joint public workshop
play

Joint Public Workshop June 26, 2019 Project Overview I-93 Typical - PowerPoint PPT Presentation

Bow Concord I-93 Improvements T-A000(018) 13742 Joint Public Workshop June 26, 2019 Project Overview I-93 Typical Sections Existing Interstate 93 Proposed Interstate 93 Project Goals Red List Bridges Pedestrian/Bicycle Accommodation


  1. Bow Concord I-93 Improvements T-A000(018) 13742 Joint Public Workshop June 26, 2019

  2. Project Overview

  3. I-93 Typical Sections Existing Interstate 93 Proposed Interstate 93

  4. Project Goals • Red List Bridges • Pedestrian/Bicycle Accommodation • Address Geometric Issues • Provide Stormwater Treatment • Address Operational Issues • Minimize Resource Impacts • Maintain Access • Minimize Property Impacts

  5. Recommended Preferred Alternative I-89 Area Exit 12 Area Exit 13 Area Exit 14/15 Area Concept K Concept F Concept B Concept F2

  6. Exit 14/15 Area

  7. Exit 14 / 15 Area - Proposed

  8. Exit 15 - Proposed • Cloverstack • Eliminates 2 Loop ramps • Eliminates 4 weaves • Maintains all Access

  9. Exit 14 - Proposed • Modified Diamond • Maintains access to Stickney Ave • Eliminates Northbound Entrance Ramp • Avoids Historic Buildings • Easterly shift of I-93 • Avoids Unitil Sub-station • Avoids Railroad corridor

  10. Exit 14 - Proposed LOUDON ROAD – TYPICAL SECTION

  11. Concord Comments/Concerns 1. Clear brush along I-93 2. Remove Highway Garage complex on Stickney Avenue 3. Consistency with Concord’s Vision for I -93 4. Pedestrian Access from Downtown to the Merrimack River 5. Increased Traffic on Fort Eddy Road 6. Loss of the Northbound Entrance ramp at Exit 14

  12. Concord Comments/Concerns 1. Clear brush along I-93 City is coordinating with Bureau of Turnpikes to get permission for the City to do the clearing. 2. Remove Highway Garage complex on Stickney Avenue Separate project and not associated with Bow Concord. Funded through the State budget.

  13. 3. Consistency with Concord’s Vision for I -93 EXITS 14/15 AREAS CONCEPT F3 • Impacts Include: • Functionally identical to Concept F2 ✓ 16-20 Month closure of Loudon Road • Loudon Road over I-93 (carries 20,000+ vehicles per day) • Relocation of Railroad possible ✓ Short term closure of Exit 14 NB Off Ramp • Access to Ralph Pill via Stickney Ave. ✓ Long term closure of both Exit 14 SB Ramps • Additional $41M ✓ Utilities under Loudon Road

  14. 3. Consistency with Concord’s Vision for I -93 EXITS 14/15 AREAS CONCEPT F3 WITH RAILROAD RELOCATION • Relocate Railroad East close to I-93 • Railroad Relocation Impacts include: • Access to Ralph Pill via Storrs Street • Unitil Substation • Historic Building • Additional $19.2M • Bus Depot

  15. 3. Consistency with Concord’s Vision for I -93 EXITS 14/15 AREAS CONCEPT F3 Ralph Pill Building

  16. 3. Consistency with Concord’s Vision for I -93 EXITS 14/15 AREAS CONCEPT F3 Stickney SB Main Ave Storrs Ramps Street Street Existing Fort RR Relocated Eddy RR Road I-93 Merrimack River Loudon Road Profile

  17. 3. Consistency with Concord’s Vision for I -93 EXITS 14/15 AREAS CONCEPT F3 Loudon Road I-93 Northbound Profile

  18. Utilities Loudon Road Underground Utilities Water (2) Sewer Gas Fire Alarm Telephone Cable Telecommunications

  19. 4. Pedestrian Access from Downtown to the Merrimack River

  20. 4. Pedestrian Access from Downtown to the Merrimack River Pedestrian Bridge – Option 1 Existing Storrs RR Street I-93 Merrimack River Note: Pedestrian could be lowered about 3’ for Concept F3.

  21. 4. Pedestrian Access from Downtown to the Merrimack River Pedestrian Bridge – Option 2 Existing Storrs RR Street I-93 Merrimack River Note: Pedestrian could be lowered about 4’ for Concept F3.

  22. 5. Increased Traffic on Fort Eddy Road Design Year 2035 6. Loss of the Northbound Entrance ramp at Exit 14 (92 vph) (302 vph) (366 vph) (885 vph) No Build AM Peak (289 vph) (1,103 vph) (238 vph) (157 vph) (837 vph) (1,025 vph) No Build PM Peak (805 vph) (838 vph)

  23. Existing Route from Downtown to Northbound I-93

  24. Future Route from Downtown to Northbound I-93 Adds 1/4 mile Adds 1/3 mile

  25. Existing Route from Fort Eddy Road to Northbound I-93

  26. Future Route from Fort Eddy Road to Northbound I-93 Adds 1/2 mile Adds 1/2 mile

  27. Project Costs Bow Concord I-93 Improvements Project Preferred Alternative Cost Matrix (Millions $) Engineering SEGMENT Concept Construction $ Right-of-Way $ and Mitigation $ Utility $ Total Project $ Permitting $ K $62.0 $1.16 $6.20 $0.62 $0.00 $70.0 I-89 Area F $29.5 $0.09 $2.95 $0.30 $1.00 $33.9 Exit 12 B $34.8 $0.36 $3.48 $0.35 $0.00 $39.0 Exit 13 F2 $111.2 $0.47 $11.12 $1.11 $1.00 $125.0 Exit 14/15 $237.5 $2.1 $23.8 $2.4 $2.0 $267.9 Total (Assessed Value) (10% of Constr.) (1% of Constr + any Major Items.)

  28. Potential Costs Engineering SEGMENT Concept Construction $ Right-of-Way $ and Mitigation $ Utility $ Total Project $ Permitting $ F2 $111.2 $0.47 $11.12 $1.11 $1.00 $125.0 Exit 14/15 * F3 $148.1 $0.47 $14.81 $1.48 $1.00 $165.9 Exit 14/15 +$40.9 F3 with * Railroad $153.2 $5.09 $15.32 $1.53 $10.00 $185.1 Exit 14/15 +$60.1 Relocation *Does not include utility impacts/relocations on Loudon Road. Pedestrian Bridge (Construction Only) $12M - $30M

  29. Open Discussion

  30. Schedule • Final Environmental Document – Summer 2019 • Final Design / Right of Way Acquisition – 2019 to 2023 • Construction – Begin 2024 with current funding • Completion – 2033 or sooner

  31. Questions www.i93bowconcord.com

Recommend


More recommend