half year 2015 results
play

Half Year 2015 results 19 August 2015 Main pipe Satellite pipe The - PowerPoint PPT Presentation

Half Year 2015 results 19 August 2015 Main pipe Satellite pipe The Leteng mine - Lesotho Disclaimer 2 No statement in this presentation is intended as a profit forecast or profit The following presentations are confidential and are being


  1. Half Year 2015 results 19 August 2015 Main pipe Satellite pipe The Letšeng mine - Lesotho

  2. Disclaimer 2 No statement in this presentation is intended as a profit forecast or profit The following presentations are confidential and are being made only to, and are estimate and no statement in the presentation should be interpreted to mean that only directed at, persons to whom such presentations may lawfully be earning per share for the current or future financial years would necessarily match communicated (“relevant persons”) . Any person who is not a relevant person or exceed the historical published earnings. The presentations also contain certain should not act or rely on these presentations or any of their contents. non-IFRS financial information. The Group’s management believes these measures Information in the following presentations relating to the price at which relevant provide valuable additional information in understanding the performance of the investments have been bought or sold in the past or the yield on such Group or the Group’s businesses because they provide measures used by the Group investments cannot be relied upon as a guide to the future performance of such to assess performance. However, this additional information presented is not investments. These presentations do not constitute an offering of securities or uniformly defined by all companies, including those in the Group’s industry. otherwise constitute an invitation or inducement to any person to underwrite, Accordingly, it may not be comparable with similarly titled measures and subscribe for or otherwise acquire securities in any company within the Group. disclosures by other companies. Neither this documentation nor the fact of its distribution nor the making of the Additionally, although these measures are important in the management of the presentation constitutes a recommendation regarding any securities. This business, they should not be viewed in isolation or as replacements for or presentation if for information purposes only. alternatives to, but rather as complementary to, the comparable IFRS measures such as revenue and other items reported in the consolidated financial The presentations contain forward-looking statements which are subject to risk statements. and uncertainties because they relate to future events. These forward-looking statements include, without limitation, statements in relation to the Group’s The distribution of this presentation or any information contained in it may be projected growth opportunities. Some of the factors which may cause actual restricted by law in certain jurisdictions, and any person into whose possession results to differ from these forward-looking statements are discussed in certain any document containing this presentation or any part of it comes should inform slides of the presentation and others can be found by referring to the themselves about, and observe such restrictions. information contained under the heading “Principle risks and uncertainties” in “The Strategic Report” in our Annual Report for the year ended 2014. The Information in this presentation is correct as at 18 August 2015 Annual Report can be found on our website (www.gemdiamonds.com).

  3. Agenda 3 Half Year 2015 highlights  Operations  HSSE  Sales, marketing and manufacturing  Financial results  Diamond market  Outlook 

  4. Half Year 2015 highlights 4 REVENUE UNDERLYING EBITDA US$118 million US$46 million 80 200 63 149 60 150 122 USD Millions USD Millions 118 46 116 44 41 97 40 33 100 20 50 0 0 H1 2013 H2 2013 H1 2014 H2 2014 H1 2015 H1 2013 H2 2013 H1 2014 H2 2014 H1 2015 BASIC EPS CASH GENERATED BY OPERATIONS 10.69 US cents US$71 million 18 100 86 15.30 16 80 14 71 69 67 10.69 12 USD Millions 9.76 US Cents 9.15 60 10 46 8 6.23 40 6 4 20 2 0 0 H1 2013 H2 2013 H1 2014 H2 2014 H1 2015 H1 2013 H2 2013 H1 2014 H2 2014 H1 2015

  5. Operations Alan Ashworth The Letšeng mine – Satellite and Main pipes The Ghaghoo mine – processing plant

  6. Letšeng operational overview Alan Ashworth Letšeng’s new Coarse Recovery Plant

  7. Letšeng operational overview 7 Waste tonnes mined Strong operational performance  15 (millions) 11.4 10.0 Production targets achieved 9.9 9.9  9.2 10 19 day shutdown for Plant 2 Phase 1 implementation*  5 Continual improvements : 0  H1 2013 H2 2013 H1 2014 H2 2014 H1 2015 Improved blasting technique  Ore treated (millions) 4.0 3.2 Larger mining fleet 3.2 3.1* 3.2  3.0 3.0 Cost efficiencies  2.0 Power back up capacity 1.0  0.0 H1 2013 H2 2013 H1 2014 H2 2014 H1 2015 Carats recovered '000s 55 60 54 53 50* 42 40 20 - H1 2013 H2 2013 H1 2014 H2 2014 H1 2015

  8. Letšeng operational overview 8 Optimised Life of Mine plan  Increased Satellite contribution - (1.65 mt in 2015; 2.0 mt from 2020 to 2031)  Optimal waste profile – (peak of 36 mtpa in 2024)  Steeper slope angles (resulting in less waste)  Improved NPV  Optimised Life of Mine plan: Optimised Life of Mine plan: tonnes treated and carats recovered profile waste profile 8 120 40 Tonnes treated and waste mined - millions 7 35 100 Waste Tonnes mined - millions 6 Carats recovered ‘000s 30 80 5 25 4 60 20 3 15 40 2 10 20 1 5 0 0 0 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 Main pit waste Satellite pit waste Satellite pipe Main pipe Carats recovered

  9. Letšeng operational overview 9 Frequency of +100 carat recoveries  3 12 Letšeng +100 carat diamonds 10 2 8 +100 carats per tender +100 carats annually 6 1 4 2 0 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 2011 2012 2013 2014 2015 +100 ct diamonds per tender 12 month rolling frequency of +100cts

  10. Letšeng project update 10 Coarse Recovery Plant Plant 2 Phase 1 upgrade Capital - Maloti 140.0m (US$11.7m) Capital - Maloti 50.0m (US$4.3m)   Optimising treatment of high value, coarse Additional capacity of 250ktpa   fraction Delivered on time and within budget  Commissioning commenced  Project payback c.13 months  First recovery – 52ct Type IIa  Security improvements; full body personnel X-ray  Delivered on time and within budget 

  11. Ghaghoo operational overview Alan Ashworth Processing plant, sort house and tailings dump at Ghaghoo

  12. Ghaghoo - Progress 12 35 283 carats recovered in H1 2015  132 125 ore tonnes treated in H1 2015  Average grade 29 cpht for May and June (above 27  cpht reserve grade) 5 production tunnels completed  Slot tunnel completed between Tunnels 1 and 5  allowing retreat stoping to commence 825 metres developed in H1 2015 out of a total of Processing plant at Ghaghoo  3 610 metres to date First sale of 10 096 carats, achieved US$210 per  carat Second sale of 29 891 carats sold in July for US$165  per carat 13 diamonds >10 carats each recovered, the largest  being a 48 carat diamond Underground operations at Ghaghoo

  13. Ghaghoo - Grade 13 Proving up of grade achieved with potential upside Grade improved to 29 cpht, above reserve grade  of 27 cpht Mining mainly conducted in lower grade portion  of VKSE with dilution near margins – upside Ghaghoo Grade Performance Diluted marginal ore 40 35 30 Higher grade 25 ore 20 15 10 5 0 1-Feb-15 3-Mar-15 2-Apr-15 2-May-15 1-Jun-15 Actual Grade Expected Grade 30 day rolling average

  14. Ghaghoo – Diamond price 14 Proving up diamond price Sale 1 achieved US$210 per carat  Sale 2 achieved US$165 per carat  Ghaghoo diamond prices Ghaghoo diamond size frequency Diamonds per category interval Price per category US$/carat +5 +7 +9 +11 3grn 4grn 5grn 6grn 8grn 10grn 3¢ 4¢ 5¢ 6¢ 7¢ 8¢ 9¢ 10¢ 10.8¢ +15¢ +20¢ +30¢ +45¢ +5 +7 +9 +11 3grn 4grn 5grn 6grn 8grn 10grn 3¢ 4¢ 5¢ 6¢ 7¢ 8¢ 9¢ 10¢ 10.8¢ +15¢ +20¢ +30¢ +45¢ Actual Price Curve Expected Price Curve Actual Size Frequency Expected Size Frequency

  15. Ghaghoo – Milling technology 15 Ghaghoo ore suitable for milling  Successful liberation of fine diamonds  Mill product to DMS 25% of headfeed  Very low diamond damage  Ghaghoo’s autogenous mill Successful liberation of fine diamonds through the mill

  16. Ghaghoo - Production ramping up 16 Ore tonnes treated 80 000 70 000 Tonnes per month 60 000 50 000 40 000 Actuals 30 000 Forecast 20 000 10 000 - Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Production ramping up  Challenging water and ground conditions  Development targeting flexibility and knowledge  Developing access to VK Main and CK kimberlite ore  -representative sampling required across phases

  17. HSSE Alan Ashworth Re- vegetation rehabilitation trials at Letšeng

Recommend


More recommend