CITY FUNDING FY28 2027-28 +1 New Construction Design Feasibility Burr Classrooms SEP '27 FY29 2028-29 +0 New Construction Design Feasibility Peirce Classrooms SEP '28 FY30 2029-30 +3 New Construction Design Feasibility Bowen Classrooms SEP '29 FY31 2030-31 +0 New Construction Design Feasibility Williams Classrooms SEP '30 FY32 2030-32 +3 New Construction Design Memorial- Classrooms Spaulding SEP '31 FY33 2032-33 +0 New Construction Underwood Classrooms SEP '32 FY34 2033-34 +0 New Classrooms SEP '33

  4. FY17-FY21 MAJOR RENOVATION • Ang ie r o pe ns Ja nua ry 2016 • Ze rva s o pe ns Se pte mb e r 2017 • Ca b o t o pe ns Ja nua ry 2019 • L inc o ln-E lio t a nd Ne wto n E a rly Childho o d o pe ns Se pte mb e r 2021

  5. FY17-FY21 MID-RANGE PROJECTS • Ne wto n E a rly Childho o d Pro g ra m • Be g in fe a sib ility & site pla nning • Re pla c e windo ws in F Y16 to re lo c a te pre sc ho o l to Aq uina s ma in b uilding • Re no va tio n o f pe rma ne nt Pre K spa c e a t Aq uina s • L inc o ln-E lio t Swing Spa c e • Co untryside • Ma inta in sc ho o l size • Re pla c e mo dula rs a nd a ddre ss o the r e duc a tio na l pro g ra m ne e ds

  6. RESULTS BY FY16 FY12 FY13 FY14 FY15 FY16 2011-12 2012-13 2013-14 2014-15 2015-16 Total School Projects Total # of Schools Completed 0 0 0 1 2 Major and Mid-Sized Completed Projects Carr Angier Cumulative # of Classrooms Added 0 0 0 0 3 Number of Modulars in use 20 29 29 29 29 Enrollment Projected Enrollment 5,687 5,790 5,799 5,833 5,859 Projected Number of Classes 256 263 273 283 283 School Enrollment Capacity 5,520 5,589 5,727 5,775 5,846 Enrolled % of Capacity 103% 104% 101% 101% 100% Annual Classroom Utilization Classrooms Available (including modulars) 278 283 300 311 315 Total Classrooms Needed 316 323 333 343 342 Suplus (+) / Deficit (-) -38 -40 -33 -32 -27

  7. RESULTS BY FY21 (FIVE YEARS) FY17 FY18 FY19 FY20 FY21 2016-17 2017-18 2018-19 2019-20 2020-21 Total School Projects Total # of Schools Completed 2 3 4 4 4 Major and Mid-Sized Completed Projects Zervas Cabot Horace Mann (Carr) Cumulative # of Classrooms Added 3 11 15 16 16 Number of Modulars in use 29 24 20 16 16 Enrollment Projected Enrollment 5,987 5,987 6,019 6,001 6,013 Projected Number of Classes 285 285 285 283 284 School Enrollment Capacity 5,866 6,057 6,110 6,155 6,155 Enrolled % of Capacity 102% 99% 99% 97% 98% Annual Classroom Utilization Classrooms Available (including modulars) 316 325 331 331 330 Total Classrooms Needed 344 344 345 342 343 Suplus (+) / Deficit (-) -28 -19 -14 -11 -13

  8. RESULTS BY FY26 (TEN YEARS) FY22 FY23 FY24 FY25 FY26 2021-22 2022-23 2023-24 2024-25 2025-26 Total School Projects Total # of Schools Completed 5 6 7 7 8 Major and Mid-Sized Completed Projects Lincoln- Lincoln-Eliot Countryside Ward Eliot/NECP Swing Space Cumulative # of Classrooms Added 22 22 22 22 25 Number of Modulars in use 16 12 12 12 12 Enrollment Projected Enrollment 6,026 6,029 6,031 6,010 6,010 Projected Number of Classes 286 286 285 285 285 School Enrollment Capacity 6,230 6,240 6,197 6,197 6,271 % Capacity 97% 97% 97% 97% 96% Annual Classroom Utilization Classrooms Available (including modulars) 339 342 346 346 348 Total Classrooms Needed 345 344 343 343 343 Suplus (+) / Deficit (-) -6 -2 3 3 5

  9. RESULTS BY FY31 (FIFTEEN YEARS) FY27 FY28 FY29 FY30 FY31 2026-27 2027-28 2028-29 2029-30 2030-31 Total School Projects Total # of Schools Completed 9 10 11 12 13 Major and Mid-Sized Completed Projects Franklin Mason-Rice Burr Peirce Bowen Cumulative # of Classrooms Added 25 26 26 29 29 Number of Modulars in use 8 6 4 0 0 Enrollment Projected Enrollment n/a n/a n/a n/a n/a Projected Number of Classes n/a n/a n/a n/a n/a School Enrollment Capacity 6,271 6,271 6,271 6,385 6,385 % Capacity n/a n/a n/a n/a n/a Annual Classroom Utilization Classrooms Available (including modulars) n/a n/a n/a n/a n/a Total Classrooms Needed n/a n/a n/a n/a n/a Suplus (+) / Deficit (-) n/a n/a n/a n/a n/a

  10. OVERALL RESULTS BY FY33 ELEMENTARY Date Future Future Additional Modulars SCHOOL Complete Capacity Classrooms Classrooms Replaced Angier Jan-16 465 22 3 Zervas Sep-17 490 24 8 5 Cabot Jan-18 480 24 4 4 Horace Mann/Carr Sep-14 390 19 1 4 Lincoln-Eliot Sep-21 490 24 6 Countryside Sep-23 460 22 0 4 Ward Sep-25 396 18 3 PLAN MID-POINT 25 17 Franklin Sep-26 437 20 0 Mason-Rice Sep-27 440 20 1 4 Burr Sep-28 391 18 0 2 Peirce Sep-29 400 18 3 2 Bowen Sep-30 440 20 0 4 Memorial-Spaulding Sep-31 462 22 0 Williams Sep-32 400 18 3 Underwood Sep-33 300 14 0 LATER PLAN PROJECTS 7 12 TOTAL 6,441 303 32 29

  11. COORDINATION WITH FY17-21 CIP • CI P F unding pla n is in dra ft sta g e F unding fo r ma jo r a nd mid-size d pro je c ts FY2017 FY2018 FY2019 FY2020 FY2021 $ 37,585,000 $ 21,000,000 $ 24,500,000 $ 10,000,000 $ 25,000,000 • Additio na l ~$3M in c usto ma ry ma inte na nc e pro je c ts