ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY - PowerPoint PPT Presentation

ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY Phase II Lisa Chow Project Manager 1 Construction of a two-story, 66,000 square foot operations and maintenance facility for the diesel-electric hybrid articulated buses. 2


  1. ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY Phase II Lisa Chow Project Manager 1

  2. Construction of a two-story, 66,000 square foot operations and maintenance facility for the diesel-electric hybrid articulated buses. 2

  3. Progress: • Perform utility relocation • Drive piles for the north and south buildings • Began erecting steel for south building Next Steps: • Continue with pile cap and grade beam, and electrical pullbox installation and erection of steel structure. 3

  4. Pile Driving 4

  5. General Excavation 5

  6. Pile Installation 6

  7. Pile Cap Excavation 7

  8. Electrical Pullbox Installation 8

  9. Steel Erection 9