kingstowne section 36a
play

Kingstowne Section 36A Office Building with Parking Garage Fairfax - PowerPoint PPT Presentation

Kingstowne Section 36A Office Building with Parking Garage Fairfax County, VA James Chavanic PSU AE Senior Thesis Structural April 8, 2013 Image Provided By DCS Design Image Provided By DCS Design P RESENTATION O UTLINE BUILDING


  1. Kingstowne Section 36A Office Building with Parking Garage Fairfax County, VA James Chavanic PSU AE Senior Thesis Structural April 8, 2013 Image Provided By DCS Design Image Provided By DCS Design

  2. P RESENTATION O UTLINE  BUILDING INTRODUCTION  EXISTING STRUCTURE  THESIS PROPOSAL  STRUCTURAL DEPTH  BREADTH 1: SITE REDESIGN  BREADTH 2: FAÇADE REDESIGN (GLAZING)  RESULTS  QUESTIONS Image Provided By DCS Design Image Provided By DCS Design

  3. P ROJECT I NFORMATION P RESENTATION O UTLINE BUILDING OVERVIEW  200,000 SF  8 Stories (4 Parking, 4 Office)  BUILDING INTRODUCTION  Height = 101’ - 2” (86’ - 11” from Avg. Grade)   $ 19 Million EXISTING STRUCTURE  Construction: February 2012 – May 2013  THESIS PROPOSAL  STRUCTURAL DEPTH PROJECT TEAM  BREADTH 1: SITE REDESIGN Owner: Halle Companies  BREADTH 2: FAÇADE REDESIGN (GLAZING) Architect: Davis, Carter, Scott Ltd. (DCS Design)  RESULTS GC: L.F. Jennings Inc.  QUESTIONS Civil Eng.: Tri-Tek Engineering Mech. Eng.: Jordan & Skala Engineers Struct. Eng.: Cagley & Associates Image From Bing Maps

  4. S ITE R ELATIONSHIP N P RESENTATION O UTLINE  BUILDING INTRODUCTION  EXISTING STRUCTURE  THESIS PROPOSAL  STRUCTURAL DEPTH  BREADTH 1: SITE REDESIGN  BREADTH 2: FAÇADE REDESIGN (GLAZING)  RESULTS  QUESTIONS 27’ Difference Original Images: DCS Design

  5. E XISTING S TRUCTURE P RESENTATION O UTLINE ROOF  3.25” LW Concrete on 2” 18 GA Composite Deck (Mech. Areas)  BUILDING INTRODUCTION  3” x 20 GA Type N Roof Deck (Remaining Areas)  EXISTING STRUCTURE   THESIS PROPOSAL Spans   A- C 45’ - 0” , C - D 36’ - 6” , D - F 43’ - 6” STRUCTURAL DEPTH  East West Direction 28’ - 6”  BREADTH 1: SITE REDESIGN  BREADTH 2: FAÇADE REDESIGN (GLAZING)  Composite action in mechanical areas  RESULTS   (4) 17,000 lb. Roof-top Mechanical Units QUESTIONS Original Image: Cagley & Associates

  6. E XISTING S TRUCTURE P RESENTATION O UTLINE OFFICE LEVELS 2 THROUGH 4  2” x 18 GA Composite Deck  3.25 ” LW Concrete Topping (3000 psi)  BUILDING INTRODUCTION  Spans  EXISTING STRUCTURE  A- C 45’ - 0” , C - D 36’ - 6” , D - F 43’ -6 ”   East West Direction 28’ - 6” THESIS PROPOSAL  Composite action beams and girders  STRUCTURAL DEPTH  13’ - 4” Floor to floor height  BREADTH 1: SITE REDESIGN  BREADTH 2: FAÇADE REDESIGN (GLAZING)  Lateral System   RESULTS Moment Frames  Concentrically Braced Frames  QUESTIONS  Eccentrically Braced Frames Original Image: Cagley & Associates

  7. E XISTING S TRUCTURE P RESENTATION O UTLINE PARKING LEVELS AND OL1  8” Thick concrete flat slab  #4 @ 12” O.C. Bottom Mat  BUILDING INTRODUCTION  f ’ c = 5000 psi  EXISTING STRUCTURE  Typical bay is 28’ - 6” x 29’ - 0”   24” x 24” Typical columns THESIS PROPOSAL  10- 8” Floor to floor height  STRUCTURAL DEPTH  BREADTH 1: SITE REDESIGN  Lateral System  BREADTH 2: FAÇADE REDESIGN (GLAZING)  12 Shear walls   RESULTS 12” Thick  f’ c = 5000 psi  QUESTIONS  #5 @ 12” O.C. Typical E.F. Original Image: Cagley & Associates

  8. E XISTING S TRUCTURE P RESENTATION O UTLINE FOUNDATION  All Concrete f’c = 3000 psi  48” Thick concrete mat foundations  BUILDING INTRODUCTION  Spread Footings  EXISTING STRUCTURE  7000 psi bearing capacity   8’ x 8’ to 16’ x 24’ THESIS PROPOSAL  STRUCTURAL DEPTH  Strip Footings  BREADTH 1: SITE REDESIGN  2500 psi bearing capacity  BREADTH 2: FAÇADE REDESIGN (GLAZING)   RESULTS Geopiers (Rammed Aggregate Piers)  30” Dia. 16’ deep  QUESTIONS  100 k capacity each Original Image: Cagley & Associates

  9. P ROPOSED W ORK P RESENTATION O UTLINE SETTING THE STAGE  Currently, no tenant selected  BUILDING INTRODUCTION  Police / Emergency services for Fairfax County, VA  EXISTING STRUCTURE www.defense.gov  THESIS PROPOSAL  Risk Category IV (Originally Category II)  STRUCTURAL DEPTH   U.S. Department of Defense Standards BREADTH 1: SITE REDESIGN  BREADTH 2: FAÇADE REDESIGN (GLAZING)  RESULTS  QUESTIONS www.asce.org www.gsa.gov

  10. P ROPOSED W ORK BREADTH 1: SITE REDESIGN P RESENTATION O UTLINE  Assess potential security issues STRUCTURAL DEPTH  Goal  Reinforced concrete  Reduce risks to human occupants  Maintain flat slab system  Gravity Design  BUILDING INTRODUCTION  Use designed OL1 for OL2 - OL4 BREADTH 2: FACADE REDESIGN  EXISTING STRUCTURE  Design edge beams  Design glazing for worst scenario from site redesign  THESIS PROPOSAL  Design roof structure  Goals   STRUCTURAL DEPTH Lateral Design  Protect occupants of the building  Ordinarily reinforced concrete shear walls  BREADTH 1: SITE REDESIGN  Maintain thermal performance  Progressive Collapse Design  BREADTH 2: FAÇADE REDESIGN (GLAZING)  Satisfy requirements adopted by the U.S. Dept. of Defense  RESULTS MAE REQUIREMENTS  Goals   QUESTIONS  AE 530 – Computer Modeling of Building Structures Reduce cost of structural system   AE 538 – Earthquake Engineering Simplify construction  AE 542 – Building Enclosure Science and Design

  11. G RAVITY D ESIGN DESIGN CONSIDERATIONS  P RESENTATION O UTLINE Risk Category IV GRAVITY SYSTEM  I snow = 1.2  2 – way flat slab   All Concrete f’ c = 5000 psi Office levels   BUILDING INTRODUCTION Significantly cheaper than existing steel system   Façade Load Reduces floor-to-floor height  EXISTING STRUCTURE  Assume 100 psf  THESIS PROPOSAL  Perimeter edge beams  STRUCTURAL DEPTH   Floor to floor height Creates moment frames   BREADTH 1: SITE REDESIGN  9’ - 0” Floor to ceiling Depth constrained to allowed structure plenum  17” Clear space in existing Office structure  BREADTH 2: FAÇADE REDESIGN (GLAZING)   Provide 24” below flat slab All columns continued from parking levels through office levels  RESULTS   8” slab system 2 additional column lines  QUESTIONS  Result = 11’ - 8”   Reduce overall by 7’ - 8” Check strength of existing column designs  Higher loads

  12. G RAVITY D ESIGN P RESENTATION O UTLINE DESIGN OF EDGE BEAMS  GSA Design Guide Appendix B.3  2(DL + 0.5L)  BUILDING INTRODUCTION  9’ - 0” Tributary Width  EXISTING STRUCTURE  20” Trial Depth (2.5*h)  THESIS PROPOSAL  Gives sufficient beam/slab ratio  STRUCTURAL DEPTH  ACI Moment Coefficients   East – West direction BREADTH 1: SITE REDESIGN  Frame Analysis  BREADTH 2: FAÇADE REDESIGN (GLAZING)  North – South direction  RESULTS  Pattern Loading  QUESTIONS

  13. G RAVITY D ESIGN P RESENTATION O UTLINE DESIGN/CHECK OF COLUMNS  GSA Design Guide Appendix B.3  2(DL + 0.5L)  BUILDING INTRODUCTION  Live load reduction considered  EXISTING STRUCTURE  Spliced at OL1  THESIS PROPOSAL  “Check” below  STRUCTURAL DEPTH  “Design” above   Unbalanced moment from slabs BREADTH 1: SITE REDESIGN  Spreadsheet  BREADTH 2: FAÇADE REDESIGN (GLAZING)  Typical columns  RESULTS  Highest load columns  QUESTIONS  Typically 129% of Original A s

  14. SOIL LOAD L ATERAL D ESIGN P RESENTATION O UTLINE  BUILDING INTRODUCTION  EXISTING STRUCTURE  THESIS PROPOSAL WIND LOAD SEISMIC LOAD  STRUCTURAL DEPTH  120 MPH (Cat. IV)  Site Class = D  BREADTH 1: SITE REDESIGN  Exposure B  I seismic = 1.5  BREADTH 2: FAÇADE REDESIGN (GLAZING)  GC pi  SDC = C   Office = 0.18  RESULTS R = 5 (ORC Walls)  Parking = 0.55  C s = 0.0249  QUESTIONS  Cont. Base Shear  Weight = 39,017 k  765 k  Base Shear  North Blowing  972 k

  15. L ATERAL D ESIGN P RESENTATION O UTLINE ETABS MODEL  All elements modeled  Idealize parking levels  BUILDING INTRODUCTION  Total height = 91’ - 4”  EXISTING STRUCTURE  Effects of cracked sections  THESIS PROPOSAL  Rigid diaphragms  STRUCTURAL DEPTH  Columns in-line with walls   Walls BREADTH 1: SITE REDESIGN  Membrane elements  BREADTH 2: FAÇADE REDESIGN (GLAZING)  18” x 18” maximum mesh  RESULTS  Seismic loads control  QUESTIONS  Extreme torsional irregularity N-S direction

  16. L ATERAL D ESIGN P RESENTATION O UTLINE SHEAR WALL DESIGN  SW7 – SW12 (Same Design)  SW7 Worst Case  BUILDING INTRODUCTION  Seismic N-S Controls  EXISTING STRUCTURE  Primarily Soil Load  THESIS PROPOSAL  SW1 – SW3 (Same Design)  STRUCTURAL DEPTH  SW1 Worst Case   Seismic N-S Controls BREADTH 1: SITE REDESIGN  SW5, SW6  BREADTH 2: FAÇADE REDESIGN (GLAZING)  Not in scope  RESULTS  SW4  QUESTIONS  Architectural interference  Seismic E-W Controls

Recommend


More recommend