d all e picture and “send to back” Gold Fields Australia – Delivery, Exploration, Growth STUART MATHEWS Executive Vice President: Australasia 7 August 2018 – Diggers & Dealers Presentation 2018
Certain statements in this document constitute “ forward looking statements ” within the meaning of Section 27A of the US Securities Act of 1933 and Section 21E of the US Securities Exchange Act of 1934. In particular, the forward looking statements in this document include among others those relating to the Damang Exploration Target Statement; the Far Southeast Exploration Target Statement; commodity prices; demand for gold and other metals and minerals; interest rate expectations; exploration and production costs; levels of expected production; Gold Fields ’ growth pipeline; levels and expected benefits of current and planned capital expenditures; future reserve, resource and other mineralisation levels; and the extent of cost efficiencies and savings to be achieved. Such forward looking statements involve known and unknown risks, uncertainties and other important factors that could cause the actual results, performance or achievements of the company to be materially different from the future results, performance or achievements expressed or implied by such forward looking statements. Such risks, uncertainties and other important factors include among others: economic, business and political conditions in South Africa, Ghana, Australia, Peru and elsewhere; the ability to achieve anticipated efficiencies and other cost savings in connection with past and future acquisitions, exploration and development activities; decreases in the market price of gold and/or copper; hazards associated with underground and surface gold mining; labour disruptions; availability terms and deployment of capital or credit; changes in government regulations, particularly taxation and environmental regulations; and new legislation affecting mining and mineral rights; changes in exchange rates; currency devaluations; the availability and cost of raw and finished materials; the cost of energy and water; inflation and other macro-economic factors, industrial action, temporary stoppages of mines for safety and unplanned maintenance reasons; and the impact of the AIDS and other occupational health risks experienced by Gold Fields ’ employees. These forward looking statements speak only as of the date of this document. Gold Fields undertakes no obligation to update publicly or release any revisions to these forward looking statements to reflect events or circumstances after the date of this document or to reflect the occurrence of unanticipated events. Diggers & Dealers, 7 August 2018 – Stuart Mathews 2
Global Footprint 2017 Performance Gold Fields Group Mines: 7 Projects: 2 Att. production: 2,160koz AIC: US$1,088/oz Net cash flow*: US$441m West Africa region Mines : Tarkwa and Damang Att. production: 639koz AIC: US$1,119/oz Net cash flow*: US$179m inflow Australia region Americas region Mines : St Ives, Granny Smith and Agnew Mine : Cerro Corona (Peru) Att. production: 307koz (Au eq) Att. production: 935koz AIC: US$673/eq oz South Africa region AIC: US$948/oz Net cash flow: US$117m Mine : South Deep Net cash flow: Project : Salares Norte (Chile) Att. production: 281koz US$187m (A$243M) AIC: US$1,400/oz Net cash flow*: US$43m inflow outflow Project : Gruyere *Excludes Damang project capital of US$115m and South Deep project capital of US$17m 3
Australia Invicible Open Pit Regional Summary St. Ives Mine ● 17 years in Western Australia ● 3 rd largest gold miner in Australia (2 nd in WA) ● Underground (80%) & Open Pit Mining (20%) ● 43% of Group gold production ● 42% of Net Cash Flow ● Approx. 2200 employees and contractors ● +A$1bn contribution to Australia employees, suppliers & contractors annually ● A$834M Total Exploration investment spend since 2002 ● Delivering replacement or depletion of Wallaby Underground reserves & growth in the region Granny Smith Mine Diggers & Dealers, 7 August 2018 – Stuart Mathews 4
Gold Fields in Australia – 2017 Performance • Production: 935koz • AIC: A$1,238/oz Gold Fields (US$948/oz) Australia • Net cash flow: (Divested US$187m (A$243m) Oct’17) • Production: 364koz • AIC: A$1,198/oz St Ives (US$922/oz) • Net cash flow: US$83m (A$108m) • Production: 290koz • AIC: A$1,171/oz Granny Smith (US$982/oz) • Net cash flow: US$72m (A$93m) • Production: 241koz • AIC: A$1,276/oz Agnew (US$971/oz) • Net cash flow: US$51m (A$64m) • Construction & development Gruyere • First gold in Q2 2019 50:50 Joint Venture • 270koz Ozs per year (135koz Gold Fields Gold Fields share) Gold Road • +13 years reserves Resources • Gold Fields – Manager Have exceeded Gold Production & AIC Guidance last 5 years 5
Historical Gold Production Profile - Australia Australian Gold Production Ozs Acquisition of 1,000,000 Granny Smith, Lawlers, Darlot Oct’13 800,000 600,000 400,000 200,000 Darlot Granny Smith Agnew - 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 St Ives Gold Fields Gold Production to exceed 1 Moz per annum from mid-2019 Gruyere Production contribution Consistency of Production Delivery for 17 Years Gold Fields – Delivery & Growth 6
Exploration in Australia Region Gold Fields - Reinvesting for the future, Diggers and Dealers, August 2017
Exploration Expenditure Sustained & Growing Investment Exploration Expenditure – Australia 120.0 Gold downturn 100.0 Company restructure Granny Smith, Lawlers, Darlot acquisition Darlot 80.0 Divestment St. Ives Mill 60.0 Upgrade 40.0 4 Mines 2 MInes Agnew Agnew 20.0 St. Ives St. Ives Granny Smith - 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Largest Gold Exploration Spend in Australia – A$90m – A$100m last 4 years Gold Fields – Delivery & Growth 8
Exploration Investment History Australia Context A$76.6M Average A$43M 2013 - 2017 Average 4 Mines A$36M 2005 - 2012 (St. Ives, Agnew, Granny Average Smith, Darlot) 2 Mines 1x Development Project 2002 - 2004 A$28M Multi-mine site at St. Ives Increased mill capacity 2017 2017 – A$9 A$94M 2 Mines Increased production Initial Exploration 2018 – A$8 2018 A$85M (P (Pla lan) UG & open pit mining Greater Ounces Investment Year 1 New target generation Invincible discovery 2 Mines – St. Ives, Agnew Extensional Exploration Delivering Resource & Reserve Growth Diggers & Dealers, 7 August 2018 – Stuart Mathews 9
St Ives Gold Mine – Exploration Focus 2018 A$37M Exploration Budget 2018 20km 10 Diggers & Dealers, 7 August 2018 – Stuart Mathews
St Ives – Exploration and Growth Invincible Camp Exploration (2018) Target Description : Brecciated mudstone hosted mineralisation Potential: +2Moz Additional Exploration: Extensional Exploration: Broad step out drilling to identify the scale of the Invincible ore Extend Invincible Deeps up dip and plunge from current system and confirm favourable host rock, alteration and position, extend Invincible South further south along strike. mineralisation. Underground: Open Pits: Drill adjacent to existing UG mine design to expand resource, Extend Stage 6 beneath the current pit floor design. drill plan over 2 year period. Invincible Invincible South Drake Fenton open Open EXTN 500m 11 Diggers & Dealers, 7 August 2018 – Stuart Mathews
St Ives – Exploration 2018 Invincible Deeps Extensions 8.5m @ 3.80 g/t Au (856m) 10.0m @ 8.40 g/t Au (714m) 4.1m @ 4.05 g/t Au (860m) 12.8m @ 11.56 g/t Au (919m) GM Open Intercept 4.1m @ 4.54 g/t Au (977m) Planned Drilling 100m Completed Drilling Currently Drilling Diggers & Dealers, 7 August 2018 – Stuart Mathews 12
St Ives – Exploration 2018 Invincible South – Stage 4 Drilling # of Holes Drilled/planned: 15 (18/32) Target Description : Sheared mudstone hosted mineralisation Metres (drilled/planned): 6,522 (8,842/14,338) Potential: >500Koz Assays (from holes) : 11 (14/32) 12.6m @ 6.25g/t Au (237m) 15.4m @ 3.34g/t Au (328m) 14.0m @ 7.98g/t Au (427m)* 2.0 m @ 3.90g/t Au (326m)* 12.0m @ 7.42g/t Au (332m)* 5.6m @ 7.00g/t Au (427m)* 1.2m @ 3.18g/t Au (374m) 5.5m @ 8.57g/t Au (468m)* 6.8m @ 45.79g/t Au (374m) GM Intercept 4.1m @ 2.67g/t Au (434m) 2.0m @ 1.45g/t Au (438m) Open Planned Drilling 100m Completed Drilling Currently Drilling * denotes intersection partially/all in footwall BFA 13 Diggers & Dealers, 7 August 2018 – Stuart Mathews
Agnew Gold Mine A$25M Exploration Budget 2018 CM Waroonga North MR Potential 500 koz New Holland South Potential 50 koz Sheba South UG FBH South Potential 100 koz Potential 50 koz VV NH WR MC Redeemer North/Zone 2 RD Potential >1 Moz LV FL GE CR CR DG SV Legend: Extensional Program Additional Program Diggers & Dealers, 7 August 2018 – Stuart Mathews 14
Agnew Gold Mine Exploration & Growth at Waroonga – focus areas Context Multiple narrow lode ore bodies (1-5 metres) Limited strike extents Large vertical extent (steeply dipping) Coarse gold 3 years reserves for 35 years Open Open Open Open Mined since 1993 – Right Investment level maintains life and production profile Diggers & Dealers, 7 August 2018 – Stuart Mathews 15